Time Cost Trade-Off Problem Using Intuitionistic Fuzzy with Real Time Application in the Field of Construction

被引:1
|
作者
Priyadharshini, S. [1 ]
Deepa, G. [1 ]
机构
[1] Vellore Inst Technol Univ, Dept Math, Vellore 632007, India
来源
CONTEMPORARY MATHEMATICS | 2024年 / 5卷 / 03期
关键词
: critical path problem; triangular fuzzy number; intuitionistic triangular fuzzy number; acyclic network; crashing; optimization; CRITICAL-PATH;
D O I
10.37256/cm.5320243727
中图分类号
O29 [应用数学];
学科分类号
070104 ;
摘要
In order to assist in locating the critical path in an acyclic network, the Critical Path Method (CPM) employs intuitionistic triangular fuzzy number. Project crashing is a technique used to cut the project timeline fast by minimizing the duration of one or more critical task below their typical duration. The goal of crashing, often referred to as the time- cost trade-off, is to shorten the project's duration while lowering its cost. The intuitionistic fuzzy critical path technique and the time-cost trade-off issue were developed as a result of the uncertainty or ambiguity around the length of activities. The present investigation proposes an optimal method for handling the time-cost trade-off problem (TCTP). When the duration aspect is taken into account, the project's overall cost is effectively reduced. It is simpler to compute the time and monetary expenses of being on the critical path while using this approach. An existing application from the literature is selected and implemented to demonstrate the operation of this technology. Additionally, we suggested a ranking method for defuzzification called "Magnitude measure". Both the traditional approach and the path length ranking methodology are used for verification. MATLAB is used to give simulation results.
引用
收藏
页数:22
相关论文
共 50 条
  • [1] A comparative study on Real Life Application of Fuzzy Time Cost Trade-off problems
    Abinaya, B.
    Amirtharaj, E. C. Henry
    JOURNAL OF ALGEBRAIC STATISTICS, 2022, 13 (02) : 1082 - 1089
  • [2] Time-cost trade-off problem in construction project management, based on fuzzy logic
    Abbasnia, R.
    Afshar, A.
    Eshtehardian, E.
    Journal of Applied Sciences, 2008, 8 (22) : 4159 - 4165
  • [3] Solving Fuzzy Time–Cost Trade-Off in Construction Projects Using Linear Programming
    Elkalla I.
    Elbeltagi E.
    El Shikh M.
    Journal of The Institution of Engineers (India): Series A, 2021, 102 (1) : 267 - 278
  • [4] New fuzzy models for time-cost trade-off problem
    Hua Ke
    Weimin Ma
    Xin Gao
    Weihua Xu
    Fuzzy Optimization and Decision Making, 2010, 9 : 219 - 231
  • [5] New fuzzy models for time-cost trade-off problem
    Ke, Hua
    Ma, Weimin
    Gao, Xin
    Xu, Weihua
    FUZZY OPTIMIZATION AND DECISION MAKING, 2010, 9 (02) : 219 - 231
  • [6] Application of fuzzy BWM-CoCoSo to time–cost–environmental impact trade-off construction project scheduling problem
    S. A. Banihashemi
    M. Khalilzadeh
    International Journal of Environmental Science and Technology, 2023, 20 : 1199 - 1214
  • [7] A fuzzy time-cost trade-off problem with credibility theory concepts
    Ke, Hua
    Ma, Weimin
    PROCEEDING OF THE SEVENTH INTERNATIONAL CONFERENCE ON INFORMATION AND MANAGEMENT SCIENCES, 2008, 7 : 258 - 262
  • [8] Application of fuzzy BWM-CoCoSo to time-cost-environmental impact trade-off construction project scheduling problem
    Banihashemi, S. A.
    Khalilzadeh, M.
    INTERNATIONAL JOURNAL OF ENVIRONMENTAL SCIENCE AND TECHNOLOGY, 2023, 20 (02) : 1199 - 1214
  • [9] Using ant colony algorithm to solve construction time-cost trade-off problem
    College of Civil Engineering and Architecture, Zhejiang University, Hangzhou 310027, China
    不详
    Zhejiang Daxue Xuebao (Gongxue Ban), 2007, 1 (176-180):
  • [10] On the discrete time, cost and quality trade-off problem
    Tareghian, Hamed R.
    Taheri, Seyyed Hassan
    APPLIED MATHEMATICS AND COMPUTATION, 2006, 181 (02) : 1305 - 1312