Structural model of cost overrun factors affecting Pakistani construction projects

被引:1
|
作者
Memon, Aftab Hameed [1 ]
Memon, Abdul Qadir [1 ]
Memon, Muneeb Ayub [1 ]
Sahito, Jam Shahzeb Khan [1 ]
机构
[1] Quaid Awam Univ Engn Sci & Technol, Dept Civil Engn, Nawabshah, Pakistan
关键词
Cost Performance; Cost Overruns; Construction; PLS-SEM Structural Equation; Modeling; Pakistan; INFRASTRUCTURE PROJECTS; DELAYS; INDUSTRY; TIME;
D O I
10.22581/muet1982.2302.12
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Cost overruns are a global challenge to successfully completing construction projects. Cost overrun has a substantial impact resulting in most construction projects failing to be completed. Several factors have contributed significantly to the industry's decline. The factors were discovered in the literature, assessed, and applied to the construction industry in Pakistan. This study scrutinized and identified the relationships between the factors causing cost overruns in the Pakistani construction industry using the Partial Least Squares Structural Equation Modelling (PLS-SEM) approach. The structural model was created and tested with Smart-PLS software using data from a questionnaire survey of 131 construction practitioners. Six constructs were used to categorize the factors. The model identifies 21 critical factors in Pakistani construction projects, with resource management ranking first. Contract management issues can also contribute significantly to project cost overruns. Model assessment results indicate that the developed model has a substantial power of explaining the factors of cost performance while R2 value showed that 45.7% variance is explained by the model. The model developed model will serve as a jumping-off point for academics, researchers, and practitioners in developing a cost-control system. It is suggested that establishing an efficient and effective contract management protocol among stakeholders throughout the design and supervision stages is extremely beneficial for improving project cost performance and significantly reducing time overruns.
引用
收藏
页码:108 / 123
页数:16
相关论文
共 50 条
  • [21] Cost overrun in the Malaysian construction industry projects: A deeper insight
    Shehu, Zayyana
    Endut, Intan Rohani
    Akintoye, Akintola
    Holt, Gary D.
    INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2014, 32 (08) : 1471 - 1480
  • [22] Critical Factors Affecting the Bid Cost of Building Construction Projects
    Shrestha, Kishor
    Shrestha, Pramen P.
    Lohoud, Mohamed
    JOURNAL OF LEGAL AFFAIRS AND DISPUTE RESOLUTION IN ENGINEERING AND CONSTRUCTION, 2023, 15 (03)
  • [23] A preliminary study of the factors affecting the cost escalation of construction projects
    Knight, K
    Fayek, A
    CANADIAN JOURNAL OF CIVIL ENGINEERING, 2000, 27 (01) : 73 - 83
  • [24] Identification and analysing of risk factors affecting cost of construction projects
    Vivek, Attada
    Rao, C. H. Hanumantha
    MATERIALS TODAY-PROCEEDINGS, 2022, 60 : 1696 - 1701
  • [25] Managing Delays in Construction Projects Aiming at Cost Overrun Minimization
    Anysz, Hubert
    4TH WORLD MULTIDISCIPLINARY CIVIL ENGINEERING-ARCHITECTURE-URBAN PLANNING SYMPOSIUM - WMCAUS, 2019, 603
  • [26] Time Delay and Cost Overrun in Qatari Public Construction Projects
    Senouci, Ahmed
    Ismail, Alaa
    Eldin, Neil
    5TH CREATIVE CONSTRUCTION CONFERENCE (CCC 2016), 2016, 164 : 368 - 375
  • [27] Research on Influencing Factors and Control Measures of Construction Cost Overrun in China's Expressway Projects
    Chen S.
    Fan X.
    Cai B.
    International Journal of Fuzzy System Applications, 2023, 12 (01)
  • [28] UNEARTHING CAUSATIVE FACTORS OF COST OVERRUN ON GHANAIAN ROAD PROJECTS
    Akinradewo, Opeoluwa
    Aigbavboa, Clinton
    Oke, Ayodeji
    Coffie, Harrison
    Ogunbayo, Babatunde
    BALTIC JOURNAL OF ROAD AND BRIDGE ENGINEERING, 2022, 17 (04): : 171 - 188
  • [29] Contributing Factors of Time Overrun in Public Sector Construction Projects
    Akhund, Muhammad Akram
    Imad, Hafiz Usama
    Memon, Nafees Ahmed
    Siddiqui, Fida Hussain
    Khoso, Ali Raza
    Panhwar, Abbas Ali
    ENGINEERING TECHNOLOGY & APPLIED SCIENCE RESEARCH, 2018, 8 (05) : 3369 - 3372
  • [30] Ranking of the Factors Causing Cost Overrun in Infrastructural Projects of UAE
    Alhammadi, Ahmed Salem Ahmed Marey
    Memon, Aftab Hameed
    INTERNATIONAL JOURNAL OF SUSTAINABLE CONSTRUCTION ENGINEERING AND TECHNOLOGY, 2020, 11 (02): : 204 - 211