Integrating Quality and Safety in Construction Scheduling Time-Cost Trade-Off Model

被引:29
|
作者
Panwar, Abhilasha [1 ]
Jha, Kumar Neeraj [1 ]
机构
[1] Indian Inst Technol Delhi, Dept Civil Engn, Delhi 110016, India
关键词
Trade-off; Time; Cost; Coordinate plot; Many-objectives; Sensitivity analysis; MULTIOBJECTIVE EVOLUTIONARY ALGORITHMS; PARTICLE SWARM OPTIMIZATION; PROJECT-MANAGEMENT; DECISION-MAKING; DISCRETE-TIME;
D O I
10.1061/(ASCE)CO.1943-7862.0001979
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Quality and safety are important and are the leading concerns in a construction project. Planning a project without properly incorporating these two performance parameters propagates multifarious defects and accidents in construction projects and this ultimately leads to cost overrun and time delay. In order to deal with quality and safety at the planning stage (along with time and cost), a decision-making model considering time, cost, quality, and safety (TCQS) is developed on the basis of a many-objective evolutionary algorithm (nondominated sorting genetic algorithm III) and presented in this study. An example is illustrated to demonstrate the capabilities of the proposed model for generating and visualizing the optimal trade-off among TCQS. The proposed model shows better results compared to earlier reported scheduling models. Additionally, the study has also conducted a correlation analysis to identify the interrelationship, if any, among the TCQS components. Furthermore, the solution obtained from the model was put through sensitivity analysis. The developed model was also checked for two large-scale scheduling cases and found to work efficiently. The inclusion of objectives like quality and safety will provide a holistic scheduling model for the construction professionals. This study is expected to provide an alternative planning strategy and assist project managers in selecting optimal TCQS trade-offs while constructing a facility.
引用
收藏
页数:15
相关论文
共 50 条
  • [1] TIME-COST TRADE-OFF SCHEDULING UNDER CONSTRUCTION LABOR RESOURCE CONSTRAINTS
    Benjaoran, Vacharapoom
    Sae-Tae, Numpheungk
    SURANAREE JOURNAL OF SCIENCE AND TECHNOLOGY, 2011, 18 (01): : 29 - 39
  • [2] Stochastic construction time-cost trade-off analysis
    Feng, CW
    Liu, L
    Burns, SA
    JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2000, 14 (02) : 117 - 126
  • [3] A Fuzzy Random Time-Cost Trade-off Model
    Ke, Hua
    Ma, Weimin
    PROCEEDINGS OF THE EIGHTH INTERNATIONAL CONFERENCE ON INFORMATION AND MANAGEMENT SCIENCES, 2009, 8 : 633 - 637
  • [4] TIME-COST TRADE-OFF FOR AIRLINERS
    HARTLEY, K
    CORCORAN, W
    JOURNAL OF INDUSTRIAL ECONOMICS, 1978, 26 (03): : 209 - 222
  • [5] Multi-objective time-cost trade-off optimization for the construction scheduling with Rao algorithms
    Yilmaz, Mehmet
    Dede, Tayfun
    STRUCTURES, 2023, 48 : 798 - 808
  • [6] Project time-cost trade-off scheduling: a hybrid optimization approach
    Mokhtari, Hadi
    Aghaie, Abdollah
    Rahimi, Javad
    Mozdgir, Ashkan
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2010, 50 (5-8): : 811 - 822
  • [7] Multi-project Scheduling: Multicriteria Time-cost Trade-off Problem
    Klevanskiy, N. N.
    Tkachev, S. I.
    Voloshchouk, L. A.
    PROCEEDINGS OF THE 13TH INTERNATIONAL SYMPOSIUM INTELLIGENT SYSTEMS 2018 (INTELS'18), 2019, 150 : 237 - 243
  • [8] A crashing-based time-cost trade-off model considering quality cost and contract clauses
    Akin, Firat Dogu
    Polat, Gul
    Turkoglu, Harun
    Damci, Atilla
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2021, 23 (06) : 954 - 963
  • [9] Time-cost trade-off of construction project based on ant colony algorithm
    Xiong, Ying
    Kuang, Ya-Ping
    Xitong Gongcheng Lilun yu Shijian/System Engineering Theory and Practice, 2007, 27 (03): : 105 - 111
  • [10] Using genetic algorithms to solve construction time-cost trade-off problems
    Feng, CW
    Liu, LA
    Burns, SA
    JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 1997, 11 (03) : 184 - 189