A TRADE-OFF BETWEEN TIME AND COST IN SCHEDULING REPETITIVE CONSTRUCTION PROJECTS

被引:21
|
作者
Zhang, Lihui [1 ]
Zou, Xin [1 ]
Qi, Jianxun [1 ]
机构
[1] North China Elect Power Univ, Sch Econ & Management, Beijing 102206, Peoples R China
关键词
Soft logic; repetitive construction projects; time/cost trade-off; scheduling; LINEAR PROJECTS; MODEL; OPTIMIZATION; ALGORITHM; PATH;
D O I
10.3934/jimo.2015.11.1423
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
The discrete time/cost trade-off problem (DTCTP) is commonly encountered in repetitive project scheduling. The current models for this problem assume that logical sequences of activities cannot be changed in different units. However, logical sequences are often changed to shorten the project time and minimize project total cost in many practical situations. This characteristic of repetitive activities is referred to as the soft logic. This paper presents a mixed integer nonlinear programming model that combines the general DTCTP and the concept of soft logic. The execution modes of an activity in different units are also considered. The DTCTP is known to be strongly NP-hard, and the introduction of soft logic makes it even more complex. A genetic algorithm (GA) is proposed to resolve the problem. The effectiveness of the proposed GA is verified using the example of a bridge construction project presented in the previous literature. The model proposed in this paper provides more flexibility to reduce the total cost and time of a repetitive project for the planners.
引用
收藏
页码:1423 / 1434
页数:12
相关论文
共 50 条
  • [41] Time and cost trade-off management for scheduling parallel applications on Utility Grids
    Garg, Saurabh Kumar
    Buyya, Rajkumar
    Siegel, Howard Jay
    FUTURE GENERATION COMPUTER SYSTEMS-THE INTERNATIONAL JOURNAL OF GRID COMPUTING-THEORY METHODS AND APPLICATIONS, 2010, 26 (08): : 1344 - 1355
  • [42] Developing an optimization financing cost-scheduling trade-off model in construction project
    Tavakolan, Mehdi
    Nikoukar, Shayan
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2022, 22 (02) : 262 - 277
  • [43] Robust scheduling and robustness measures for the discrete time/cost trade-off problem
    Hazir, Oencue
    Haouari, Mohamed
    Erel, Erdal
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2010, 207 (02) : 633 - 643
  • [44] Optimizing sustainable construction projects through LNSGA III: a time-cost-environmental impact trade-off approach
    Bohra P.
    Verma R.S.
    Asian Journal of Civil Engineering, 2024, 25 (5) : 4343 - 4354
  • [45] Fuzzy Multicriteria Decision-Making Model for Time-Cost-Risk Trade-Off Optimization in Construction Projects
    Alzarrad, M. Ammar
    Moynihan, Gary P.
    Hatamleh, Muhammad T.
    Song, Siyuan
    ADVANCES IN CIVIL ENGINEERING, 2019, 2019
  • [46] TIME-COST TRADE-OFF FOR AIRLINERS
    HARTLEY, K
    CORCORAN, W
    JOURNAL OF INDUSTRIAL ECONOMICS, 1978, 26 (03): : 209 - 222
  • [47] Application of fuzzy BWM-CoCoSo to time–cost–environmental impact trade-off construction project scheduling problem
    S. A. Banihashemi
    M. Khalilzadeh
    International Journal of Environmental Science and Technology, 2023, 20 : 1199 - 1214
  • [48] SCTTS: Scalable Cost-Time Trade-off Scheduling for Workflow Application in Grids
    Khajehvand, Vahid
    Pedram, Hossein
    Zandieh, Mostafa
    KSII TRANSACTIONS ON INTERNET AND INFORMATION SYSTEMS, 2013, 7 (12): : 3096 - 3117
  • [49] A trade-off method between cost and reliability
    Burnett, R
    XVII INTERNATIONAL CONFERENCE OF THE CHILEAN COMPUTER SCIENCE SOCIETY, PROCEEDINGS, 1997, : 21 - 28
  • [50] A Developmental Genetic Approach to the cost/time trade-off in Resource Constrained Project Scheduling
    Pawinski, Grzegorz
    Sapiecha, Krzysztof
    FEDERATED CONFERENCE ON COMPUTER SCIENCE AND INFORMATION SYSTEMS, 2014, 2014, 2 : 171 - 179