A ROBUST OPTIMIZATION MODEL FOR THE RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM WITH UNCERTAIN ACTIVITY DURATIONS

被引:0
|
作者
Wang, Wei [1 ]
Shou, Yongyi [1 ]
机构
[1] Zhejiang Univ, Sch Management, Hangzhou, Zhejiang, Peoples R China
关键词
Project Scheduling; Robust Optimization; Uncertain Activity Durations; Ant Colony Algorithm;
D O I
暂无
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
In researches of project scheduling, the majority is based on the hypothesis that the activity duration is deterministic. However, in the real world, a major challenge comes from the stochastic activity durations. In this paper, the current methods for the recourse-constraint project scheduling problem with uncertain activity durations' are reviewed and their deficiencies are discussed. Then, combining with the robust optimization concept, a new robust optimization model is proposed for the recourse-constraint project scheduling problem, in order to reduce the turbulence caused by uncertain activity durations during the project implementation, and to improve the robustness of the project schedules. A case example is employed to illustrate the new robust model. An ant colony algorithm is integrated to solve the above mentioned problem and to generate a robust solution. The project schedule is also tested in various scenarios to analyze its robustness. The results are discussed in details to explore potential opportunities of further extensions and improvement of the proposed model.
引用
收藏
页码:2376 / 2381
页数:6
相关论文
共 50 条
  • [31] Hybrid ant colony optimization for the resource-constrained project scheduling problem
    Deng, Linyi
    Lin, Yan
    Chen, Ming
    JOURNAL OF SYSTEMS ENGINEERING AND ELECTRONICS, 2010, 21 (01) : 67 - 71
  • [32] An Enhanced Invasive Weed Optimization in Resource-Constrained Project Scheduling Problem
    Cai, Wei
    Chen, Haojie
    Zhang, Jian
    2020 11TH INTERNATIONAL CONFERENCE ON AWARENESS SCIENCE AND TECHNOLOGY (ICAST), 2020,
  • [33] An improved particle swarm optimization for the resource-constrained project scheduling problem
    Jia, Qiong
    Seo, Yoonho
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2013, 67 (9-12): : 2627 - 2638
  • [34] Financial Optimization of the Resource-Constrained Project Scheduling Problem with Milestones Payments
    Klimek, Marcin
    APPLIED SCIENCES-BASEL, 2021, 11 (02): : 1 - 14
  • [35] An improved particle swarm optimization for the resource-constrained project scheduling problem
    Qiong Jia
    Yoonho Seo
    The International Journal of Advanced Manufacturing Technology, 2013, 67 : 2627 - 2638
  • [36] Hybrid ant colony optimization for the resource-constrained project scheduling problem
    Linyi Deng1
    2. State Key Laboratory of Structural Analysis for Industrial Equipment
    JournalofSystemsEngineeringandElectronics, 2010, 21 (01) : 67 - 71
  • [37] Optimization algorithms for solving resource-constrained project scheduling problem: A review
    Liu, Shi-Xin
    Wang, Meng-Guang
    Tang, Jia-Fu
    Kongzhi yu Juece/Control and Decision, 2001, 16 (SUPPL.): : 647 - 651
  • [38] Genetic algorithms to solve resource-constrained project scheduling problems with variable activity durations
    Sebt, M. H. (sebt@aut.ac.ir), 1600, Iran University of Science and Technology (11):
  • [39] Genetic algorithms to solve resource-constrained project scheduling problems with variable activity durations
    Sebt, M. H.
    Zarandi, M. H. Fazel
    Alipouri, Y.
    INTERNATIONAL JOURNAL OF CIVIL ENGINEERING, 2013, 11 (3A) : 189 - 198
  • [40] Multi-mode resource-constrained project scheduling with uncertain activity cost
    Xie, Fang
    Li, Haitao
    Xu, Zhe
    EXPERT SYSTEMS WITH APPLICATIONS, 2021, 168