In this article two approaches of Tabu Search in Multi-Skill Resource-Constrained Project Scheduling Problem (MS-RCPSP) have been proposed, based on different neighbourhood generation methods. The first approach assumes swapping resources assigned to pair of tasks, while the second one proposes assigning any resource that could perform given task. Both approaches need to respect the skill constraints. The objective of this paper is to research the usability and robustness of proposed approaches in solving MS-RCPSP. Experiments have been performed using artificially created dataset instances, based on real-world instances, got from Volvo IT and verified by experienced project manager. Presented results show that Tabu Search (TS) based methods are efficient approaches that could be developed in the further work.
引用
收藏
页码:153 / 158
页数:6
相关论文
共 50 条
  • [1] A Tabu Search Approach for the Resource Constrained Project Scheduling Problem
    Paul R. Thomas
    Said Salhi
    Journal of Heuristics, 1998, 4 : 123 - 139
  • [2] A tabu search approach for the resource constrained project scheduling problem
    Thomas, PR
    Salhi, S
    JOURNAL OF HEURISTICS, 1998, 4 (02) : 123 - 139
  • [3] GRASP Applied to Multi-Skill Resource-Constrained Project Scheduling Problem
    Myszkowski, Pawel B.
    Siemienski, Jedrzej J.
    COMPUTATIONAL COLLECTIVE INTELLIGENCE, ICCCI 2016, PT I, 2016, 9875 : 402 - 411
  • [4] An Improved Tabu Search for Multi-skill Resource-Constrained Project Scheduling Problems Under Step-Deterioration
    Dai, Huafeng
    Cheng, Wenming
    Guo, Peng
    ARABIAN JOURNAL FOR SCIENCE AND ENGINEERING, 2018, 43 (06) : 3279 - 3290
  • [5] An Improved Tabu Search for Multi-skill Resource-Constrained Project Scheduling Problems Under Step-Deterioration
    Huafeng Dai
    Wenming Cheng
    Peng Guo
    Arabian Journal for Science and Engineering, 2018, 43 : 3279 - 3290
  • [6] Weighted Multi-Skill Resource Constrained Project Scheduling: A Greedy and Parallel Scheduling Approach
    Akbar, Saeed
    Zubair, Muhammad
    Khan, Rizwan
    Ul Akbar, Ubaid
    Ullah, Rahmat
    Zheng, Zhonglong
    IEEE ACCESS, 2024, 12 : 29824 - 29836
  • [7] A genetic programming hyper-heuristic approach for the multi-skill resource constrained project scheduling problem
    Lin, Jian
    Zhu, Lei
    Gao, Kaizhou
    EXPERT SYSTEMS WITH APPLICATIONS, 2020, 140
  • [8] A Constraint Programming Approach to Solve Multi-skill Resource-constrained Project Scheduling Problem with Calendars
    Nikaeen, R.
    Najafi, A.A.
    International Journal of Engineering, Transactions B: Applications, 2022, 35 (08):
  • [9] A Constraint Programming Approach to Solve Multi-skill Resource-constrained Project Scheduling Problem with Calendars
    Nikaeen, R.
    Najafi, A. A.
    INTERNATIONAL JOURNAL OF ENGINEERING, 2022, 35 (08): : 1579 - 1587
  • [10] Priority-based heuristics for the multi-skill resource constrained project scheduling problem
    Almeida, Bernardo F.
    Correia, Isabel
    Saldanha-da-Gama, Francisco
    EXPERT SYSTEMS WITH APPLICATIONS, 2016, 57 : 91 - 103