Causes and Impacts of Delays in Ethiopian Public Construction Projects (Case on Debre Markos University Construction Projects)

被引:2
|
作者
Demissew, Abebe [1 ]
Abiy, Fasika [1 ]
机构
[1] Debre Markos Univ, Inst Technol, Construct Technol & Management Dept, POB 269, Debre Markos, Ethiopia
关键词
D O I
10.1155/2023/6577676
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The construction project is regarded successful when it is given over to the owner within the time, cost, and standards necessary while minimizing delays in public construction projects. Debre Markos University (DMU) is one of the public universities undergoing massive development projects that are experiencing significant delays. This article evaluates the most prevalent delay issues encountered by Ethiopian government-funded construction projects, particularly those using DMU, analyzes their impacts, and suggests a delay management system. The study applied qualitative as well as quantitative techniques to evaluate primary and secondary data. Per the entirety statistics, the top five most important and highly ranked factors are erroneous time estimates, force majeure, lowest bid, procurement policy, and volatile markets, as well as frequent design changes. Nearly every DMU project schedule overruns up to 268.67% of its contract duration. As a result, the institution suffered from poor public relations and a high cost of supervision and contract administration (6.87% of the overall project cost). Conducting a thorough and accurate project feasibility study, awarding bids to experienced contractors, avoiding drawing discrepancies, preparing an accurate initial time and cost estimate, and strict schedule monitoring were discovered to be effective techniques for reducing delays in public construction projects.
引用
收藏
页数:14
相关论文
共 50 条
  • [41] Risk allocation in public construction projects: the case of Jordan
    Hiyassat, Mohammed A.
    Alkasagi, Fatima
    El-Mashaleh, Mohammad
    Sweis, Ghaleb J.
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2022, 22 (08) : 1478 - 1488
  • [42] An evaluation of environmental impacts of construction projects
    Enshassi, Adnan
    Kochendoerfer, Bernd
    Rizq, Ehsan
    REVISTA INGENIERIA DE CONSTRUCCION, 2014, 29 (03): : 234 - 254
  • [43] Exploring Causes of Delays in National Road and Highway Projects in Developing Construction Economy
    Karimi S.
    Piroozfar P.
    Journal of Engineering, Project, and Production Management, 2022, 12 (02) : 137 - 148
  • [44] CATEGORIZATION OF CLASHES AND THEIR IMPACTS ON CONSTRUCTION PROJECTS
    Matejka, Petr
    Sabart, Daniel
    17TH INTERNATIONAL SCIENTIFIC CONFERENCE: ENGINEERING FOR RURAL DEVELOPMENT, 2018, : 827 - 835
  • [45] An Investigation into the Risk of Construction Projects Delays in the UAE
    Motaleb, Omayma
    Kishk, Mohammed
    INTERNATIONAL JOURNAL OF INFORMATION TECHNOLOGY PROJECT MANAGEMENT, 2013, 4 (03) : 50 - 65
  • [46] Delays in the Iranian construction projects: Stakeholders and economy
    Asnaashari, E.
    Knight, A.
    Hurst, A.
    CHALLENGES, OPPORTUNITIES AND SOLUTIONS IN STRUCTURAL ENGINEERING AND CONSTRUCTION, 2010, : 699 - 704
  • [47] Using PIPS to minimize causes of delay in Saudi Arabian construction projects: university case study
    Alzara, Majed
    Kashiwagi, Jacob
    Kashiwagi, Dean
    Al-Tassan, Abdulrahman
    ICSDEC 2016 - INTEGRATING DATA SCIENCE, CONSTRUCTION AND SUSTAINABILITY, 2016, 145 : 932 - 939
  • [48] Target costing in public construction projects
    Sobotka, Anna
    Czarnigowska, Agata
    9TH INTERNATIONAL CONFERENCE: MODERN BUILDING MATERIALS, STRUCTURES AND TECHNIQUES, VOLS 1-3, 2008, : 375 - +
  • [49] Dispute Avoidance in Public Construction Projects
    Tabish, Syed Zafar Shahid
    Jha, Kumar Neeraj
    JOURNAL OF LEGAL AFFAIRS AND DISPUTE RESOLUTION IN ENGINEERING AND CONSTRUCTION, 2023, 15 (01)
  • [50] Causes of Delay in the Construction Projects of Subway Tunnel
    Zhang, Dingbang
    Zhang, Hang
    Cheng, Tao
    ADVANCES IN CIVIL ENGINEERING, 2020, 2020