Novel Hybrid Method in Time-Cost Trade-Off for Resource-Constrained Construction Projects

被引:21
|
作者
Albayrak, Gulcag [1 ]
机构
[1] Eskisehir Osmangazi Univ, Dept Civil Engn, TR-26040 Eskisehir, Turkey
关键词
Hybrid algorithm; Metaheuristic method; Optimization; Project planning; MULTIOBJECTIVE APPROACH; GENETIC ALGORITHM; OPTIMIZATION; COLONY; MODELS;
D O I
10.1007/s40996-020-00437-2
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Time and cost are two of the most important issues for construction planning. Nowadays, the relationship between time and cost becomes more crucial due to the competitive conditions. The contradiction of these two project factors which are affected by the various project constraints needs to be balanced. In this study, time-cost trade-off (TCT) problem is considered as a multi-objective problem. To solve TCT, a novel hybrid algorithm (NHA) is suggested. This method, which is developed by hybridization of particle swarm optimization (PSO) and genetic algorithm, is compared on the application with standard PSO. NHA, which is expected to be more efficient in terms of avoiding local best points and searching the solution space, also presents shorter and more economical alternatives of the project.
引用
收藏
页码:1295 / 1307
页数:13
相关论文
共 50 条
  • [41] TIME-COST TRADE-OFF IN A SOLID TRANSPORTATION PROBLEM
    BHATIA, HL
    PURI, MC
    ZEITSCHRIFT FUR ANGEWANDTE MATHEMATIK UND MECHANIK, 1977, 57 (10): : 616 - 619
  • [42] Factors affecting time and cost trade-off in multiple construction projects
    Hasan, Musaab Falih
    Mohammed, Sawsan Rasheed
    ARCHIVES OF CIVIL ENGINEERING, 2022, 68 (02) : 549 - 561
  • [43] A TRADE-OFF BETWEEN TIME AND COST IN SCHEDULING REPETITIVE CONSTRUCTION PROJECTS
    Zhang, Lihui
    Zou, Xin
    Qi, Jianxun
    JOURNAL OF INDUSTRIAL AND MANAGEMENT OPTIMIZATION, 2015, 11 (04) : 1423 - 1434
  • [44] Using ant colony algorithm to solve construction time-cost trade-off problem
    College of Civil Engineering and Architecture, Zhejiang University, Hangzhou 310027, China
    不详
    Zhejiang Daxue Xuebao (Gongxue Ban), 2007, 1 (176-180):
  • [45] Time-cost trade-off problem in construction project management, based on fuzzy logic
    Abbasnia, R.
    Afshar, A.
    Eshtehardian, E.
    Journal of Applied Sciences, 2008, 8 (22) : 4159 - 4165
  • [46] Construction time-cost trade-off analysis using ant colony optimization algorithm
    Kuang Ya-ping
    Xiong Ying
    PROCEEDINGS OF THE 2006 INTERNATIONAL CONFERENCE ON MANAGEMENT SCIENCE & ENGINEERING (13TH), VOLS 1-3, 2006, : 2039 - 2044
  • [47] A ROBUST TIME-COST-QUALITY-ENERGY-ENVIRONMENT TRADE-OFF WITH RESOURCE-CONSTRAINED IN PROJECT MANAGEMENT: A CASE STUDY FOR A BRIDGE CONSTRUCTION PROJECT
    Lotfi, Reza
    Yadegari, Zahra
    Hosseini, Seyed Hossein
    Khameneh, Amir Hossein
    Tirkolaee, Erfan Babaee
    Weber, Gerhard-Wilhelm
    JOURNAL OF INDUSTRIAL AND MANAGEMENT OPTIMIZATION, 2022, 18 (01) : 375 - 396
  • [48] TIME-COST TRADE-OFF AMONG RELATED ACTIVITIES - CLOSURE
    REDA, R
    CARR, RI
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1991, 117 (02): : 375 - 376
  • [49] TIME-COST TRADE-OFF AMONG RELATED ACTIVITIES - DISCUSSION
    HANSCOM, GB
    WAUGH, L
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1991, 117 (02): : 374 - 375
  • [50] New fuzzy models for time-cost trade-off problem
    Hua Ke
    Weimin Ma
    Xin Gao
    Weihua Xu
    Fuzzy Optimization and Decision Making, 2010, 9 : 219 - 231