CONSTRUCTION TIME-COST TRADE-OFF ANALYSIS USING LP/IP HYBRID METHOD

被引:85
|
作者
LIU, L
BURNS, SA
FENG, CW
机构
[1] Dept. of Civ. Engrg., Univ. of Illinois at Urbana-Champaign, Urbana, IL, 61801
[2] Dept. of General Engrg., Univ. of Illinois at UrbanaChampaign, Urbana, IL
关键词
D O I
10.1061/(ASCE)0733-9364(1995)121:4(446)
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Construction planners must select appropriate resources, including crew size, equipment, methods, and technologies, to perform the tasks of a construction project. In general, there is a trade-off between time and cost to complete a task-the less expensive the resources, the longer it takes. Using critical-path-method techniques, the overall project cost can be reduced by using less expensive resources for noncritical activities without impacting the duration. Furthermore planners usually need to adjust the selection of resources in order to shorten or lengthen the project duration. Finding optimal decisions is difficult and time-consuming considering the numbers of permutations involved. For example, a critical-path-method network with only eight activities, each with two options, will have 256 (2(8)) alternatives. Exhaustive enumeration is not economically feasible even with very fast computers. This paper presents a new algorithm using linear and integer programming to efficiently obtain optimal resource selections that optimize time and cost of a construction project.
引用
收藏
页码:446 / 454
页数:9
相关论文
共 50 条
  • [21] Integrating Quality and Safety in Construction Scheduling Time-Cost Trade-Off Model
    Panwar, Abhilasha
    Jha, Kumar Neeraj
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2021, 147 (02)
  • [22] Time-Cost Trade-off Optimization of Construction Projects using Teaching Learning Based Optimization
    Togan, Vedat
    Eirgash, M. Azim
    KSCE JOURNAL OF CIVIL ENGINEERING, 2019, 23 (01) : 10 - 20
  • [23] A GENERALIZED TIME-COST TRADE-OFF TRANSPORTATION PROBLEM
    PRASAD, VR
    NAIR, KPK
    ANEJA, YP
    JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 1993, 44 (12) : 1243 - 1248
  • [24] A Fuzzy Random Time-Cost Trade-off Model
    Ke, Hua
    Ma, Weimin
    PROCEEDINGS OF THE EIGHTH INTERNATIONAL CONFERENCE ON INFORMATION AND MANAGEMENT SCIENCES, 2009, 8 : 633 - 637
  • [25] Time-cost trade-off analysis of project networks in fuzzy environments
    Chen, Shih-Pin
    Tsai, Ming-Jiun
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2011, 212 (02) : 386 - 397
  • [26] TIME-COST TRADE-OFF ANALYSIS IN SOME CONSTRAINED ASSIGNMENT PROBLEMS
    GEETHA, S
    VARTAK, MN
    JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 1989, 40 (01) : 97 - 101
  • [27] TIME-COST TRADE-OFF AMONG RELATED ACTIVITIES
    REDA, R
    CARR, RI
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1989, 115 (03): : 475 - 486
  • [28] TIME-COST TRADE-OFF IN A SOLID TRANSPORTATION PROBLEM
    BHATIA, HL
    PURI, MC
    ZEITSCHRIFT FUR ANGEWANDTE MATHEMATIK UND MECHANIK, 1977, 57 (10): : 616 - 619
  • [29] Time-cost trade-off in PERT networks using a genetic algorithm
    Azaron, A
    Perkgoz, C
    Kato, K
    Katagiri, H
    Sakawa, M
    2004 47TH MIDWEST SYMPOSIUM ON CIRCUITS AND SYSTEMS, VOL III, CONFERENCE PROCEEDINGS, 2004, : 57 - 60
  • [30] Multiobjective Optimization of Time-Cost Trade-Off Using Harmony Search
    Geem, Zong Woo
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2010, 136 (06): : 711 - 716