Resource-constrained Scheduling of a Real Project from the Construction Industry: A Comparison of Software Packages for Project Management

被引:4
|
作者
Trautmann, N. [1 ]
Baumann, P. [1 ]
机构
[1] Univ Bern, Dept Business Adm, Bern, Switzerland
关键词
Project management; resource-constrained scheduling; construction industry; software; ALLOCATION; MICROCOMPUTER;
D O I
10.1109/IEEM.2009.5373255
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Commercial software packages for project management apply proprietary, heuristic procedures for resource-constrained scheduling. We analyze the scheduling performance of seven such packages. Three of them offer the possibility to select the priority rule to be used for the resource-constrained scheduling procedure. The project duration obtained strongly depends on this rule. Some packages know several thousand priority rules; in general, it is impossible to predict which rule provides the best result for a given project. By analyzing 1560 projects of an internationally recognized benchmark library, we propose a set of three rules for each package. We apply these rules to a real project from the construction industry. For each of the three packages, the project duration obtained by this set of rules is among the best results for all available rules, and is shorter than the project duration obtained by the packages which do not offer alternative priority rules.
引用
收藏
页码:628 / 632
页数:5
相关论文
共 50 条
  • [41] Pre-emption in resource-constrained project scheduling
    Ballestin, Francisco
    Valls, Vicente
    Quintanilla, Sacramento
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2008, 189 (03) : 1136 - 1152
  • [42] The proactive and reactive resource-constrained project scheduling problem
    Morteza Davari
    Erik Demeulemeester
    Journal of Scheduling, 2019, 22 : 211 - 237
  • [43] Periodically aggregated resource-constrained project scheduling problem
    Morin, Pierre-Antoine
    Artigues, Christian
    Hait, Alain
    EUROPEAN JOURNAL OF INDUSTRIAL ENGINEERING, 2017, 11 (06) : 792 - 817
  • [44] MILP Formulation for Resource-Constrained Project Scheduling Problems
    Kyriakidis, Thomas S.
    Kopanos, Georgios M.
    Georgiadis, Michael C.
    21ST EUROPEAN SYMPOSIUM ON COMPUTER AIDED PROCESS ENGINEERING, 2011, 29 : 880 - 884
  • [45] Ant colony optimization for resource-constrained project scheduling
    Merkle, D
    Middendorf, M
    Schmeck, H
    IEEE TRANSACTIONS ON EVOLUTIONARY COMPUTATION, 2002, 6 (04) : 333 - 346
  • [46] Integration of routing into a resource-constrained project scheduling problem
    Lacomme, Philippe
    Moukrim, Aziz
    Quilliot, Alain
    Vinot, Marina
    EURO JOURNAL ON COMPUTATIONAL OPTIMIZATION, 2019, 7 (04) : 421 - 464
  • [47] An efficient hybrid algorithm for resource-constrained project scheduling
    Chen, Wang
    Shi, Yan-jun
    Teng, Hong-fei
    Lan, Xiao-ping
    Hu, Li-chen
    INFORMATION SCIENCES, 2010, 180 (06) : 1031 - 1039
  • [48] A hybrid metaheuristic for the resource-constrained project scheduling problem
    Tseng, Lin-Yu
    Chen, Shih-Chieh
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2006, 175 (02) : 707 - 721
  • [49] Resource-constrained project scheduling: A survey of recent developments
    Herroelen, W
    De Reyck, B
    Demeulemeester, E
    COMPUTERS & OPERATIONS RESEARCH, 1998, 25 (04) : 279 - 302
  • [50] Memetic algorithm for the resource-constrained project scheduling problem
    Chen, Di
    Liu, Shixin
    Qin, Shujin
    2014 11TH WORLD CONGRESS ON INTELLIGENT CONTROL AND AUTOMATION (WCICA), 2014, : 4991 - 4996