The calculation of acceleration costs on construction projects

被引:0
|
作者
Maritz, Tinus [1 ]
Schutte, Andries [2 ]
机构
[1] Univ Pretoria, Dept Construct Econ, ZA-0002 Pretoria, South Africa
[2] Ivanhoe Mines Mongolia Inc, Ulaanbaatar, Mongolia
关键词
Construction; delays; acceleration; claims; float; critical path;
D O I
暂无
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
A lack of understanding often exists between contractors, client organisations and consultants as to what may, and what may not, be included in acceleration claims on construction projects. The aim of this article is to create a better understanding of the complexity of acceleration claims. It should also lead to new insights into claim procedures and the substantiation of acceleration costs. The impacts and delays which may result in acceleration claims on a project were analysed as they form the basis for establishing liability in terms of a particular contract. Matters of principle that are applicable to acceleration claims, regardless of the form of contract recommended for use in the South African construction industry, were also examined. The findings indicate that there are significant differences on a number of aspects regarding the calculation of acceleration costs on construction projects between contractors, consultants and employers/developers. The majority of the respondents, however, were of the opinion that of the various methods used for calculating acceleration costs, the time impact analysis is most frequently applied, but that the modified total cost approach is the method most suitable on projects where there is a significant increase in the scope of work, something that occurs regularly on construction projects.
引用
收藏
页码:86 / 102
页数:17
相关论文
共 50 条
  • [31] Learning Practices as a Tool for Quality Costs Reduction in Construction Projects
    Titov, Sergei
    Nikulchev, Evgeny
    Bubnov, Gregory
    QUALITY-ACCESS TO SUCCESS, 2015, 16 (149): : 68 - 70
  • [32] A Method to Estimate Occupational Health and Safety Costs in Construction Projects
    Pellicer, Eugenio
    Carvajal, Gloria I.
    Carmen Rubio, M.
    Catala, Joaquin
    KSCE JOURNAL OF CIVIL ENGINEERING, 2014, 18 (07) : 1955 - 1965
  • [33] Planning for production in construction: controlling costs in major capital projects
    Caffieri, Jake J.
    Love, Peter E. D.
    Whyte, Andrew
    Ahiaga-Dagbui, Dominic D.
    PRODUCTION PLANNING & CONTROL, 2018, 29 (01) : 41 - 50
  • [34] IMPACTS OF CONSTRUCTION RISKS ON COSTS IN LEED-CERTIFIED PROJECTS
    Gurgun, Asli Pelin
    Arditi, David
    Vilar, Pablo Casals
    JOURNAL OF GREEN BUILDING, 2016, 11 (04): : 163 - 181
  • [35] A Case for Acceleration rather than Extension of time on Construction projects in Uganda
    Ssemwogerere, Kenneth
    CONSTRUCTION AND PROJECT MANAGEMENT, ICCPM 2011, 2011, 15 : 192 - 195
  • [36] The Analysis on the Accounting Methods System of Environmental Costs Focused on the Construction Phase of Construction Projects
    Du, Huishu
    Ge, Maomao
    Zhang, Wei
    Chen, Yingyue
    PROCEEDINGS OF THE 20TH INTERNATIONAL SYMPOSIUM ON ADVANCEMENT OF CONSTRUCTION MANAGEMENT AND REAL ESTATE, 2017, : 425 - 435
  • [37] Incorporating lost productivity calculation into delay analysis for construction projects
    Yang, Jyh-Bin
    Huang, Kuei-Mei
    Lee, Chang-Hung
    Chiu, Chui-Te
    KSCE JOURNAL OF CIVIL ENGINEERING, 2014, 18 (02) : 380 - 388
  • [38] Incorporating lost productivity calculation into delay analysis for construction projects
    Jyh-Bin Yang
    Kuei-Mei Huang
    Chang-Hung Lee
    Chui-Te Chiu
    KSCE Journal of Civil Engineering, 2014, 18 : 380 - 388
  • [39] Ensuring Efficient Incentive and Disincentive Values for Highway Construction Projects: A Systematic Approach Balancing Road User, Agency and Contractor Acceleration Costs and Savings
    Lee, Eul-Bum
    Alleman, Douglas
    SUSTAINABILITY, 2018, 10 (03):
  • [40] Quantifying costs of the productivity loss due to schedule changes in construction projects
    Lee, Jae-Seob
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2023, 30 (01) : 56 - 73