Solving Fuzzy Time–Cost Trade-Off in Construction Projects Using Linear Programming

被引:3
|
作者
Elkalla I. [1 ]
Elbeltagi E. [1 ]
El Shikh M. [1 ]
机构
[1] Structural Engineering Department, Faculty of Engineering, Mansoura University, Mansoura
关键词
Fuzzy time–cost trade-off; Linear programming; Nearest symmetric trapezoidal fuzzy number; Simplex method;
D O I
10.1007/s40030-020-00489-7
中图分类号
学科分类号
摘要
The time–cost trade-off has been recognized as a very significant aspect of construction management. Generally, time–cost trade-off can be modeled as a fuzzy linear programming problem with symmetric or non-symmetric fuzzy numbers. However, it was successfully solved when the fuzzy membership functions are only symmetric. In the present work, a novel approach is introduced to solve fuzzy linear programming problem with non-symmetric fuzzy membership functions by transforming it to its corresponding nearest symmetric one. The transformed problem is then converted to its crisp linear programming problem and then solved by the standard primal simplex method. Two examples are presented to show the effectiveness of the proposed approach, and the results are discussed. © 2020, The Institution of Engineers (India).
引用
收藏
页码:267 / 278
页数:11
相关论文
共 50 条
  • [21] SOLVING FUZZY TIME-COST TRADE-OFF PROBLEM USING HAAR CRITICAL PATH METHOD OF OCTAGONAL FUZZY NUMBERS
    Rameshan, N.
    Dinagar, D. Stephen
    ADVANCES AND APPLICATIONS IN MATHEMATICAL SCIENCES, 2021, 21 (02): : 907 - 922
  • [22] Fuzzy Multi-Mode Time-Cost-Quality Trade-Off Optimization in Construction Management of Hydraulic Structure Projects
    Mendomo Meye, Serges
    Li, Guowei
    Shen, Zhenzhong
    Zhang, Jingbin
    APPLIED SCIENCES-BASEL, 2022, 12 (12):
  • [23] A Dependent-Chance Programming Model for Fuzzy Time-Cost Trade-off Problem
    Ke, Hua
    Ma, Weimin
    2009 IEEE INTERNATIONAL CONFERENCE ON FUZZY SYSTEMS, VOLS 1-3, 2009, : 2183 - 2186
  • [24] A Fuzzy Random Time-Cost Trade-off Model
    Ke, Hua
    Ma, Weimin
    PROCEEDINGS OF THE EIGHTH INTERNATIONAL CONFERENCE ON INFORMATION AND MANAGEMENT SCIENCES, 2009, 8 : 633 - 637
  • [25] Linear programming based approaches for the discrete time/cost trade-off problem in project networks
    Hafizoglu, A. B.
    Azizoglu, M.
    JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 2010, 61 (04) : 676 - 685
  • [26] A GOAL PROGRAMMING-MODEL FOR PROJECT CRASHING WITH PIECEWISE LINEAR TIME COST TRADE-OFF
    VRAT, P
    KRIENGKRAIRUT, C
    ENGINEERING COSTS AND PRODUCTION ECONOMICS, 1986, 10 (02): : 161 - 172
  • [27] Stochastic construction time-cost trade-off analysis
    Feng, CW
    Liu, L
    Burns, SA
    JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2000, 14 (02) : 117 - 126
  • [28] Time-cost trade-off problem in construction project management, based on fuzzy logic
    Abbasnia, R.
    Afshar, A.
    Eshtehardian, E.
    Journal of Applied Sciences, 2008, 8 (22) : 4159 - 4165
  • [29] Multi-objective Genetic Algorithm for the Time, Cost, and Quality Trade-Off Analysis in Construction Projects
    Bragadin, Marco Alvise
    Pozzi, Luca
    Kahkonen, Kalle
    SDGS IN CONSTRUCTION ECONOMICS AND ORGANIZATION, CREON 2022, 2023, : 193 - 207
  • [30] Adaptive opposition slime mold algorithm for time–cost–quality–safety trade-off for construction projects
    Son P.V.H.
    Khoi L.N.Q.
    Asian Journal of Civil Engineering, 2023, 24 (7) : 1927 - 1942