Feasibility study for the geothermal exploitation of the Brenner Base Tunnel

被引:0
|
作者
Lanconelli, Matteo [1 ]
Voza, Antonio [1 ]
Egger, Harald [1 ]
Zurlo, Raffaele [1 ]
Boldini, Daniela [2 ]
Tinti, Francesco [2 ]
Ferrari, Marco [2 ]
Kasmaee, Sara [2 ]
机构
[1] Brenner BasisTunnel BBT SE, Bolzano, Italy
[2] Univ Bologna, Dipartimento Ingn Civile Chim Ambientale & Mat DI, Bologna, Italy
来源
关键词
D O I
暂无
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The thesis deals with the low enthalpy geothermal energy and its exploitation through tunnels, in the specific case the Brenner Base Tunnel (BBT). The heat stored in rock masses is proposed to be exploited by a geothermal system, composed by a pipe system placed inside of the lining, defined energy lining. Through a geothermal characterization, laboratory tests and temperature measurements, it has been possible to define the energy potential of the considered part of the BBT. A scheme of the energy lining has been designed, with regard to does not alter the other working phases. A road with snow-melting and de-icing has been supposed as possible energy user and a cost estimation of the investment was obtained. Operating costs have been compared with other heating solutions. The study shows the technical and economic feasibility of this solution and represents a step for future research on this subject.
引用
收藏
页码:35 / 47
页数:13
相关论文
共 50 条
  • [31] Simulation of fire and structural response in the Brenner Base Tunnel by means of a combined approach: A case study
    Bergmeister, Konrad
    Brunello, Pierfrancesco
    Pachera, Matteo
    Pesavento, Francesco
    Schrefler, B. A.
    ENGINEERING STRUCTURES, 2020, 211
  • [32] Analysis of Stress Conditions at Deep Seated Tunnels-A Case Study at Brenner Base Tunnel
    Patzelt, Johanna
    Thuro, Kurosch
    ENGINEERING GEOLOGY FOR SOCIETY AND TERRITORY, VOL 6: APPLIED GEOLOGY FOR MAJOR ENGINEERING PROJECTS, 2015, : 459 - 463
  • [33] Aicha-Mauls on the Brenner base tunnel -status of the works and results
    Bergmeister, Konrad
    Facchin, Ezio
    Quick, Hubert
    Michael, Joachim
    Geomechanik und Tunnelbau, 2010, 3 (05): : 520 - 533
  • [34] Planning optimisation for the Brenner Base Tunnel considering both maintenance and sustainability
    Planungsoptimierungen beim Brenner Basistunnel aus Sicht der Instandhaltung und Nachhaltigkeit
    1600, Ernst und Sohn (07):
  • [35] Tunnelling in complex geological structures during the construction of the Brenner Base Tunnel
    Marini, David
    Lussu, Andrea
    Hofmann, Matthias
    Venditti, Giuseppe
    Geomechanik und Tunnelbau, 2024, 17 (06): : 594 - 604
  • [36] Brenner Base Tunnel - description of the work and progress through the periadrial fault
    Zurlo, R.
    Rea, G.
    Roccia, M.
    GALLERIE E GRANDI OPERE SOTTERRANEE, 2014, (109): : 57 - 60
  • [37] Brenner Base Tunnel - Construction of the Exploratory Tunnel Non-linear Stochastic Structural Analysis
    Bergmeister, Konrad
    BETON- UND STAHLBETONBAU, 2008, 103 (10) : 658 - 665
  • [38] The excavation of the Brenner Base Tunnel where the Eurasian and Adriatic tectonic plates collide
    Marini, D.
    Venditti, G.
    PROCEEDINGS OF THE ITA-AITES WORLD TUNNEL CONGRESS 2023, WTC 2023: Expanding Underground-Knowledge and Passion to Make a Positive Impact on the World, 2023, : 720 - 725
  • [39] Aicha-Mauls on the Brenner Base Tunnel-status of the works and results
    Quick, H.
    Michael, J.
    Bergmeister, K.
    Facchin, E.
    GEOTECHNICAL ASPECTS OF UNDERGROUND CONSTRUCTION IN SOFT GROUND, 7TH INTERNATIONAL SYMPOSIUM, 2012, : 263 - 270
  • [40] Effects of the geometric position of the Brenner Base Tunnel on rock mass plastification and the tunnel's shotcrete shell
    Bergmeister, Konrad
    Weifner, Tassilo
    Collizzolli, Mara
    BETON- UND STAHLBETONBAU, 2012, 107 (11) : 735 - 748