Assessing and Prioritising Delay Factors of Prefabricated Concrete Building Projects in China

被引:47
|
作者
Ji, Yingbo [1 ]
Qi, Lin [1 ]
Liu, Yan [1 ]
Liu, Xinnan [1 ]
Li, Hong Xian [2 ]
Li, Yan [2 ]
机构
[1] North China Univ Technol, Dept Civil Engn, Beijing 100043, Peoples R China
[2] Deakin Univ, Sch Architecture & Built Environm, Geelong, Vic 3220, Australia
来源
APPLIED SCIENCES-BASEL | 2018年 / 8卷 / 11期
基金
国家重点研发计划;
关键词
construction delay; prefabricated construction; decision-making trial and evaluation laboratory (DEMATEL); analytic network process (ANP); multi-criteria decision making; ROAD CONSTRUCTION PROJECTS; HIERARCHY PROCESS AHP; SCHEDULE RISK; HONG-KONG; MANAGEMENT; COST; DEMATEL; PERSPECTIVE; OPPORTUNITY; SIMULATION;
D O I
10.3390/app8112324
中图分类号
O6 [化学];
学科分类号
0703 ;
摘要
Prefabricated construction has been widely accepted as an alternative to conventional cast-in-situ construction, given its improved performance. However, prefabricated concrete building projects frequently encounter significant delays. It is, therefore, crucial to identify key factors affecting schedule and explore strategies to minimise the schedule delays for prefabricated concrete building projects. This paper adopts the decision-making trial and evaluation laboratory (DEMATEL) model and analytic network process (ANP) method to quantify the cause-and-effect relationships and prioritise the key delay factors in terms of their importance in the Chinese construction industry. The DEMATEL model evaluates the extent to which each factor impacts other factors. The quantified extents are then converted into a prioritisation matrix through ANP. The delay factors of prefabricated construction projects are selected and categorised based on a literature review and an expert interview. Questionnaires are then implemented to collect the data. The results reveal that the issue of inefficient structural connections for prefabricated components is found to be the most significant factor and most easily affected by other delay factors. This research also suggests prioritising major delay factors, such as lack of communication among participants' and low productivity', in the Chinese construction industry during scheduling control. Overall, this research contributes an assessment framework for decision making in the scheduling management of prefabricated construction.
引用
收藏
页数:16
相关论文
共 50 条
  • [21] CAUSES OF DELAY IN LARGE BUILDING CONSTRUCTION PROJECTS
    ASSAF, SA
    ALKHALIL, M
    ALHAZMI, M
    JOURNAL OF MANAGEMENT IN ENGINEERING, 1995, 11 (02) : 45 - 50
  • [22] Causes of Delay in Building Construction Projects in Egypt
    El-Razek, M. E. Abd
    Bassioni, H. A.
    Mobarak, A. M.
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2008, 134 (11) : 831 - 841
  • [23] Monitoring Method of Vertical Stress on Precast Concrete of Prefabricated Building
    Tian, Manli
    FORTHCOMING NETWORKS AND SUSTAINABILITY IN THE IOT ERA (FONES-IOT 2021), VOL 1, 2022, 129 : 220 - 227
  • [24] Stakeholder Perceptions of Transaction Costs in Prefabricated Housing Projects in China
    Wu, Hongjuan
    Qian, Queena K.
    Straub, Ad
    Visscher, Henk
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2021, 147 (01)
  • [25] Development and analysis of prefabricated concrete buildings in Chengdu, China
    Yao G.
    Wang M.
    Yang Y.
    Li J.
    International Journal of Sustainable Development and Planning, 2020, 15 (03): : 403 - 411
  • [26] Identifying and Assessing Influence Factors on Improving Waste Management Performance for Building Construction Projects
    Cha, Hee Sung
    Kim, Jeehye
    Han, Ju-Yeoun
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2009, 135 (07): : 647 - 656
  • [27] Visualization of Component Status Information of Prefabricated Concrete Building Based on Building Information Modeling and Radio Frequency Identification: A Case Study in China
    Ma, Guofeng
    Jiang, Jun
    Shang, Shanshan
    ADVANCES IN CIVIL ENGINEERING, 2019, 2019
  • [28] Assessing the performance of sustainable technologies for building projects
    Nelms, C
    Russell, AD
    Lence, BJ
    CANADIAN JOURNAL OF CIVIL ENGINEERING, 2005, 32 (01) : 114 - 128
  • [29] Research on Influencing Factors of Unsafe Behavior of Prefabricated Building
    Wang, Xiaowen
    Sun, Yucheng
    Liu, Yan
    2020 6TH INTERNATIONAL CONFERENCE ON ADVANCES IN ENERGY, ENVIRONMENT AND CHEMICAL ENGINEERING, PTS 1-5, 2020, 546
  • [30] Performance Comparison of Prefabricated Building Construction Projects vs. Traditional On-site Construction Projects
    Wasana, K. H., I
    Gunatilake, Sachie
    Fasna, M. F. F.
    2019 MORATUWA ENGINEERING RESEARCH CONFERENCE (MERCON) / 5TH INTERNATIONAL MULTIDISCIPLINARY ENGINEERING RESEARCH CONFERENCE, 2019, : 169 - 174