AN IMPROVED TIME-COST TRADE-OFF MODEL WITH OPTIMAL LABOR PRODUCTIVITY

被引:9
|
作者
Lin, Chien-Liang [1 ]
Lai, Yu-Che [1 ]
机构
[1] Natl Kaohsiung Univ Sci & Technol, Dept Construct Engn, Kaohsiung, Taiwan
关键词
labor productivity; time-cost trade-off; optimization; genetic algorithm; CONSTRUCTION; OPTIMIZATION; DESIGN; ACCELERATION;
D O I
10.3846/jcem.2020.11663
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Optimization of the time-cost trade off (TCT) has received considerable attention for several decades. However, few studies have considered improving performance/productivity of existing crews. To shorten the gap to real-world applications, this study presents an improved TCT model that considers variable productivity using genetic algorithms (GAs). Through an illustrative case and a real world case, the results demonstrate that improving labor productivity of selected activities by allocating existing crews and management can yield an optimized solution. As such, a decision maker can implement a better optimized technique to reduce a project duration under budget while reducing the risk of liquidated damages. The main contribution of this study is to apply managerial improvement of labor productivity to TCT optimization, the project duration can be reduced owing to improved productivity of existing crews rather than inefficient overmanning, overlapping or costly substitution. In the end, three important managerial insights are presented and future research is recommended.
引用
收藏
页码:113 / 130
页数:18
相关论文
共 50 条
  • [41] Multiobjective Optimization of Time-Cost Trade-Off Using Harmony Search
    Geem, Zong Woo
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2010, 136 (06): : 711 - 716
  • [42] Time-cost trade-off optimization with a new initial population approach
    Toğan V.
    Eirgash M.A.
    Teknik Dergi/Technical Journal of Turkish Chamber of Civil Engineers, 2019, 30 (06): : 9561 - 9580
  • [43] Time-cost trade-off analysis of a priority based assignment problem
    Prabhjot Kaur
    Kalpana Dahiya
    Vanita Verma
    OPSEARCH, 2021, 58 : 448 - 482
  • [44] Research on the Hierarchical Discrete Time-Cost Trade-Off Problem for Program
    Chen, Liangwei
    Zhang, Jingwen
    Peng, Wuliang
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2022, 148 (07)
  • [45] Project time-cost trade-off optimization by maximal flow theory
    Liu, JM
    Rahbar, F
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2004, 130 (04) : 607 - 609
  • [46] MANAGING NEW PRODUCT TIME TO MARKET USING TIME-COST TRADE-OFF METHODS
    HAFFNER, EW
    GRAVES, RJ
    OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 1988, 16 (02): : 117 - 124
  • [47] A discrete-time approximation technique for the time-cost trade-off in pert networks
    Azaron, Amir
    Sakawa, Masatoshi
    Tavakkoli-Moghaddam, Reza
    Safaei, Nima
    RAIRO-OPERATIONS RESEARCH, 2007, 41 (01) : 61 - 81
  • [48] Using machine learning and GA to solve time-cost trade-off problems
    Li, Heng
    Cao, J.-N.
    Love, P.E.D.
    Journal of Construction Engineering and Management, 125 (05): : 347 - 353
  • [49] Time-cost trade-off of construction project based on ant colony algorithm
    Xiong, Ying
    Kuang, Ya-Ping
    Xitong Gongcheng Lilun yu Shijian/System Engineering Theory and Practice, 2007, 27 (03): : 105 - 111
  • [50] Using genetic algorithms to solve construction time-cost trade-off problems
    Feng, CW
    Liu, LA
    Burns, SA
    JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 1997, 11 (03) : 184 - 189