A ROBUST OPTIMIZATION MODEL FOR THE RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM WITH UNCERTAIN ACTIVITY DURATIONS

被引:0
|
作者
Wang, Wei [1 ]
Shou, Yongyi [1 ]
机构
[1] Zhejiang Univ, Sch Management, Hangzhou, Zhejiang, Peoples R China
关键词
Project Scheduling; Robust Optimization; Uncertain Activity Durations; Ant Colony Algorithm;
D O I
暂无
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
In researches of project scheduling, the majority is based on the hypothesis that the activity duration is deterministic. However, in the real world, a major challenge comes from the stochastic activity durations. In this paper, the current methods for the recourse-constraint project scheduling problem with uncertain activity durations' are reviewed and their deficiencies are discussed. Then, combining with the robust optimization concept, a new robust optimization model is proposed for the recourse-constraint project scheduling problem, in order to reduce the turbulence caused by uncertain activity durations during the project implementation, and to improve the robustness of the project schedules. A case example is employed to illustrate the new robust model. An ant colony algorithm is integrated to solve the above mentioned problem and to generate a robust solution. The project schedule is also tested in various scenarios to analyze its robustness. The results are discussed in details to explore potential opportunities of further extensions and improvement of the proposed model.
引用
收藏
页码:2376 / 2381
页数:6
相关论文
共 50 条
  • [21] Simulation Library for Resource Constrained Project Scheduling with Uncertain Activity Durations
    Brcic, Mario
    Hlupic, Nikica
    2014 37TH INTERNATIONAL CONVENTION ON INFORMATION AND COMMUNICATION TECHNOLOGY, ELECTRONICS AND MICROELECTRONICS (MIPRO), 2014, : 1041 - 1046
  • [22] A heuristic approach for resource constrained project scheduling with uncertain activity durations
    Bruni, M. E.
    Beraldi, P.
    Guerriero, F.
    Pinto, E.
    COMPUTERS & OPERATIONS RESEARCH, 2011, 38 (09) : 1305 - 1318
  • [23] A lexicographic approach to the robust resource-constrained project scheduling problem
    Palacio, Juan D.
    Larrea, Olga L.
    INTERNATIONAL TRANSACTIONS IN OPERATIONAL RESEARCH, 2017, 24 (1-2) : 143 - 157
  • [24] A robust optimization approach for the multi-mode resource-constrained project scheduling problem
    Balouka, Noemie
    Cohen, Izack
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2021, 291 (02) : 457 - 470
  • [25] A Hybrid Multiobjective Genetic Algorithm for Robust Resource-Constrained Project Scheduling with Stochastic Durations
    Xiong, Jian
    Chen, Ying-wu
    Yang, Ke-wei
    Zhao, Qing-song
    Xing, Li-ning
    MATHEMATICAL PROBLEMS IN ENGINEERING, 2012, 2012
  • [26] Scheduling resource-constrained project problem with alternative activity chains
    Tao, Sha
    Dong, Zhijie Sasha
    COMPUTERS & INDUSTRIAL ENGINEERING, 2017, 114 : 288 - 296
  • [27] Resource-constrained project scheduling problem with reworking
    Liao Y.
    Lu Z.
    Jisuanji Jicheng Zhizao Xitong/Computer Integrated Manufacturing Systems, CIMS, 2019, 25 (11): : 2762 - 2774
  • [28] A matheuristic for the resource-constrained project scheduling problem
    Vanhoucke, Mario
    Coelho, Jose
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2024, 319 (03) : 711 - 725
  • [29] A SURVEY ON THE RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM
    OZDAMAR, L
    ULUSOY, G
    IIE TRANSACTIONS, 1995, 27 (05) : 574 - 586
  • [30] Extensions of the resource-constrained project scheduling problem
    Ding, Hongyan
    Zhuang, Cunbo
    Liu, Jianhua
    AUTOMATION IN CONSTRUCTION, 2023, 153