A mathematical model for the multi-mode resource-constrained project scheduling problem with mode dependent time lags

被引:0
|
作者
Majid Sabzehparvar
S. Mohammad Seyed-Hosseini
机构
[1] Iran University of Science and Technology,Department of Industrial Engineering
来源
关键词
Multi-mode; Rectangle packing; Resource constrained; Time lags; Time windows;
D O I
暂无
中图分类号
学科分类号
摘要
This paper presents an exact model for the multi-mode resource-constrained project scheduling problem with generalized precedence relations in which the minimal or maximal time lags between a pair of activities may vary depending on the chosen modes. All resources considered are renewable. The objective is to determine a mode and a start time for each activity so that all constraints are obeyed and the project duration is minimized. Project scheduling of this type occurs in many fields, for instance, construction industries. The proposed model has been inspired by the rectangle packing problems. In spite of the fact that it needs a feasible solution to start for conventional models, the new model has no need for a feasible solution to start. Computational results with a set of 60 test problems have been reported and the efficiency of the proposed model has been analyzed.
引用
收藏
页码:257 / 273
页数:16
相关论文
共 50 条
  • [31] Memetic algorithm for multi-mode resource-constrained project scheduling problems
    Shixin Liu
    Di Chen
    Yifan Wang
    Journal of Systems Engineering and Electronics, 2014, 25 (04) : 609 - 617
  • [32] Local search for nonpreemptive multi-mode resource-constrained project scheduling
    Kolisch, R
    Drexl, A
    IIE TRANSACTIONS, 1997, 29 (11) : 987 - 999
  • [33] Scatter Search for Multi-mode Resource-constrained Project Scheduling Problems
    Pourghaderi, A. R.
    Torabi, S. A.
    Talebi, J.
    IEEM: 2008 INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND ENGINEERING MANAGEMENT, VOLS 1-3, 2008, : 163 - 167
  • [34] Multi-mode resource-constrained project scheduling with uncertain activity cost
    Xie, Fang
    Li, Haitao
    Xu, Zhe
    EXPERT SYSTEMS WITH APPLICATIONS, 2021, 168
  • [35] Memetic algorithm for multi-mode resource-constrained project scheduling problems
    Liu, Shixin
    Chen, Di
    Wang, Yifan
    JOURNAL OF SYSTEMS ENGINEERING AND ELECTRONICS, 2014, 25 (04) : 609 - 617
  • [36] A Cross-Entropy Based Population Learning Algorithm for Multi-mode Resource-Constrained Project Scheduling Problem with Minimum and Maximum Time Lags
    Jedrzejowicz, Piotr
    Skakovski, Aleksander
    COMPUTATIONAL COLLECTIVE INTELLIGENCE: TECHNOLOGIES AND APPLICATIONS, PT I, 2010, 6421 : 383 - +
  • [37] A multi-mode resource-constrained scheduling problem in the context of port operations
    Lorenzoni, Luciano Lessa
    Ahonen, Hannu
    Gomes de Alvarenga, Arlindo
    COMPUTERS & INDUSTRIAL ENGINEERING, 2006, 50 (1-2) : 55 - 65
  • [38] Multi-mode resource-constrained project scheduling problem with multiple shifts and dynamic energy prices
    Peng, Wuliang
    Yu, Dongmin
    Xie, Fang
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2024,
  • [39] A faster exact method for solving the robust multi-mode resource-constrained project scheduling problem
    Bold, Matthew
    Goerigk, Marc
    OPERATIONS RESEARCH LETTERS, 2022, 50 (05) : 581 - 587
  • [40] A Modified NSGA-II for the Multiobjective Multi-mode Resource-Constrained Project Scheduling Problem
    Vanucci, Sanderson C.
    Bicalho, Rafael
    Carrano, Eduardo G.
    Takahashi, Ricardo H. C.
    2012 IEEE CONGRESS ON EVOLUTIONARY COMPUTATION (CEC), 2012,