Optimizing of Discrete Time- cost Trade-off Problem in Construction Projects Using Advanced Jaya Algorithm

被引:2
|
作者
Albayrak, Gulcag [1 ]
机构
[1] Eskisehir Osmangazi Univ, Dept Civil Engn, Fac Engn & Architecture, Meselik Campus, TR-26040 Eskisehir, Turkiye
来源
关键词
construction management; Jaya algorithm; metaheuristic method; optimization; multi-objective modelling; ROBUST OPTIMIZATION; CASH FLOW; SEARCH;
D O I
10.3311/PPci.22156
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
This paper proposes a novel algorithm to optimize the discrete time-cost trade-off problem (DTCTP) in construction projects. As DTCTP is assumed NP-hard, the new metaheuristic models are investigated to contribute for decision-making of project managers. DTCTP can be modelled as multi-mode to represent real-life problems more practical. According to the model, the project activities have at least two or more durations and cost alternative modes. For solving this problem effectively, a novel optimization metaheuristic method named Advanced Jaya Algorithm (A-JA) is proposed, which is generated from Jaya Algorithm (JA). The benchmark function tests are applied to verify the model with other well-known metaheuristic methods. The key weakness of the base algorithm JA is that, it has unstable solution accuracy and low likelihood of escaping local optimums. According to the results, A-JA considerably improves these areas. Two case studies of DTCTP are carried out after verification to demonstrate the effectiveness and efficiency of the proposed algorithm in comparison with JA and three well-known methods. The results of A-JA are found to be more powerful than the base algorithm JA and the benchmark algorithms. The proposed method achieves the Pareto fronts to help decision makers to make trade-off between the objectives and choose the optimum solution considering on their preference.
引用
收藏
页码:806 / 818
页数:13
相关论文
共 50 条
  • [21] Discrete time/cost trade-off problem: A decomposition-based solution algorithm for the budget version
    Hazir, Oencue
    Haouari, Mohamed
    Erel, Erdal
    COMPUTERS & OPERATIONS RESEARCH, 2010, 37 (04) : 649 - 655
  • [22] Time-cost-quality trade-off software by using simplified Genetic algorithm for typical-repetitive construction projects
    Abd El Razek, Refaat H.
    Diab, Ahmed M.
    Hafez, Sherif M.
    Aziz, Remon F.
    World Academy of Science, Engineering and Technology, 2010, 61 : 312 - 321
  • [23] Bi-Objective Scheduling Optimization for Discrete Time/Cost Trade-Off in Projects
    Li, Hongbo
    Xu, Zhe
    Wei, Wenchao
    SUSTAINABILITY, 2018, 10 (08)
  • [24] Optimal procedures for the discrete time cost trade-off problem in project networks
    Demeulemeester, EL
    Herroelen, WS
    Elmaghraby, SE
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1996, 88 (01) : 50 - 68
  • [25] Optimal procedures for the discrete time/cost trade-off problem in project networks
    Katholieke Universiteit Leuven, Leuven, Belgium
    Eur J Oper Res, 1 (50-68):
  • [26] Optimizing sustainable construction projects through LNSGA III: a time-cost-environmental impact trade-off approach
    Bohra P.
    Verma R.S.
    Asian Journal of Civil Engineering, 2024, 25 (5) : 4343 - 4354
  • [27] Multi-Mode Discrete Time-Cost-Environment Trade-Off Problem of Construction Systems for Large-Scale Hydroelectric Projects
    Zheng, Huan
    PROCEEDINGS OF THE NINTH INTERNATIONAL CONFERENCE ON MANAGEMENT SCIENCE AND ENGINEERING MANAGEMENT, 2015, 362 : 337 - 346
  • [28] Robust scheduling and robustness measures for the discrete time/cost trade-off problem
    Hazir, Oencue
    Haouari, Mohamed
    Erel, Erdal
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2010, 207 (02) : 633 - 643
  • [29] Research on the Hierarchical Discrete Time-Cost Trade-Off Problem for Program
    Chen, Liangwei
    Zhang, Jingwen
    Peng, Wuliang
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2022, 148 (07)
  • [30] Time Cost Trade-Off Problem Using Intuitionistic Fuzzy with Real Time Application in the Field of Construction
    Priyadharshini, S.
    Deepa, G.
    CONTEMPORARY MATHEMATICS, 2024, 5 (03):