A Developmental Genetic Approach to the cost/time trade-off in Resource Constrained Project Scheduling

被引:0
|
作者
Pawinski, Grzegorz [1 ]
Sapiecha, Krzysztof [2 ]
机构
[1] Kielce Univ Technol, Dept Comp Sci, PL-25314 Kielce, Poland
[2] Cracow Univ Technol, Fac Elect & Comp Engn, PL-31155 Krakow, Poland
关键词
ALGORITHM;
D O I
暂无
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
In this paper, the use of Developmental Genetic Programming (DGP) for solving a new extension of the Resource-Constrained Project Scheduling Problem (RCPSP) is investigated. We consider a variant of the problem when resources are only partially available and a deadline is given but it is the cost of the project that should be minimized. RCPSP is a well-known NP-hard problem but in its original formulation it does not take into consideration initial resource workload and it minimises the makespan. Unlike other genetic approaches, where genotypes represent solutions, a genotype in DGP is a procedure that constructs a solution to the problem. Genotypes (the search space) and phenotypes (the solution space) are distinguished and a genotype-to-phenotype mapping (GPM) is used. Thus, genotypes are evolved without any restrictions and the whole search space is explored. The goal of the evolution is to find a procedure constructing the best solution of the problem for which the cost of the project is minimal. The paper presents genetic operators as well as GPM specified for the DGP. Experimental results showed that our approach gives significantly better results compared with methods presented in the literature.
引用
收藏
页码:171 / 179
页数:9
相关论文
共 50 条
  • [31] A ROBUST TIME-COST-QUALITY-ENERGY-ENVIRONMENT TRADE-OFF WITH RESOURCE-CONSTRAINED IN PROJECT MANAGEMENT: A CASE STUDY FOR A BRIDGE CONSTRUCTION PROJECT
    Lotfi, Reza
    Yadegari, Zahra
    Hosseini, Seyed Hossein
    Khameneh, Amir Hossein
    Tirkolaee, Erfan Babaee
    Weber, Gerhard-Wilhelm
    JOURNAL OF INDUSTRIAL AND MANAGEMENT OPTIMIZATION, 2022, 18 (01) : 375 - 396
  • [32] Novel Hybrid Method in Time-Cost Trade-Off for Resource-Constrained Construction Projects
    Albayrak, Gulcag
    IRANIAN JOURNAL OF SCIENCE AND TECHNOLOGY-TRANSACTIONS OF CIVIL ENGINEERING, 2020, 44 (04) : 1295 - 1307
  • [33] Project scheduling with time, cost and risk trade-off using adaptive multiple objective differential evolution
    Duc Hoc Tran
    Luong Duc Long
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2018, 25 (05) : 623 - 638
  • [34] The discrete time/resource trade-off problem in project networks: a branch-and-bound approach
    Demeulemeester, E
    De Reyck, B
    Herroelen, W
    IIE TRANSACTIONS, 2000, 32 (11) : 1059 - 1069
  • [35] Scheduling parallel CNC machines with time/cost trade-off considerations
    Gurel, Sinan
    Akturk, M. Selim
    COMPUTERS & OPERATIONS RESEARCH, 2007, 34 (09) : 2774 - 2789
  • [36] A TRADE-OFF BETWEEN TIME AND COST IN SCHEDULING REPETITIVE CONSTRUCTION PROJECTS
    Zhang, Lihui
    Zou, Xin
    Qi, Jianxun
    JOURNAL OF INDUSTRIAL AND MANAGEMENT OPTIMIZATION, 2015, 11 (04) : 1423 - 1434
  • [37] The resource-constrained time/cost trade-offs project scheduling with discount cash flow
    Zhang, JW
    Xu, Y
    He, ZW
    PROCEEDINGS OF THE 2005 INTERNATIONAL CONFERENCE ON MANAGEMENT SCIENCE & ENGINEERING (12TH), VOLS 1- 3, 2005, : 2303 - 2307
  • [38] Trade-off between time and cost in project planning: a simulation-based optimization approach
    Senses, Sena
    Kumral, Mustafa
    SIMULATION-TRANSACTIONS OF THE SOCIETY FOR MODELING AND SIMULATION INTERNATIONAL, 2024, 100 (02): : 127 - 143
  • [39] Time, cost and quality trade-off in project management: A case study
    Asia Inst of Technology, Bangkok, Thailand
    Int J Proj Manage, 4 (249-256):
  • [40] An overview of the time-cost trade-off problems of project planning
    Csordas, Helga
    CREATIVE CONSTRUCTION CONFERENCE 2017, CCC 2017, 2017, 196 : 323 - 326