Quantifying the Impact of I/D Contracting on the Time/Cost Trade-Off for Pavement Rehabilitation Projects

被引:0
|
作者
Ibrahim, Mohamed [1 ]
Orabi, Wallied [2 ]
机构
[1] Florida Int Univ, Dept Civil & Environm Engn, Miami, FL 33174 USA
[2] Florida Int Univ, OHL Sch Construct, Miami, FL 33174 USA
关键词
HIGHWAY CONSTRUCTION;
D O I
暂无
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The current deteriorating state of the highway system in the Unites States is shifting the balance of highway construction projects towards maintenance and rehabilitation works on the expense of new construction. Hence, state highway agencies (SHAs) are now challenged to complete a substantial scope of highway rehabilitation work while controlling and reducing the negative impacts on the travelling public. Therefore, alternative contracting methods that are aimed at reducing highway projects' durations, such as the incentive/disincentive (I/D) method, are gaining popularity among SHAs. For instance, the value of the ID assigned in a highway project has a significant effect on expediting the completion of the project while saving tax dollars. However, the current practice of estimating and assigning the ID value is not adequate and is frequently either overestimated or underestimated. This paper presents the development of a new model to accurately estimate ID value in highway rehabilitation projects based on the desired level of duration reduction. The model quantifies the impact of the I/D contracting method on the trade-off between time and cost of highway rehabilitation projects which should prove useful to SHAs in determining and assigning values of ID that are proper for the required project duration reduction together with the likelihood of achieving it.
引用
收藏
页码:679 / 688
页数:10
相关论文
共 50 条
  • [1] A time - Cost trade-off algorithm for nonserial linear projects
    Senouci, AB
    Eldin, NN
    CANADIAN JOURNAL OF CIVIL ENGINEERING, 1996, 23 (01) : 134 - 149
  • [2] Factors affecting time and cost trade-off in multiple construction projects
    Hasan, Musaab Falih
    Mohammed, Sawsan Rasheed
    ARCHIVES OF CIVIL ENGINEERING, 2022, 68 (02) : 549 - 561
  • [3] A TRADE-OFF BETWEEN TIME AND COST IN SCHEDULING REPETITIVE CONSTRUCTION PROJECTS
    Zhang, Lihui
    Zou, Xin
    Qi, Jianxun
    JOURNAL OF INDUSTRIAL AND MANAGEMENT OPTIMIZATION, 2015, 11 (04) : 1423 - 1434
  • [4] Time-cost-quality trade-off analysis for planning construction projects
    Wang, Tianqi
    Abdallah, Moatassem
    Clevenger, Caroline
    Monghasemi, Shahryar
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2021, 28 (01) : 82 - 100
  • [5] Automated trade-off between time and cost in planning repetitive construction projects
    Hyari, Khalied Hesham
    El-Rayes, Khaled
    El-Mashaleh, Mohammad
    CONSTRUCTION MANAGEMENT AND ECONOMICS, 2009, 27 (08) : 749 - 761
  • [6] Solving Fuzzy Time–Cost Trade-Off in Construction Projects Using Linear Programming
    Elkalla I.
    Elbeltagi E.
    El Shikh M.
    Journal of The Institution of Engineers (India): Series A, 2021, 102 (1) : 267 - 278
  • [7] Development of time–cost trade-off optimization model for construction projects with MOPSO technique
    Agarwal A.K.
    Chauhan S.S.
    Sharma K.
    Sethi K.C.
    Asian Journal of Civil Engineering, 2024, 25 (6) : 4529 - 4539
  • [8] Bi-Objective Scheduling Optimization for Discrete Time/Cost Trade-Off in Projects
    Li, Hongbo
    Xu, Zhe
    Wei, Wenchao
    SUSTAINABILITY, 2018, 10 (08)
  • [9] Optimization of environmental impacts of construction projects: a time–cost–quality trade-off approach
    S. A. Banihashemi
    Mohammad Khalilzadeh
    A. Shahraki
    M. Rostami Malkhalifeh
    S. S. R. Ahmadizadeh
    International Journal of Environmental Science and Technology, 2021, 18 : 631 - 646
  • [10] TIME-COST TRADE-OFF FOR AIRLINERS
    HARTLEY, K
    CORCORAN, W
    JOURNAL OF INDUSTRIAL ECONOMICS, 1978, 26 (03): : 209 - 222