Causes and Impacts of Delays in Ethiopian Public Construction Projects (Case on Debre Markos University Construction Projects)

被引:2
|
作者
Demissew, Abebe [1 ]
Abiy, Fasika [1 ]
机构
[1] Debre Markos Univ, Inst Technol, Construct Technol & Management Dept, POB 269, Debre Markos, Ethiopia
关键词
D O I
10.1155/2023/6577676
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The construction project is regarded successful when it is given over to the owner within the time, cost, and standards necessary while minimizing delays in public construction projects. Debre Markos University (DMU) is one of the public universities undergoing massive development projects that are experiencing significant delays. This article evaluates the most prevalent delay issues encountered by Ethiopian government-funded construction projects, particularly those using DMU, analyzes their impacts, and suggests a delay management system. The study applied qualitative as well as quantitative techniques to evaluate primary and secondary data. Per the entirety statistics, the top five most important and highly ranked factors are erroneous time estimates, force majeure, lowest bid, procurement policy, and volatile markets, as well as frequent design changes. Nearly every DMU project schedule overruns up to 268.67% of its contract duration. As a result, the institution suffered from poor public relations and a high cost of supervision and contract administration (6.87% of the overall project cost). Conducting a thorough and accurate project feasibility study, awarding bids to experienced contractors, avoiding drawing discrepancies, preparing an accurate initial time and cost estimate, and strict schedule monitoring were discovered to be effective techniques for reducing delays in public construction projects.
引用
收藏
页数:14
相关论文
共 50 条
  • [21] An investigation into the causes of delays in the construction of Metro Rail Projects in India
    Donga, A.
    Prasad, K. V.
    Kumaran, G. S.
    Sagathiya, K.
    Vasugi, V.
    BUILDING SMART, RESILIENT AND SUSTAINABLE INFRASTRUCTURE IN DEVELOPING COUNTRIES, DII-2022, 2023, : 235 - 244
  • [22] Identification of Causes of Non-excusable Delays of Construction Projects
    Afshari, Hamidreza
    Khosravi, Shahrzad
    Ghorbanali, Abbas
    Borzabadi, Mandi
    Valipour, Mahbod
    E-BUSINESS, MANAGEMENT AND ECONOMICS, 2011, 3 : 42 - 46
  • [23] Towards a sustainable construction industry: Delays and cost overrun causes in construction projects of Oman
    Al Amri, Tariq
    Marey-Perez, Manuel
    JOURNAL OF PROJECT MANAGEMENT, 2020, 5 (02) : 87 - 102
  • [24] An Investigation into the Causes of Payment Delays and Deliberate Delay Tactics in Public Construction Projects in Saudi Arabia
    Bageis, Abdulrahman Salem
    BUILDINGS, 2024, 14 (06)
  • [25] Improving Performance in Construction Projects: A Case Study of Malaysian Public Projects
    Yusof, Aminah Md
    Khoso, Ali Raza
    Sohu, Samiullah
    Khahro, Shabir Hussain
    Chai, Chang Saar
    PERTANIKA JOURNAL OF SCIENCE AND TECHNOLOGY, 2021, 29 (04): : 2579 - 2604
  • [26] Underlying causes and mitigation measures of delays in construction projects An empirical study
    Arantes, Amilcar
    Ferreira, Luis Miguel D. F.
    JOURNAL OF FINANCIAL MANAGEMENT OF PROPERTY AND CONSTRUCTION, 2020, 25 (02) : 165 - 181
  • [27] CONCURRENT DELAYS IN CONSTRUCTION PROJECTS - DISCUSSION
    LOGCHER, RD
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1989, 115 (02): : 335 - 337
  • [28] CONCURRENT DELAYS IN CONSTRUCTION PROJECTS.
    Kraiem, Zaki M.
    Diekmann, James E.
    Journal of Construction Engineering and Management, 1987, 113 (04) : 591 - 602
  • [29] Delays in Building Construction Projects in Ghana
    Fugar, Frank D. K.
    Agyakwah-Baah, Adwoa B.
    CONSTRUCTION ECONOMICS AND BUILDING, 2010, 10 (1-2):
  • [30] CONCURRENT DELAYS IN CONSTRUCTION PROJECTS - CLOSURE
    KRAIEM, ZM
    DIEKMANN, JE
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1989, 115 (02): : 337 - 338