Analysis of Dalian Subway Tunnel Shield Construction Impact with Engineering Materials and Engineering Mechanics on Existing Bridge Pier

被引:1
|
作者
Li, Jinkui [1 ]
Hou, Qinghao [1 ]
Liang, Wenjing [1 ]
机构
[1] Dalian Univ, Civil Engn Coll, Dalian 116600, Peoples R China
关键词
shield construction; existing bridge; surface subsidence; pier settlement;
D O I
10.4028/www.scientific.net/AMR.848.96
中图分类号
O69 [应用化学];
学科分类号
081704 ;
摘要
In the 202 section of subway shield Dalian interval in close proximity to existing bridge as the basis, the surface settlement and bridge pier settlement observation station are established. By the 62 day of the crossing construction monitoring, the monitoring data are analyzed in detail. When surface subsidence induced by shield tunnel construction, above the measuring point start speed is faster than settling startup speed measuring points on both sides, about 2-2.5 times, subsidence range higher about 8 to 10 m ahead of time. Away from the pier side first started, and start faster than the side near the pier,is about 1.2 times, settlement of shield construction are mainly concentrated in the distance before and after the excavation of shield machine 10 m, accounting for 80.72%-81.6% of the total settlement. At highest risk for shield construction area, we should strengthen monitoring and make contingency plans in a timely manner.
引用
收藏
页码:96 / 99
页数:4
相关论文
共 50 条
  • [41] The monitoring and analysis of surface subsidence of Soft soil rock large section of subway tunnel shield construction
    Li, Jinkui
    Yan, Bingwei
    Shi, Yongjian
    ADVANCED RESEARCH ON ENERGY, CHEMISTRY AND MATERIALS APPLICATION, 2014, 848 : 78 - 82
  • [42] Field test and calculation analysis on mechanics characteristics of double-shield TBM tunnel segments in urban subway
    Wang L.
    Sun Z.
    Zhou J.
    Zhang B.
    Li H.
    Yang Z.
    Zhai Q.
    Meitan Xuebao/Journal of the China Coal Society, 2019, 44 : 502 - 508
  • [43] The Risk Analysis and Evaluation of Shanghai Changjiang Tunnel and Bridge Engineering Projects
    Zhang Guo-an
    2010 INTERNATIONAL CONFERENCE ON INNOVATIVE COMPUTING AND COMMUNICATION AND 2010 ASIA-PACIFIC CONFERENCE ON INFORMATION TECHNOLOGY AND OCEAN ENGINEERING: CICC-ITOE 2010, PROCEEDINGS, 2010, : 342 - 346
  • [44] Subsidence analysis of ELH Bridge through ground-based interferometric radar during the crossing of a subway shield tunnel underneath the bridge
    Zhou, Lv
    Guo, Jiming
    Hu, Jiyuan
    Ma, Jun
    Wei, Fuhong
    Xue, Xiaoyan
    INTERNATIONAL JOURNAL OF REMOTE SENSING, 2018, 39 (06) : 1911 - 1928
  • [45] Analysis of the Impact of the New Two-Lane Shield Tunnel Underpass on the Existing Tunnels
    Li, Jinkui
    Fang, Xinxia
    Yang, Yu
    APPLIED SCIENCES-BASEL, 2025, 15 (05):
  • [46] Numerical simulation of the influences of new over-crossing tunnel's blasting construction on existing tunnel and engineering countermeasures
    Lu, Yujie
    Xie, Yongtao
    Ding, Xiang
    Zhongguo Tiedao Kexue/China Railway Science, 2012, 33 (SUPPL. 1): : 104 - 110
  • [47] On-site measurement and environmental impact of vibration caused by construction of double-shield TBM tunnel in urban subway
    Wang, Zhenyong
    Jiang, Yusheng
    Shao, Xiaokang
    Liu, Chenglong
    SCIENTIFIC REPORTS, 2023, 13 (01)
  • [48] On-site measurement and environmental impact of vibration caused by construction of double-shield TBM tunnel in urban subway
    Zhenyong Wang
    Yusheng Jiang
    Xiaokang Shao
    Chenglong Liu
    Scientific Reports, 13
  • [49] Tunnel Engineering Construction Schedule Analysis and Management Based on Visual Simulation
    宋洋
    钟炜
    Transactions of Tianjin University, 2007, (02) : 131 - 136
  • [50] Coupled fluid-mechanical analysis of DOT shield tunnel construction beneath adjacent existing underpass
    Chen Yu
    Zhang Qing-he
    Zhu Ji-wen
    Yao Hai-ming
    ROCK AND SOIL MECHANICS, 2010, 31 (06) : 1950 - +