Olympic Dam operations review

被引:0
|
作者
Webb, D [1 ]
机构
[1] WMC Olympic Dam, Roxby Downs, SA 5725, Australia
来源
SEVENTH AUSIMM UNDERGROUND OPERATORS' CONFERENCE | 1998年 / 98卷 / 03期
关键词
D O I
暂无
中图分类号
TD [矿业工程];
学科分类号
0819 ;
摘要
The Olympic Dam copper/uranium deposit was discovered in 1975 and subsequently commenced production in 1988 at a rate of 1.5 Mtpa using the sublevel open stoping mining method. In the following five years the operation underwent two optimisation programs that have increased mine output to the current rate of 3.4 Mtpa of ore. The pre-expansion requirements were annual development of approximately 10 000 m and the placement of around 500 000 m(3)/yr of cemented backfill. Previous to 1995 all hoisting was carried out by the Whenan shaft. The Robinson shaft was commissioned during that year to hoist increasing development mullock tonnages and to allow for increased ore hoist via the Whenan system. In 1996 WMC committed to expanding the output of the operation from 85 000 tpa (1996/97 budget) copper metal to 200 000 tpa. The corresponding increase in mine ore production requires expansion to a nominal rate of 9.0 Mtpa. To achieve these increased tonnages, major hardware installations will include sinking of a third shaft capable of hoisting in excess of 9.5 Mtpa, a rail haulage horizon utilising automatic trains, expansion of the existing backfill plant to a production capacity of over 1.8 million m(3)/yr, increasing long term development rates to 15 000 m/yr and increasing the production drilling and blasting rates in line with the higher stope production output. This paper provides detail into the intended hardware (shafts, equipment, etc) of the mining system, and outlines the intended longterm operation and management of the operation. Of particular note is the background requirement of ensuring existing production targets are met to provide critical cashflows into the project during the period of expansion.
引用
收藏
页码:87 / 94
页数:8
相关论文
共 50 条
  • [41] Prehistoric mining at Olympic Dam in arid South Australia
    Sullivan, Marjorie
    Hughes, Philip
    Way, Amy Mosig
    Spooner, Nigel
    ARCHAEOLOGY IN OCEANIA, 2014, 49 (01) : 43 - 55
  • [42] CONCRETE OPERATIONS OF ARCH GRAVITY DAM
    RIFF, S
    REVUE FRANCAISE DE RECHERCHE OPERATIONNELE, 1966, 10 (38): : 93 - 93
  • [43] Modified storm operations at Bradbury Dam
    Fiedler, WR
    REDUCING RISK FROM EXTREME EVENTS, 2003, : 393 - 402
  • [44] Increasing throughput at Olympic Dam by effective management of the mine bottleneck
    Bloss, M.
    TRANSACTIONS OF THE INSTITUTIONS OF MINING AND METALLURGY SECTION A-MINING TECHNOLOGY, 2009, 118 (01): : 33 - 46
  • [45] WMC's Olympic Dam faces major furnace repairs
    不详
    E&MJ-ENGINEERING AND MINING JOURNAL, 2002, 203 (08): : 7 - 7
  • [46] WMC's olympic dam faces major furnace repairs
    Anon
    Engineering and Mining Journal, 2002, 203 (08):
  • [47] BHP Billiton Profit Drops; Olympic Dam Study Extended
    不详
    E&MJ-ENGINEERING AND MINING JOURNAL, 2012, 213 (09): : 7 - 8
  • [48] OLYMPIC DAM ORE GENESIS - A FLUID-MIXING MODEL
    HAYNES, DW
    CROSS, KC
    BILLS, RT
    REED, MH
    ECONOMIC GEOLOGY AND THE BULLETIN OF THE SOCIETY OF ECONOMIC GEOLOGISTS, 1995, 90 (02): : 281 - 307
  • [49] SELECTIVE DISSOLUTION OF URANIUM FROM OLYMPIC DAM COPPER CONCENTRATES
    RAGOZZINI, RJ
    SPARROW, GJ
    HYDROMETALLURGY, 1987, 18 (03) : 367 - 382
  • [50] Flotation circuit analysis at WMC Ltd Olympic Dam Operation
    Alexander, D. J.
    Wigley, P.
    Eighth Mill Operators' Conference, Proceedings: EVOLUTION AND SURVIVAL IN THE MINERALS INDUSTRY, 2003, 2003 (04): : 41 - 51