Project Scheduling by Integration of Time Cost Trade-off and Constrained Resource Scheduling

被引:18
|
作者
Tiwari S. [1 ]
Johari S. [1 ]
机构
[1] Department of Civil Engineering, Madhav Institute of Technology & Science Gwalior, Gwalior, Madhya Pradesh
关键词
Constrained resource scheduling; Critical path method; Linear programming; Microsoft project software;
D O I
10.1007/s40030-014-0099-2
中图分类号
学科分类号
摘要
Project managers today rely on scheduling tools based on project network techniques like Critical Path Method (CPM) to determine the overall project duration and the activities float time. Such data provide important information about the degree of flexibility with respect to the project schedule that leads to greater efficiency in planning and control of projects. The traditional representation of CPM, however, is based on two unrealistic assumptions: that the project deadline is not restricted and that resources are unlimited. In most of the construction projects the deadline and resource limits are practical constraints that need to be satisfied simultaneously. While the available literatures describe several techniques to resolve the Time Cost Trade off (TCT) and Constrained Resource Scheduling (CRS) individually, little effort has been devoted to consider them simultaneously because of the higher modeling complexity involved. No commercial software includes any TCT heuristic to help meet deadline, let alone any procedure to resolve both deadline and resource constraints. In practice on the other hand there is a need to formulate a method that simultaneously resolves to meet out the specified duration and resource constraints. This paper therefore introduces a two-step procedure where first the TCT is applied using Microsoft excel software to meet the project deadline assuming unlimited resources. The various feasible schedules obtained in the first step are then explored by applying CRS using Microsoft Project Software (MSP) to arrive at the desired project schedule meeting the deadline with available resources. The proposed approach was experimented on several case studies that proved its usefulness. The intertwined approach using simple and popular Microsoft office tools (Excel and MSP) is logical, fast and provides a set of feasible project schedule meeting the deadline and that do not violate resource limits. © 2014, The Institution of Engineers (India).
引用
收藏
页码:37 / 46
页数:9
相关论文
共 50 条
  • [1] A Developmental Genetic Approach to the cost/time trade-off in Resource Constrained Project Scheduling
    Pawinski, Grzegorz
    Sapiecha, Krzysztof
    FEDERATED CONFERENCE ON COMPUTER SCIENCE AND INFORMATION SYSTEMS, 2014, 2014, 2 : 171 - 179
  • [2] A multi-objective resource-constrained optimization of time-cost trade-off problems in scheduling project
    Zareei, Mostafa
    Hassan-Pour, Hossein Ali
    IRANIAN JOURNAL OF MANAGEMENT STUDIES, 2015, 8 (04) : 653 - 685
  • [3] The trade-off between stability and makespan in resource-constrained project scheduling
    Van De Vonder, S
    Demeulemeester, E
    Herroelen, W
    Leus, R
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2006, 44 (02) : 215 - 236
  • [4] Project time–cost trade-off scheduling: a hybrid optimization approach
    Hadi Mokhtari
    Abdollah Aghaie
    Javad Rahimi
    Ashkan Mozdgir
    The International Journal of Advanced Manufacturing Technology, 2010, 50 : 811 - 822
  • [5] Time-cost-quality-environmental impact trade-off resource-constrained project scheduling problem with DEA approach
    Banihashemi, Sayyid Ali
    Khalilzadeh, Mohammad
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2021, 28 (07) : 1979 - 2004
  • [6] Project time-cost trade-off scheduling: a hybrid optimization approach
    Mokhtari, Hadi
    Aghaie, Abdollah
    Rahimi, Javad
    Mozdgir, Ashkan
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2010, 50 (5-8): : 811 - 822
  • [7] Analysis of a time-cost trade-off in a resource-constrained GERT project scheduling problem using the Markov decision process
    Sadri, Shadi
    Ghomi, S. M. T. Fatemi
    Dehghanian, Amin
    ANNALS OF OPERATIONS RESEARCH, 2024, 338 (01) : 535 - 568
  • [8] Solving the discrete time/resource trade-off problem in project scheduling with genetic algorithms
    Ranjbar, Mohammad R.
    Kianfar, Fereydoon
    APPLIED MATHEMATICS AND COMPUTATION, 2007, 191 (02) : 451 - 456
  • [9] A hybrid scatter search for the discrete time/resource trade-off problem in project scheduling
    Ranjbar, Mohammad
    De Reyck, Bert
    Kianfar, Fereydoon
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2009, 193 (01) : 35 - 48
  • [10] TIME-COST TRADE-OFF SCHEDULING UNDER CONSTRUCTION LABOR RESOURCE CONSTRAINTS
    Benjaoran, Vacharapoom
    Sae-Tae, Numpheungk
    SURANAREE JOURNAL OF SCIENCE AND TECHNOLOGY, 2011, 18 (01): : 29 - 39