A contingency approach for time-cost trade-off in construction projects based on machine learning techniques

被引:3
|
作者
Wang, Peipei [1 ]
Wang, Kun [2 ]
Huang, Yunhan [1 ]
Fenn, Peter [2 ]
机构
[1] Jiangsu Ocean Univ, Sch Civil & Ocean Engn, Lianyungang, Peoples R China
[2] Univ Manchester, Sch Engn, Dept Engn Management, Manchester, England
关键词
Construction; Novel model; Project management; Risk management; CRITICAL SUCCESS FACTORS; PUBLIC-PRIVATE PARTNERSHIPS; DELAY FACTORS; OVERRUN; PERFORMANCE; MANAGEMENT; ERRORS; SOLVE; MODEL;
D O I
10.1108/ECAM-11-2022-1104
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
PurposeTime-cost trade-off is normal conduct in construction projects when projects are expectedly late for delivery. Existing research on time-cost trade-off strategic management mostly focused on the technical calculation towards the optimal combination of activities to be accelerated, while the managerial aspects are mostly neglected. This paper aims to understand the managerial efforts necessary to prepare construction projects ready for an upcoming trade-off implementation.Design/methodology/approachA preliminary list of critical factors was first identified from the literature and verified by a Delphi survey. Quantitative data was then collected by a questionnaire survey to first shortlist the preliminary factors and quantify the predictive model with different machine learning algorithms, i.e. k-nearest neighbours (kNN), radial basis function (RBF), multiplayer perceptron (MLP), multinomial logistic regression (MLR), naive Bayes classifier (NBC) and Bayesian belief networks (BBNs).FindingsThe model's independent variable importance ranking revealed that the top challenges faced were the realism of contractual obligation, contractor planning and control and client management and monitoring. Among the tested machine learning algorithms, multilayer perceptron was demonstrated to be the most suitable in this case. This model accuracy reached 96.5% with the training dataset and 95.6% with an independent test dataset and could be used as the contingency approach for time-cost trade-offs.Originality/valueThe identified factor list contributed to the theoretical explanation of the failed implementation in general and practical managerial improvement to better avoid such failure. In addition, the established predictive model provided an ad-hoc early warning and diagnostic tool to better ensure time-cost implementation success.
引用
收藏
页码:4677 / 4695
页数:19
相关论文
共 50 条
  • [31] Time-cost trade-off analysis of a priority based assignment problem
    Kaur, Prabhjot
    Dahiya, Kalpana
    Verma, Vanita
    OPSEARCH, 2021, 58 (02) : 448 - 482
  • [32] Time-cost trade-off analysis of a priority based assignment problem
    Prabhjot Kaur
    Kalpana Dahiya
    Vanita Verma
    OPSEARCH, 2021, 58 : 448 - 482
  • [33] Factors affecting time and cost trade-off in multiple construction projects
    Hasan, Musaab Falih
    Mohammed, Sawsan Rasheed
    ARCHIVES OF CIVIL ENGINEERING, 2022, 68 (02) : 549 - 561
  • [34] A TRADE-OFF BETWEEN TIME AND COST IN SCHEDULING REPETITIVE CONSTRUCTION PROJECTS
    Zhang, Lihui
    Zou, Xin
    Qi, Jianxun
    JOURNAL OF INDUSTRIAL AND MANAGEMENT OPTIMIZATION, 2015, 11 (04) : 1423 - 1434
  • [35] Mixed-Integer Linear Programming Approach for Scheduling Repetitive Projects with Time-Cost Trade-Off Consideration
    Zou, Xin
    Fang, Shu-Cherng
    Huang, Yuan-Sheng
    Zhang, Li-Hui
    JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2017, 31 (03)
  • [36] CONSTRUCTION TIME-COST TRADE-OFF ANALYSIS USING LP/IP HYBRID METHOD
    LIU, L
    BURNS, SA
    FENG, CW
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1995, 121 (04): : 446 - 454
  • [37] Using ant colony algorithm to solve construction time-cost trade-off problem
    College of Civil Engineering and Architecture, Zhejiang University, Hangzhou 310027, China
    不详
    Zhejiang Daxue Xuebao (Gongxue Ban), 2007, 1 (176-180):
  • [38] Optimization of environmental impacts of construction projects: a time-cost-quality trade-off approach
    Banihashemi, S. A.
    Khalilzadeh, Mohammad
    Shahraki, A.
    Malkhalifeh, M. Rostami
    Ahmadizadeh, S. S. R.
    INTERNATIONAL JOURNAL OF ENVIRONMENTAL SCIENCE AND TECHNOLOGY, 2021, 18 (03) : 631 - 646
  • [39] Construction time-cost trade-off analysis using ant colony optimization algorithm
    Kuang Ya-ping
    Xiong Ying
    PROCEEDINGS OF THE 2006 INTERNATIONAL CONFERENCE ON MANAGEMENT SCIENCE & ENGINEERING (13TH), VOLS 1-3, 2006, : 2039 - 2044
  • [40] TIME-COST TRADE-OFF AMONG RELATED ACTIVITIES - CLOSURE
    REDA, R
    CARR, RI
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1991, 117 (02): : 375 - 376