Factors influencing Time and Cost Overruns on Freeform Construction Projects

被引:0
|
作者
Andrew Kavuma
Jongho Ock
Hyounseung Jang
机构
[1] Seoul National University of Science and Technology,School of Architecture
来源
关键词
time overruns; cost overruns; freeform projects; Building Information Modeling (BIM); latent factors;
D O I
暂无
中图分类号
学科分类号
摘要
Freeform buildings differ from conventional buildings in a way that they have irregularly shaped facades. Oftentimes, freeform projects run behind schedule and over the budget. This study aimed at exploring factors that influence time and cost overruns on freeform buildings. The study employed questionnaire surveys to collect data from experts with freeform project experience, and the responses were analyzed using R statistical program. The study used exploratory factor analysis to identify the most critical latent factors to freeform project success. The study found factors related to application of Building Information Modeling (BIM) and fabrication of freeform components as very crucial to timely completion, whereas factors related to personnel involved as essential to completing within budget. Additionally, the study summarized time overrun variables into three latent factors; uniqueness, capabilities and practices of the parties involved, and level of preparation for the project. The cost overrun latent factors were: cost uncertainty, client decisions, extent of preparation, and delay. Understanding the causes of time and cost overruns on freeform buildings identified in this study can help clients make informed decisions regarding undertaking freeform projects as well as help consultants and contractors minimize the risk of encountering such overruns.
引用
收藏
页码:1442 / 1450
页数:8
相关论文
共 50 条
  • [31] Factors Influencing the Construction Cost of Industrialised Building System (IBS) Projects
    Bari, Nor Azmi Ahmad
    Yusuff, Rosnah
    Ismail, Napsiah
    Jaapar, Aini
    Ahmad, Norizan
    AICE-BS 2011 FAMAGUSTA (ASIA PACIFIC INTERNATIONAL CONFERENCE ON ENVIRONMENT-BEHAVIOUR STUDIES), 2012, 35 : 689 - 696
  • [32] Construction claims and disputes: causes and cost/time overruns
    Semple, Cheryl
    Hartman, Francis T.
    Jergeas, George
    Journal of Construction Engineering and Management, 1994, 120 (04) : 785 - 795
  • [33] Factors influencing the construction time of civil engineering projects in Malaysia
    Othman, Ahmad
    Torrance, Johan
    Hamid, Munshi
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2006, 13 (05) : 481 - +
  • [34] Time and Cost Overruns on Large Projects: Understanding the Root Cause
    Simushi, Sitwala
    Wium, Jan
    JOURNAL OF CONSTRUCTION IN DEVELOPING COUNTRIES, 2020, 25 (01) : 129 - 146
  • [35] Managing Cost Risks in Oil and Gas Construction Projects: Root Causes of Cost Overruns
    Esmaeili, Iraj
    Kashani, Hamed
    ASCE-ASME JOURNAL OF RISK AND UNCERTAINTY IN ENGINEERING SYSTEMS PART A-CIVIL ENGINEERING, 2022, 8 (01)
  • [36] Investigation on the Factors Influencing Construction Time and Cost Overrun for High-Rise Building Projects In Penang
    Haslinda, A. Nor
    Xian, T. Wei
    Norfarahayu, K.
    Hanafi, R. Muhamad
    Fikri, H. Muhammad
    INTERNATIONAL SEMINAR ON MATHEMATICS AND PHYSICS IN SCIENCES AND TECHNOLOGY 2017 (ISMAP 2017), 2018, 995
  • [37] COST ESCALATION, SCHEDULE OVERRUNS AND QUALITY SHORTFALLS ON CONSTRUCTION PROJECTS: THE CASE OF ZAMBIA
    Muya, Mundia
    Kaliba, Chabota
    Sichombo, Balimu
    Shakantu, Winston
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2013, 13 (01) : 53 - 68
  • [38] Federal projects experience cost overruns
    不详
    CIVIL ENGINEERING, 1999, 69 (11): : 28 - 28
  • [39] Significant Factors Causing Cost Overruns in the Construction Industry in Afghanistan
    Niazi, Ghulam Abbas
    Painting, Noel
    7TH INTERNATIONAL CONFERENCE ON ENGINEERING, PROJECT, AND PRODUCTION MANAGEMENT, 2017, 182 : 510 - 517
  • [40] An Analysis of Factors Contributing to Cost Overruns in the Global Construction Industry
    Abdelalim, Ahmed Mohammed
    Salem, Maram
    Salem, Mohamed
    Al-Adwani, Manal
    Tantawy, Mohamed
    BUILDINGS, 2025, 15 (01)