Optimizing of Discrete Time- cost Trade-off Problem in Construction Projects Using Advanced Jaya Algorithm

被引:2
|
作者
Albayrak, Gulcag [1 ]
机构
[1] Eskisehir Osmangazi Univ, Dept Civil Engn, Fac Engn & Architecture, Meselik Campus, TR-26040 Eskisehir, Turkiye
来源
关键词
construction management; Jaya algorithm; metaheuristic method; optimization; multi-objective modelling; ROBUST OPTIMIZATION; CASH FLOW; SEARCH;
D O I
10.3311/PPci.22156
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
This paper proposes a novel algorithm to optimize the discrete time-cost trade-off problem (DTCTP) in construction projects. As DTCTP is assumed NP-hard, the new metaheuristic models are investigated to contribute for decision-making of project managers. DTCTP can be modelled as multi-mode to represent real-life problems more practical. According to the model, the project activities have at least two or more durations and cost alternative modes. For solving this problem effectively, a novel optimization metaheuristic method named Advanced Jaya Algorithm (A-JA) is proposed, which is generated from Jaya Algorithm (JA). The benchmark function tests are applied to verify the model with other well-known metaheuristic methods. The key weakness of the base algorithm JA is that, it has unstable solution accuracy and low likelihood of escaping local optimums. According to the results, A-JA considerably improves these areas. Two case studies of DTCTP are carried out after verification to demonstrate the effectiveness and efficiency of the proposed algorithm in comparison with JA and three well-known methods. The results of A-JA are found to be more powerful than the base algorithm JA and the benchmark algorithms. The proposed method achieves the Pareto fronts to help decision makers to make trade-off between the objectives and choose the optimum solution considering on their preference.
引用
收藏
页码:806 / 818
页数:13
相关论文
共 50 条
  • [1] Improvement Optimization Algorithm for Stochastic Discrete Time-cost Trade-off Problems of Construction Projects
    Wang J.
    Tang J.
    Zhou Z.
    Han C.
    Hunan Daxue Xuebao/Journal of Hunan University Natural Sciences, 2023, 50 (07): : 229 - 238
  • [2] On the discrete time, cost and quality trade-off problem
    Tareghian, Hamed R.
    Taheri, Seyyed Hassan
    APPLIED MATHEMATICS AND COMPUTATION, 2006, 181 (02) : 1305 - 1312
  • [3] A hybrid genetic algorithm for the discrete time-cost trade-off problem
    Sonmez, Rifat
    Bettemir, Onder Halis
    EXPERT SYSTEMS WITH APPLICATIONS, 2012, 39 (13) : 11428 - 11434
  • [4] Using ant colony algorithm to solve construction time-cost trade-off problem
    College of Civil Engineering and Architecture, Zhejiang University, Hangzhou 310027, China
    不详
    Zhejiang Daxue Xuebao (Gongxue Ban), 2007, 1 (176-180):
  • [5] A time - Cost trade-off algorithm for nonserial linear projects
    Senouci, AB
    Eldin, NN
    CANADIAN JOURNAL OF CIVIL ENGINEERING, 1996, 23 (01) : 134 - 149
  • [6] Network analysis algorithm for the solution of discrete time-cost trade-off problem
    Önder Halis Bettemir
    M. Talat Birgönül
    KSCE Journal of Civil Engineering, 2017, 21 : 1047 - 1058
  • [7] Network Analysis Algorithm for the Solution of Discrete Time-Cost Trade-off Problem
    Bettemir, Onder Halis
    Birgonul, M. Talat
    KSCE JOURNAL OF CIVIL ENGINEERING, 2017, 21 (04) : 1047 - 1058
  • [8] Solving Fuzzy Time–Cost Trade-Off in Construction Projects Using Linear Programming
    Elkalla I.
    Elbeltagi E.
    El Shikh M.
    Journal of The Institution of Engineers (India): Series A, 2021, 102 (1) : 267 - 278
  • [9] Factors affecting time and cost trade-off in multiple construction projects
    Hasan, Musaab Falih
    Mohammed, Sawsan Rasheed
    ARCHIVES OF CIVIL ENGINEERING, 2022, 68 (02) : 549 - 561
  • [10] A TRADE-OFF BETWEEN TIME AND COST IN SCHEDULING REPETITIVE CONSTRUCTION PROJECTS
    Zhang, Lihui
    Zou, Xin
    Qi, Jianxun
    JOURNAL OF INDUSTRIAL AND MANAGEMENT OPTIMIZATION, 2015, 11 (04) : 1423 - 1434