Integrating Quality and Safety in Construction Scheduling Time-Cost Trade-Off Model

被引:29
|
作者
Panwar, Abhilasha [1 ]
Jha, Kumar Neeraj [1 ]
机构
[1] Indian Inst Technol Delhi, Dept Civil Engn, Delhi 110016, India
关键词
Trade-off; Time; Cost; Coordinate plot; Many-objectives; Sensitivity analysis; MULTIOBJECTIVE EVOLUTIONARY ALGORITHMS; PARTICLE SWARM OPTIMIZATION; PROJECT-MANAGEMENT; DECISION-MAKING; DISCRETE-TIME;
D O I
10.1061/(ASCE)CO.1943-7862.0001979
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Quality and safety are important and are the leading concerns in a construction project. Planning a project without properly incorporating these two performance parameters propagates multifarious defects and accidents in construction projects and this ultimately leads to cost overrun and time delay. In order to deal with quality and safety at the planning stage (along with time and cost), a decision-making model considering time, cost, quality, and safety (TCQS) is developed on the basis of a many-objective evolutionary algorithm (nondominated sorting genetic algorithm III) and presented in this study. An example is illustrated to demonstrate the capabilities of the proposed model for generating and visualizing the optimal trade-off among TCQS. The proposed model shows better results compared to earlier reported scheduling models. Additionally, the study has also conducted a correlation analysis to identify the interrelationship, if any, among the TCQS components. Furthermore, the solution obtained from the model was put through sensitivity analysis. The developed model was also checked for two large-scale scheduling cases and found to work efficiently. The inclusion of objectives like quality and safety will provide a holistic scheduling model for the construction professionals. This study is expected to provide an alternative planning strategy and assist project managers in selecting optimal TCQS trade-offs while constructing a facility.
引用
收藏
页数:15
相关论文
共 50 条
  • [41] Systematic solution procedure for time-cost trade-off problems
    Udosen, Udosen J.
    INTERNATIONAL JOURNAL OF INDUSTRIAL ENGINEERING-THEORY APPLICATIONS AND PRACTICE, 2007, 14 (02): : 158 - 168
  • [42] An evolutionary stochastic discrete time-cost trade-off method
    Hussein, Bahaa
    Moselhi, Osama
    CANADIAN JOURNAL OF CIVIL ENGINEERING, 2019, 46 (07) : 581 - 600
  • [43] New fuzzy models for time-cost trade-off problem
    Ke, Hua
    Ma, Weimin
    Gao, Xin
    Xu, Weihua
    FUZZY OPTIMIZATION AND DECISION MAKING, 2010, 9 (02) : 219 - 231
  • [44] A New Model for Solving Time-Cost-Quality Trade-Off Problems in Construction
    Fu, Fang
    Zhang, Tao
    PLOS ONE, 2016, 11 (12):
  • [45] Time-Cost Trade-off Optimization of Construction Projects using Teaching Learning Based Optimization
    Vedat Toğan
    M. Azim Eirgash
    KSCE Journal of Civil Engineering, 2019, 23 : 10 - 20
  • [46] Improvement Optimization Algorithm for Stochastic Discrete Time-cost Trade-off Problems of Construction Projects
    Wang J.
    Tang J.
    Zhou Z.
    Han C.
    Hunan Daxue Xuebao/Journal of Hunan University Natural Sciences, 2023, 50 (07): : 229 - 238
  • [47] Time-cost trade-off optimization model for retrofitting planning projects using MOGA
    Patil A.S.
    Agarwal A.K.
    Sharma K.
    Trivedi M.K.
    Asian Journal of Civil Engineering, 2024, 25 (5) : 3823 - 3833
  • [48] A contingency approach for time-cost trade-off in construction projects based on machine learning techniques
    Wang, Peipei
    Wang, Kun
    Huang, Yunhan
    Fenn, Peter
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2024, 31 (11) : 4677 - 4695
  • [49] Novel Hybrid Method in Time-Cost Trade-Off for Resource-Constrained Construction Projects
    Albayrak, Gulcag
    IRANIAN JOURNAL OF SCIENCE AND TECHNOLOGY-TRANSACTIONS OF CIVIL ENGINEERING, 2020, 44 (04) : 1295 - 1307
  • [50] THE TIME-COST TRADE-OFF ANALYSIS IN CONSTRUCTION PROJECT USING COMPUTER SIMULATION AND INTERACTIVE PROCEDURE
    Blaszczyk, Tomasz
    Nowak, Maciej
    TECHNOLOGICAL AND ECONOMIC DEVELOPMENT OF ECONOMY, 2009, 15 (04) : 523 - 539