Resource Constrained Project Scheduling Optimization With Robust Objective Under Stochastic Duration Of Activities

被引:1
|
作者
Zheng, Wei-bo [1 ,2 ]
He, Yu-kang [3 ]
机构
[1] Xi An Jiao Tong Univ, Sch Management, Xian, Shaanxi, Peoples R China
[2] Minist Educ Proc Control & Efficiency Engn, Key Lab, Xian, Shaanxi, Peoples R China
[3] Heilongjiang Univ, Sch Comp Sci & Technol, Harbin, Heilongjiang, Peoples R China
基金
中国国家自然科学基金;
关键词
Optimization model; project scheduling; robustness; variable neighborhood search; TRADE-OFF; STABILITY; MODEL;
D O I
10.2991/978-94-6239-255-7_43
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
This paper involves the resource constrained project robust scheduling problem where the objective is to maximize the robustness of the baseline schedule under the constraints of resources and project deadline. On the basis of the identification of the problem, the optimization model is constructed. Then, for the NP-hardness of the problem, the two versions of variable neighborhood search (VNS), i.e., the hybrid VNS and the parallel VNS, are developed to solve the problem. To evaluate the performance of the two VNS methods, a computational experiment is conducted based on a set of data consisting of 50 instances generated randomly. The results show that the developed algorithms can solve the problem with an acceptable computational time. With the increase of the problem scale, the hybrid VNS performs better while the parallel VNS becomes worse.
引用
收藏
页码:239 / 243
页数:5
相关论文
共 50 条
  • [31] Multi-objective robust optimization of staff scheduling for emergency under stochastic demand
    Hu, Yucong
    Liu, Qingyang
    Li, Sitong
    Wu, Weitiao
    EXPERT SYSTEMS WITH APPLICATIONS, 2024, 254
  • [32] Resource-constrained project scheduling - Minimization of general objective functions
    不详
    PROJECT SCHEDULING WITH TIME WINDOWS AND SCARCE RESOURCES, 2002, 508 : 175 - 299
  • [33] Multi-objective resource constrained project scheduling problem based on improved ant colony optimization
    An X.
    Zhang Z.
    Xitong Gongcheng Lilun yu Shijian/System Engineering Theory and Practice, 2019, 39 (02): : 509 - 519
  • [34] RESOURCE CONSTRAINED PROJECT SCHEDULING
    FITZPATRICK, DW
    VEMUGANTI, RR
    OPERATIONS RESEARCH, 1975, 23 : B407 - B407
  • [35] Resource Constrained Project Scheduling Using Particle Swarm Optimization
    Wang, Jiancheng
    PROCEEDINGS OF THE 2016 INTERNATIONAL CONFERENCE ON APPLIED MATHEMATICS, SIMULATION AND MODELLING, 2016, 41 : 387 - 392
  • [36] Ant colony optimization for resource-constrained project scheduling
    Merkle, D
    Middendorf, M
    Schmeck, H
    IEEE TRANSACTIONS ON EVOLUTIONARY COMPUTATION, 2002, 6 (04) : 333 - 346
  • [37] Particle swarm optimization for resource-constrained project scheduling
    Department of Building and Construction, City University of Hong Kong, Tat Avenue, Kowloon, Hong Kong
    不详
    Int. J. Proj. Manage., 2006, 1 (83-92):
  • [38] A bi-objective Model for Robust Resource-constrained Project Scheduling Problem with Random Activity Durations
    Zhang, Jingwen
    Qiao, Chuanzhuo
    2015 IEEE 12th International Conference on Networking, Sensing and Control (ICNSC), 2015, : 28 - 32
  • [39] Proactive policies for the stochastic resource-constrained project scheduling problem
    Deblaere, Filip
    Demeulemeester, Erik
    Herroelen, Willy
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2011, 214 (02) : 308 - 316
  • [40] An Uncertainty Tolerant Approach For Stochastic Resource Constrained Project Scheduling Problems
    Chakrabortty, Ripon K.
    Ryan, Michael J.
    2019 IEEE TECHNOLOGY & ENGINEERING MANAGEMENT CONFERENCE (TEMSCON), 2019,