Factors influencing Time and Cost Overruns on Freeform Construction Projects

被引:0
|
作者
Andrew Kavuma
Jongho Ock
Hyounseung Jang
机构
[1] Seoul National University of Science and Technology,School of Architecture
来源
关键词
time overruns; cost overruns; freeform projects; Building Information Modeling (BIM); latent factors;
D O I
暂无
中图分类号
学科分类号
摘要
Freeform buildings differ from conventional buildings in a way that they have irregularly shaped facades. Oftentimes, freeform projects run behind schedule and over the budget. This study aimed at exploring factors that influence time and cost overruns on freeform buildings. The study employed questionnaire surveys to collect data from experts with freeform project experience, and the responses were analyzed using R statistical program. The study used exploratory factor analysis to identify the most critical latent factors to freeform project success. The study found factors related to application of Building Information Modeling (BIM) and fabrication of freeform components as very crucial to timely completion, whereas factors related to personnel involved as essential to completing within budget. Additionally, the study summarized time overrun variables into three latent factors; uniqueness, capabilities and practices of the parties involved, and level of preparation for the project. The cost overrun latent factors were: cost uncertainty, client decisions, extent of preparation, and delay. Understanding the causes of time and cost overruns on freeform buildings identified in this study can help clients make informed decisions regarding undertaking freeform projects as well as help consultants and contractors minimize the risk of encountering such overruns.
引用
收藏
页码:1442 / 1450
页数:8
相关论文
共 50 条
  • [41] Analysis of delays and cost overruns of road construction projects in the Colombian Caribbean Region
    Canales, Fausto A.
    Mora, Otto
    Arrieta-Castro, Marco
    Moreno-Natera, Anibal
    del Savio, Alexandre
    BULLETIN OF GEOGRAPHY-SOCIO-ECONOMIC SERIES, 2023, 61 (61) : 59 - 70
  • [42] FACTORS INFLUENCING THE CHOICE OF COST ESTIMATES TYPES AND THE ACCURACY OF ESTIMATES FOR CONSTRUCTION PROJECTS
    Simion-Melinte, Cezar
    PROCEEDINGS OF THE 10TH INTERNATIONAL MANAGEMENT CONFERENCE: CHALLENGES OF MODERN MANAGEMENT (IMC 2016), 2016, : 50 - 56
  • [43] Cost and time risk factors in construction projects in the Dominican Republic
    Fernandez-Valderrama, Pedro
    Urena-Estrella, Crismal
    Moyano, Juan
    Bienvenido-Huertas, David
    FRONTIERS IN BUILT ENVIRONMENT, 2024, 10
  • [44] Critical Factors Influencing Cost Overrun in Construction Projects: A Fuzzy Synthetic Evaluation
    Xie, Wenwen
    Deng, Binchao
    Yin, Yilin
    Lv, Xindong
    Deng, Zhenhua
    BUILDINGS, 2022, 12 (11)
  • [45] ANALYSIS AND DEVELOPMENT OF A MODEL FOR THE CAUSES OF COST AND TIME OVERRUNS IN ENGINEERING PROJECTS
    Masood, Syed Athar
    2012 ASEE ANNUAL CONFERENCE, 2012,
  • [46] Time and cost overruns in the UAE construction industry: a critical analysis
    Johnson, Reshma Mary
    Babu, Robin Itty Ipe
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2020, 20 (05) : 402 - 411
  • [47] Construction claims and disputes: Causes and cost/time overruns - Discussion
    McDonald, DF
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1996, 122 (02): : 197 - 198
  • [48] Investigation into the Causes of Delays and Cost Overruns in Uganda's Public Sector Construction Projects
    Alinaitwe, Henry
    Apolot, Ruth
    Tindiwensi, Dan
    JOURNAL OF CONSTRUCTION IN DEVELOPING COUNTRIES, 2013, 18 (02) : 33 - 47
  • [49] Risk factors contributing to cost overruns in implementing public sector projects in China
    Shen, LY
    Deng, XP
    PROCEEDINGS OF CRIOCM 2005 INTERNATIONAL RESEARCH SYMPOSIUM ON ADVANCEMENT OF CONSTRUCTION MANAGEMENT AND REAL ESTATE, 2005, : 513 - 520
  • [50] Delay and Cost Overruns in Vietnam Large Construction Projects: A Comparison with Other Selected Countries
    Le-Hoai, Long
    Lee, Young Dai
    Lee, Jun Yong
    KSCE JOURNAL OF CIVIL ENGINEERING, 2008, 12 (06) : 367 - 377