An extension of the earned value management to improve the accuracy of schedule analysis results

被引:0
|
作者
Najafi, Amir [1 ]
Azimi, Fatemeh [2 ]
机构
[1] Islamic Azad Univ, Qazvin Branch, Fac Ind & Mech Engn, Qazvin, Iran
[2] Islamic Azad Univ, Qazvin Branch, Dept Math, Qazvin, Iran
关键词
Earned value; Project delay; Project management; Schedule analysis;
D O I
暂无
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
A project is any endeavor involving planned action, for example, developing a new product or constructing a dam. Major factors for a project to be successful are applying performance measurement and feedback tool. One such well-known performance measurement tool to control the project execution is earned value management (EVM). EVM uses the fundamental principle that trends in the past can be good predictors of the future. It was originally developed to follow time and cost of a project, but it has some weak points in analyzing the time performance of a project. In this article, we first explain these weak points in detail. Then, to improve them, we develop two methods: the first one is a simple and approximation method to minimize errors in EVM analysis with a high probability and the second method is an exact approach that uses earned value and floating time concepts. At the end, the performance of the proposed methods is evaluated and analyzed on a set of instances containing a variety of project sizes. The results of this experimentation show that the efficiency of the methods is relatively good.
引用
收藏
页码:63 / 75
页数:13
相关论文
共 50 条
  • [41] Earned-value management terminology
    Heires, JT
    COMPUTER, 2003, 36 (08) : 5 - 5
  • [42] Earned value management clogs profits
    Gupta, Sanjeev
    Ind Manage (Norcross GA), 2008, 3 (12-16): : 12 - 16
  • [43] The Application of Earned Value in Project Management
    Lv, Xiuling
    Wu, Jiangfeng
    ADVANCED BUILDING MATERIALS AND SUSTAINABLE ARCHITECTURE, PTS 1-4, 2012, 174-177 : 2844 - 2847
  • [44] A fuzzy approach for the earned value management
    Naeni, Leila Moslemi
    Shadrokh, Shahram
    Salehipour, Amir
    INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2011, 29 (06) : 764 - 772
  • [45] Earned Value Management Software Projects
    Hanna, Robert A.
    SMC-IT 2009: THIRD IEEE INTERNATIONAL CONFERENCE ON SPACE MISSION CHALLENGES FOR INFORMATION TECHNOLOGY, PROCEEDINGS, 2009, : 297 - 304
  • [46] Earned Value Management Symposium a Success
    Fontaine, Dan
    Insight, 2000, 2 (04)
  • [47] Dangers in using earned duration and other earned value metrics to measure a project’s schedule performance
    Richard E. Wendell
    Timothy J. Lowe
    Mike M. Gordon
    Central European Journal of Operations Research, 2023, 31 : 665 - 680
  • [48] Sensitivity of Earned Value Schedule Forecasting to S-Curve Patterns
    Kim, Byung-Cheol
    Kim, Hyung-Jin
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2014, 140 (07)
  • [49] "KAIZEN" (Improvement) in Spacecraft Project Management using "Earned Value Analysis"
    Lakshman, Deepti
    Kannan, M. V.
    Bhojraj, H.
    JOURNAL OF SPACECRAFT TECHNOLOGY, 2011, 21 (01): : 21 - 30
  • [50] Project Performance Analysis using Earned Value Management Method in Telecommunication
    Widiningrum, Adelia
    Pratami, Devi
    Haryono, Imam
    INTERNATIONAL JOURNAL OF INTEGRATED ENGINEERING, 2020, 12 (03): : 107 - 114