Project time–cost trade-off scheduling: a hybrid optimization approach

被引:0
|
作者
Hadi Mokhtari
Abdollah Aghaie
Javad Rahimi
Ashkan Mozdgir
机构
[1] K.N. Toosi University of Technology,Industrial Engineering Department
[2] Mazandaran University of Science and Technology,Industrial Engineering Department
关键词
Project scheduling; Time–cost trade-off; Hybrid approach; Cutting plane; Optimization;
D O I
暂无
中图分类号
学科分类号
摘要
This paper develops a hybrid approach for stochastic time–cost trade-off problem (STCTP) in PERT networks of project management, where activities are subjected to linear cost functions. The main objective of proposed approach is to improve the project completion probability in a prespecified deadline from a risky value to a confident predefined probability. To this end, we construct a nonlinear mathematical program with decision variables of activity mean durations, in which the objective function is concerned with minimization of project crashing direct cost. In order to solve the constructed model, we present a hybrid approach based on cutting plane method and Monte Carlo (MC) simulation. To illustrate the process of proposed approach, the approach was coded using MATLAB 7.6.0 and two illustrative examples are discussed. The results obtained from the computational study show that the proposed algorithm is an effective approach for the STCTP.
引用
收藏
页码:811 / 822
页数:11
相关论文
共 50 条
  • [21] Hybrid time-quality-cost trade-off problems
    Kosztyan, Zsolt T.
    Szalkai, Istvan
    OPERATIONS RESEARCH PERSPECTIVES, 2018, 5 : 306 - 318
  • [22] Time-cost-quality-environmental impact trade-off resource-constrained project scheduling problem with DEA approach
    Banihashemi, Sayyid Ali
    Khalilzadeh, Mohammad
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2021, 28 (07) : 1979 - 2004
  • [23] Project scheduling with time, cost and risk trade-off using adaptive multiple objective differential evolution
    Duc Hoc Tran
    Luong Duc Long
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2018, 25 (05) : 623 - 638
  • [24] Optimization of environmental impacts of construction projects: a time–cost–quality trade-off approach
    S. A. Banihashemi
    Mohammad Khalilzadeh
    A. Shahraki
    M. Rostami Malkhalifeh
    S. S. R. Ahmadizadeh
    International Journal of Environmental Science and Technology, 2021, 18 : 631 - 646
  • [25] Scheduling parallel CNC machines with time/cost trade-off considerations
    Gurel, Sinan
    Akturk, M. Selim
    COMPUTERS & OPERATIONS RESEARCH, 2007, 34 (09) : 2774 - 2789
  • [26] A TRADE-OFF BETWEEN TIME AND COST IN SCHEDULING REPETITIVE CONSTRUCTION PROJECTS
    Zhang, Lihui
    Zou, Xin
    Qi, Jianxun
    JOURNAL OF INDUSTRIAL AND MANAGEMENT OPTIMIZATION, 2015, 11 (04) : 1423 - 1434
  • [27] Time, cost and quality trade-off in project management: A case study
    Asia Inst of Technology, Bangkok, Thailand
    Int J Proj Manage, 4 (249-256):
  • [28] Time-cost Trade-off Analysis of Project Using Fuzzy-Genetic Approach
    Glisovic, Natasa
    ECONOMICS AND SOCIAL SCIENCE, 2013, 13 : 121 - 126
  • [29] An overview of the time-cost trade-off problems of project planning
    Csordas, Helga
    CREATIVE CONSTRUCTION CONFERENCE 2017, CCC 2017, 2017, 196 : 323 - 326
  • [30] Multi-objective time-cost trade-off optimization for the construction scheduling with Rao algorithms
    Yilmaz, Mehmet
    Dede, Tayfun
    STRUCTURES, 2023, 48 : 798 - 808