The calculation of acceleration costs on construction projects

被引:0
|
作者
Maritz, Tinus [1 ]
Schutte, Andries [2 ]
机构
[1] Univ Pretoria, Dept Construct Econ, ZA-0002 Pretoria, South Africa
[2] Ivanhoe Mines Mongolia Inc, Ulaanbaatar, Mongolia
关键词
Construction; delays; acceleration; claims; float; critical path;
D O I
暂无
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
A lack of understanding often exists between contractors, client organisations and consultants as to what may, and what may not, be included in acceleration claims on construction projects. The aim of this article is to create a better understanding of the complexity of acceleration claims. It should also lead to new insights into claim procedures and the substantiation of acceleration costs. The impacts and delays which may result in acceleration claims on a project were analysed as they form the basis for establishing liability in terms of a particular contract. Matters of principle that are applicable to acceleration claims, regardless of the form of contract recommended for use in the South African construction industry, were also examined. The findings indicate that there are significant differences on a number of aspects regarding the calculation of acceleration costs on construction projects between contractors, consultants and employers/developers. The majority of the respondents, however, were of the opinion that of the various methods used for calculating acceleration costs, the time impact analysis is most frequently applied, but that the modified total cost approach is the method most suitable on projects where there is a significant increase in the scope of work, something that occurs regularly on construction projects.
引用
收藏
页码:86 / 102
页数:17
相关论文
共 50 条
  • [42] Methodology for monitoring quality costs in the design of construction projects: Case study
    Alonso Dzul-Lopez, Luis
    Gracia-Villar, Santos
    Gonzalez-Benitez, Margarita
    Fernandez-Diez, Federico
    Cremades-Oliver, Lazaro
    DYNA, 2010, 85 (01): : 47 - 60
  • [43] A method for estimating labour requirements and costs for international construction projects at inception
    Proverbs, DG
    Holt, GD
    Olomolaiye, PO
    BUILDING AND ENVIRONMENT, 1999, 34 (01) : 43 - 48
  • [44] Estimating OHS costs of building construction projects based on mathematical methods
    Akcay, Cemil
    Aslan, Selman
    Sayin, Baris
    Manisali, Ekrem
    SAFETY SCIENCE, 2018, 109 : 361 - 367
  • [45] RSVRs based on Feature Extraction: A Novel Method for Prediction of Construction Projects’ Costs
    Ying Zhang
    Shutian Fang
    KSCE Journal of Civil Engineering, 2019, 23 : 1436 - 1441
  • [46] Particle Swarm Optimization Based Approach for Estimation of Costs and Duration of Construction Projects
    Khalaf, Tarq Zaed
    Caglar, Hakan
    Caglar, Arzu
    Hanoon, Ammar N.
    CIVIL ENGINEERING JOURNAL-TEHRAN, 2020, 6 (02): : 384 - 401
  • [47] Contractors' perception of the use of costs of quality system in Malaysian building construction projects
    Al-Tmeemy, Samiaah M. Hassen
    Abdul-Rahman, Hamzah
    Harun, Zakaria
    INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2012, 30 (07) : 827 - 838
  • [48] Watch Out for the Hidden Costs of Subcontracting in Construction Projects: The Impacts of Subcontractor Dispersion
    Tang, Yinqiu
    Yao, Hongjiang
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2023, 149 (11)
  • [49] CORRECT ACCOUNTING PRINCIPLES IN CONNECTION WITH THE PAYMENT OF CONSTRUCTION COSTS ON FEDERAL IRRIGATION PROJECTS
    Hauter, L. H.
    JOURNAL OF FARM ECONOMICS, 1932, 14 (04): : 687 - 690
  • [50] Estimating road user costs associated with highway construction projects: Simplified method
    Daniels, G.
    Stockton, W.R.
    Hundley, R.
    Transportation Research Record, 2000, (1732) : 70 - 79