Analysis of Railway Bridge Girder Installation and Construction Technology-Based on BIM Technology

被引:0
|
作者
Ke L. [1 ]
Wan R. [1 ]
机构
[1] Southwest Jiaotong University Hope College, Sichuan, Chengdu
关键词
BIM technology; Bridge girder plate installation; Construction simulation; Deviation warning; Lean management;
D O I
10.2478/amns-2024-1242
中图分类号
学科分类号
摘要
The emergence of BIM technology has caused changes in the field of construction, which is of great significance to improving the construction technology and management level of roads and bridges. In this paper, the overall framework of the railroad bridge BIM model is constructed by utilizing several BIM software to display its corresponding geometric construction information and line information. Based on the relevant information, construction simulation technology is combined with BIM technology to propose a lean management model for a railroad bridge construction site. Specifically, it first checks the mechanical properties of the bridge plate to ensure the safety of its installation, and then optimizes the progress of the construction phase under the constraints of the construction site, realizes the deviation warning, and ensures the optimal completion of the construction project. The results show that the paving layer connection structure has an optimal load transfer effect in the range of 0-502kN. However, cracking at the critical point of the pressure plate can result in plastic deformation before. At the same time, the vibration of the abutment plays an important role in the safety of the overall bridge structure, and the abutment height of the bridge should be controlled within 40M. By optimizing the construction schedule of beams and slabs, the contract period can be shortened by up to 19 days, and the expected cost can be reduced by 760,000 yuan. The research results accumulate methods for applying BIM technology in the installation and construction stages of railway bridge beams and slabs. © 2024 Long Ke et al., published by Sciendo.
引用
收藏
相关论文
共 50 条
  • [21] Application Study of BIM Technology in Swivel Construction of Continuous Beam Bridge
    Wu, Zengtao
    CICTP 2022: INTELLIGENT, GREEN, AND CONNECTED TRANSPORTATION, 2022, : 2100 - 2111
  • [22] Study of Bridge Scheme Creation based on BIM Technology
    Chen, Xiaohu
    Xiao, Kui
    Guo, Wei
    Chen, Jiayong
    STRUCTURAL ENGINEERING INTERNATIONAL, 2021, 31 (04) : 577 - 583
  • [23] Construction control of cable-stayed bridge top push method based on BIM technology
    Chengyong Chen
    Wenming Su
    Wenqiang Dou
    Yongquan Dong
    Ben Zhang
    Discover Applied Sciences, 7 (4)
  • [24] Jacking technology for a simply supported girder bridge
    Xu, Lige
    Wang, Yili
    Xu, Changjie
    APPLIED MECHANICS AND MATERIALS II, PTS 1 AND 2, 2014, 477-478 : 675 - 680
  • [25] A BIM technology-based underwater structure damage identification and management method
    Li, Xiaofei
    Su, Rongrong
    Cheng, Peng
    Sun, Heming
    Meng, Qinghang
    Song, Taiyi
    Wei, Mengpu
    Zhang, Chen
    BULLETIN OF THE POLISH ACADEMY OF SCIENCES-TECHNICAL SCIENCES, 2023, 71 (02)
  • [26] Research on Visual Management Technology of Tunnel Construction Process Based on BIM Technology
    Zhou, Yue
    Wang, Chuang
    Yuan, Bingxiang
    Chen, Minjie
    Lv, Jianbing
    ADVANCES IN CIVIL ENGINEERING, 2021, 2021
  • [27] Technology-based training
    Cheng, EWL
    HUMAN FACTORS AND ERGONOMICS IN MANUFACTURING, 1999, 9 (04): : 413 - 414
  • [28] Technology-based dissemination
    Jennett, PA
    Premkumar, K
    CANADIAN JOURNAL OF PUBLIC HEALTH-REVUE CANADIENNE DE SANTE PUBLIQUE, 1996, 87 : S34 - S39
  • [29] Reliability analysis for new technology-based transmitters
    Brissaud, Florent
    Barros, Anne
    Berenguer, Christophe
    Charpentier, Dominique
    RELIABILITY ENGINEERING & SYSTEM SAFETY, 2011, 96 (02) : 299 - 313
  • [30] Research on Construction Schedule Management Based on BIM Technology
    Li, Xue
    Xu, Jing
    Zhang, Qun
    13TH GLOBAL CONGRESS ON MANUFACTURING AND MANAGEMENT, 2017, 174 : 657 - 667