Analysis of Railway Bridge Girder Installation and Construction Technology-Based on BIM Technology

被引:0
|
作者
Ke L. [1 ]
Wan R. [1 ]
机构
[1] Southwest Jiaotong University Hope College, Sichuan, Chengdu
关键词
BIM technology; Bridge girder plate installation; Construction simulation; Deviation warning; Lean management;
D O I
10.2478/amns-2024-1242
中图分类号
学科分类号
摘要
The emergence of BIM technology has caused changes in the field of construction, which is of great significance to improving the construction technology and management level of roads and bridges. In this paper, the overall framework of the railroad bridge BIM model is constructed by utilizing several BIM software to display its corresponding geometric construction information and line information. Based on the relevant information, construction simulation technology is combined with BIM technology to propose a lean management model for a railroad bridge construction site. Specifically, it first checks the mechanical properties of the bridge plate to ensure the safety of its installation, and then optimizes the progress of the construction phase under the constraints of the construction site, realizes the deviation warning, and ensures the optimal completion of the construction project. The results show that the paving layer connection structure has an optimal load transfer effect in the range of 0-502kN. However, cracking at the critical point of the pressure plate can result in plastic deformation before. At the same time, the vibration of the abutment plays an important role in the safety of the overall bridge structure, and the abutment height of the bridge should be controlled within 40M. By optimizing the construction schedule of beams and slabs, the contract period can be shortened by up to 19 days, and the expected cost can be reduced by 760,000 yuan. The research results accumulate methods for applying BIM technology in the installation and construction stages of railway bridge beams and slabs. © 2024 Long Ke et al., published by Sciendo.
引用
收藏
相关论文
共 50 条
  • [1] Optimize bridge construction process based on BIM technology
    Shi, X. F.
    Liu, Z. Q.
    Yan, X.
    Ma, Z. Q.
    MAINTENANCE, MONITORING, SAFETY, RISK AND RESILIENCE OF BRIDGES AND BRIDGE NETWORKS, 2016, : 250 - 250
  • [2] Installation Technology of Webs in the Construction of PC Box-girder Bridge with Corrugated Steel Webs
    Du, Yajiang
    Yang, Bingwen
    Wan, Shui
    PROGRESS IN INDUSTRIAL AND CIVIL ENGINEERING, PTS. 1-5, 2012, 204-208 : 2209 - +
  • [3] Application of BIM Technology Based on Autodesk Revit in Construction and Installation Engineering
    Huang, Chen
    PROCEEDINGS OF THE 2017 3RD INTERNATIONAL CONFERENCE ON ECONOMICS, SOCIAL SCIENCE, ARTS, EDUCATION AND MANAGEMENT ENGINEERING (ESSAEME 2017), 2017, 119 : 1280 - 1283
  • [4] Integration Technology of BIM and 3DGIS and Its Application in Railway Bridge Construction
    Zhang W.
    Wu Q.
    Qi P.
    Wu Z.
    Wang B.
    Zhongguo Tiedao Kexue/China Railway Science, 2019, 40 (06): : 45 - 51
  • [5] Innovation and Practice of Railway Engineering Construction Management Based on BIM Technology
    Wang T.
    Tiedao Xuebao/Journal of the China Railway Society, 2019, 41 (01): : 1 - 9
  • [6] Simulation of bridge steel structure construction process based on BIM technology
    Pan W.
    Applied Mathematics and Nonlinear Sciences, 2024, 9 (01)
  • [7] Research on Construction of Highway Bridge Quality Engineering Based on BIM Technology
    Zhang, Kechao
    Wang, Chen
    Liu, Xiangsheng
    2020 4TH INTERNATIONAL WORKSHOP ON RENEWABLE ENERGY AND DEVELOPMENT (IWRED 2020), 2020, 510
  • [8] Research on Intelligent Construction Technology of Prefabricated Railway Bridge
    Qi, Chenglong
    Li, Yan
    2022 16TH IEEE INTERNATIONAL CONFERENCE ON SIGNAL PROCESSING (ICSP2022), VOL 1, 2022, : 375 - 378
  • [9] Practice and Thoughts on Application of BIM Technology to Digital Railway Construction
    Liu W.
    Tiedao Xuebao/Journal of the China Railway Society, 2019, 41 (03): : 97 - 101
  • [10] Application of BIM in construction management of railway tunnel by virtual technology
    Chen Fuqiang
    2018 2ND INTERNATIONAL WORKSHOP ON RENEWABLE ENERGY AND DEVELOPMENT (IWRED 2018), 2018, 153