A multi-objective resource-constrained optimization of time-cost trade-off problems in scheduling project

被引:0
|
作者
Zareei, Mostafa [1 ]
Hassan-Pour, Hossein Ali [1 ]
机构
[1] Imam Hossein AS Univ, Fac Ind Engn, Tehran, Iran
关键词
Comparative indicators of evolutionary algorithms; MOSA and MOPSO algorithm; NSGA-II; Payment patterns; Project scheduling; Resource constraints;
D O I
暂无
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
This paper presents a multi-objective resource-constrained project scheduling problem with positive and negative cash flows. The net present value (NPV) maximization and making span minimization are this study objectives. And since this problem is considered as complex optimization in NP-Hard context, we present a mathematical model for the given problem and solve three evolutionary algorithms; NSGA-II, MOSA and MOPSO are applied to find the set of Pareto solutions for this multi-objective scheduling problem. In order to show performance of the algorithms, different metrics are applied and comparisons between the two algorithms are also considered. The computational results for a set of test problems taken from the project scheduling problem Bandar Abbas Gas condensate Refinery project and library are presented and discussed. Finally, the computational results illustrate the superior performance of the NSGA-II, MOSA and MOPSO algorithm with regard to the proposed metrics. In order to solve proposed method from NSGA-II algorithm, the results are compared with GAMS software in some problems. The proposed method is a Converge to the optimum and efficient solution algorithm.
引用
收藏
页码:653 / 685
页数:33
相关论文
共 50 条
  • [1] A Multi-objective Genetic Algorithm for Optimization Time-Cost Trade-off Scheduling
    Aghassi, Hadi
    Abadi, Sedigheh Nader
    Roghanian, Emad
    KNOWLEDGE TECHNOLOGY, 2012, 295 : 356 - +
  • [2] Multi-objective time-cost trade-off optimization for the construction scheduling with Rao algorithms
    Yilmaz, Mehmet
    Dede, Tayfun
    STRUCTURES, 2023, 48 : 798 - 808
  • [3] Analysis of a time-cost trade-off in a resource-constrained GERT project scheduling problem using the Markov decision process
    Sadri, Shadi
    Ghomi, S. M. T. Fatemi
    Dehghanian, Amin
    ANNALS OF OPERATIONS RESEARCH, 2024, 338 (01) : 535 - 568
  • [4] Project time-cost trade-off scheduling: a hybrid optimization approach
    Mokhtari, Hadi
    Aghaie, Abdollah
    Rahimi, Javad
    Mozdgir, Ashkan
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2010, 50 (5-8): : 811 - 822
  • [5] Project Scheduling by Integration of Time Cost Trade-off and Constrained Resource Scheduling
    Tiwari S.
    Johari S.
    Journal of The Institution of Engineers (India): Series A, 2015, 96 (1) : 37 - 46
  • [6] Flexible Resource-constrained Discrete Time-cost Trade-off Problem Considering Resource Transfer
    Zou, Haobo
    Zhou, Guohua
    JOURNAL OF INTERNET TECHNOLOGY, 2021, 22 (01): : 197 - 207
  • [7] Novel Hybrid Method in Time-Cost Trade-Off for Resource-Constrained Construction Projects
    Albayrak, Gulcag
    IRANIAN JOURNAL OF SCIENCE AND TECHNOLOGY-TRANSACTIONS OF CIVIL ENGINEERING, 2020, 44 (04) : 1295 - 1307
  • [8] Fuzzy Multi-objective Programming Application for Time-Cost Trade-off of CPM in Project Management
    Yang, Gino K.
    COMPUTATIONAL COLLECTIVE INTELLIGENCE: TECHNOLOGIES AND APPLICATIONS, PT I, 2010, 6421 : 215 - 229
  • [9] An integrated multi-objective optimization model for solving the construction time-cost trade-off problem
    Koo, Choongwan
    Hong, Taehoon
    Kim, Sangbum
    JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2015, 21 (03) : 323 - 333
  • [10] Multi-project Scheduling: Multicriteria Time-cost Trade-off Problem
    Klevanskiy, N. N.
    Tkachev, S. I.
    Voloshchouk, L. A.
    PROCEEDINGS OF THE 13TH INTERNATIONAL SYMPOSIUM INTELLIGENT SYSTEMS 2018 (INTELS'18), 2019, 150 : 237 - 243