An extension of the earned value management to improve the accuracy of schedule analysis results

被引:0
|
作者
Najafi, Amir [1 ]
Azimi, Fatemeh [2 ]
机构
[1] Islamic Azad Univ, Qazvin Branch, Fac Ind & Mech Engn, Qazvin, Iran
[2] Islamic Azad Univ, Qazvin Branch, Dept Math, Qazvin, Iran
关键词
Earned value; Project delay; Project management; Schedule analysis;
D O I
暂无
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
A project is any endeavor involving planned action, for example, developing a new product or constructing a dam. Major factors for a project to be successful are applying performance measurement and feedback tool. One such well-known performance measurement tool to control the project execution is earned value management (EVM). EVM uses the fundamental principle that trends in the past can be good predictors of the future. It was originally developed to follow time and cost of a project, but it has some weak points in analyzing the time performance of a project. In this article, we first explain these weak points in detail. Then, to improve them, we develop two methods: the first one is a simple and approximation method to minimize errors in EVM analysis with a high probability and the second method is an exact approach that uses earned value and floating time concepts. At the end, the performance of the proposed methods is evaluated and analyzed on a set of instances containing a variety of project sizes. The results of this experimentation show that the efficiency of the methods is relatively good.
引用
收藏
页码:63 / 75
页数:13
相关论文
共 50 条
  • [21] Using the Earned Value Management System to Improve Electrical Project Control
    Hanna, Awad S.
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2012, 138 (03): : 449 - 457
  • [22] Beyond Earned Value Management: A Graphical Framework for Integrated Cost, Schedule and Risk Monitoring
    Acebes, Fernando
    Pajares, Javier
    Manuel Galan, Jose
    Lopez-Paredes, Adolfo
    SELECTED PAPERS FROM THE 26TH IPMA (INTERNATIONAL PROJECT MANAGEMENT ASSOCIATION), WORLD CONGRESS, 2013, 74 : 181 - 189
  • [23] Implementation and Evaluation of Earned Value Index to Achieve an Accurate Project Time and Cost Estimation and Improve "Earned Value Management System"
    Attarzadeh, Iman
    Hock, Ow Siew
    2009 INTERNATIONAL CONFERENCE ON INFORMATION MANAGEMENT AND ENGINEERING, PROCEEDINGS, 2009, : 312 - 316
  • [24] Project management: Earned value management
    Duncan, B
    TECHNOLOGY OF OBJECT-ORIENTED LANGUAGES AND SYSTEMS - TOOLS 34, PROCEEDINGS, 2000, : 513 - 514
  • [25] Earned value project management
    Fleming, Quentin W.
    Koppelman, Joel M.
    Cost Engineering (Morgantown, West Virginia), 1997, 39 (02): : 13 - 15
  • [26] Stability and accuracy of deterministic project duration forecasting methods in earned value management
    Barrientos-Orellana, Alexis
    Ballesteros-Perez, Pablo
    Mora-Melia, Daniel
    Gonzalez-Cruz, Maria Carmen
    Vanhoucke, Mario
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2022, 29 (03) : 1449 - 1469
  • [27] Modernizing earned value management
    Abba, Wayne F. (abbaconsulting@cox.net), 1600, U.S. Department of Defense (30):
  • [28] Practical experiences of cost/schedule measure through earned value management and statistical process control
    Wang, Qing
    Jiang, Nan
    Gou, Lang
    Che, Meiru
    Zhang, Ronghui
    SOFTWARE PROCESS CHANGE, 2006, 3966 : 348 - 354
  • [29] An Active Construction Dynamic Schedule Management Model: Using the Fuzzy Earned Value Management and BP Neural Network
    Yu, Fangfang
    Chen, Xiaobo
    Cory, Clark A.
    Yang, Zhixuan
    Hu, Yingwen
    KSCE JOURNAL OF CIVIL ENGINEERING, 2021, 25 (07) : 2335 - 2349
  • [30] An Active Construction Dynamic Schedule Management Model: Using the Fuzzy Earned Value Management and BP Neural Network
    Fangfang Yu
    Xiaobo Chen
    Clark A. Cory
    Zhixuan Yang
    Yingwen Hu
    KSCE Journal of Civil Engineering, 2021, 25 : 2335 - 2349