Integrating quality in resource-constrained time-cost trade-off optimization for civil construction projects using NSGA-III technique

被引:0
|
作者
Shrivastava A. [1 ]
Pandey M. [1 ]
机构
[1] Civil Engineering Department, Institute of Technology and Management University, Gwalior
关键词
Construction projects; NSGA III; Optimization; TCQT;
D O I
10.1007/s42107-024-01068-y
中图分类号
学科分类号
摘要
In the realm of civil construction projects, achieving an optimal balance between project time, cost, and quality is paramount for ensuring project success and stakeholder satisfaction. Traditional optimization approaches often focus solely on time and cost, potentially neglecting the critical aspect of quality. This study presents a novel framework aimed at integrating quality considerations into resource-constrained time-cost trade-off optimization process using Non-dominated Sorting Genetic Algorithm III (NSGA III) technique. The proposed framework addresses the inherent trade-offs among time, cost, and quality by simultaneously optimizing these objectives. By leveraging NSGA-III, a powerful multi-objective optimization algorithm, the framework generates a set of Pareto-optimal solutions that represent various trade-off options. This enables decision-makers to explore and select solutions that best align with project objectives and constraints. Through solving a real case study project, the effectiveness of the proposed framework is demonstrated in real-world civil construction projects. Results of the study indicate that integrating quality considerations into the time-cost trade-off optimization process leads to more informed decision-making, ultimately enhancing project outcomes and stakeholder satisfaction. This research contributes to advancing the field of project management in civil construction by providing a systematic approach for addressing the complex interplay of time, cost, and quality objectives. © The Author(s), under exclusive licence to Springer Nature Switzerland AG 2024.
引用
收藏
页码:4619 / 4632
页数:13
相关论文
共 50 条
  • [21] Time-cost trade-off optimization model for retrofitting planning projects using MOGA
    Patil A.S.
    Agarwal A.K.
    Sharma K.
    Trivedi M.K.
    Asian Journal of Civil Engineering, 2024, 25 (5) : 3823 - 3833
  • [22] Optimizing trade-off between time, cost, and carbon emissions in construction using NSGA-III: an integrated approach for sustainable development
    Amir Prasad Behera
    Mayank Chauhan
    Gaurav Shrivastava
    Prachi Singh
    Jyoti Shukla
    Krushna Chandra Sethi
    Asian Journal of Civil Engineering, 2025, 26 (1) : 73 - 87
  • [23] Multimode variable resource-constrained time/cost trade-off problem in repetitive projects with adjustment strategy
    Zou, Haobo
    Zhou, Guohua
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2024, 24 (12) : 1271 - 1281
  • [24] Construction time-cost trade-off analysis using ant colony optimization algorithm
    Kuang Ya-ping
    Xiong Ying
    PROCEEDINGS OF THE 2006 INTERNATIONAL CONFERENCE ON MANAGEMENT SCIENCE & ENGINEERING (13TH), VOLS 1-3, 2006, : 2039 - 2044
  • [25] TIME-COST TRADE-OFF SCHEDULING UNDER CONSTRUCTION LABOR RESOURCE CONSTRAINTS
    Benjaoran, Vacharapoom
    Sae-Tae, Numpheungk
    SURANAREE JOURNAL OF SCIENCE AND TECHNOLOGY, 2011, 18 (01): : 29 - 39
  • [26] Development of time–cost trade-off optimization model for construction projects with MOPSO technique
    Agarwal A.K.
    Chauhan S.S.
    Sharma K.
    Sethi K.C.
    Asian Journal of Civil Engineering, 2024, 25 (6) : 4529 - 4539
  • [27] Multimodal optimization for time-cost trade-off in construction projects using a novel hybrid method based on FA and PSO
    Arlbayrak, Gulcag
    Ozdemir, Ilker
    REVISTA DE LA CONSTRUCCION, 2018, 17 (02): : 304 - 318
  • [28] Two-Phase Differential Evolution for the Multiobjective Optimization of Time-Cost Tradeoffs in Resource-Constrained Construction Projects
    Cheng, Min-Yuan
    Duc-Hoc Tran
    IEEE TRANSACTIONS ON ENGINEERING MANAGEMENT, 2014, 61 (03) : 450 - 461
  • [29] Resource Constrained Time-cost Trade-off Problem and its Genetic Algorithm Solution
    Feng, Yixiong
    Lin, Xiaohua
    Tan, Jianrong
    APPLIED MATHEMATICS & INFORMATION SCIENCES, 2013, 7 (02): : 639 - 643
  • [30] Optimization of environmental impacts of construction projects: a time–cost–quality trade-off approach
    S. A. Banihashemi
    Mohammad Khalilzadeh
    A. Shahraki
    M. Rostami Malkhalifeh
    S. S. R. Ahmadizadeh
    International Journal of Environmental Science and Technology, 2021, 18 : 631 - 646