A mathematical model for the multi-mode resource-constrained project scheduling problem with mode dependent time lags

被引:0
|
作者
Majid Sabzehparvar
S. Mohammad Seyed-Hosseini
机构
[1] Iran University of Science and Technology,Department of Industrial Engineering
来源
关键词
Multi-mode; Rectangle packing; Resource constrained; Time lags; Time windows;
D O I
暂无
中图分类号
学科分类号
摘要
This paper presents an exact model for the multi-mode resource-constrained project scheduling problem with generalized precedence relations in which the minimal or maximal time lags between a pair of activities may vary depending on the chosen modes. All resources considered are renewable. The objective is to determine a mode and a start time for each activity so that all constraints are obeyed and the project duration is minimized. Project scheduling of this type occurs in many fields, for instance, construction industries. The proposed model has been inspired by the rectangle packing problems. In spite of the fact that it needs a feasible solution to start for conventional models, the new model has no need for a feasible solution to start. Computational results with a set of 60 test problems have been reported and the efficiency of the proposed model has been analyzed.
引用
收藏
页码:257 / 273
页数:16
相关论文
共 50 条
  • [21] Hybrid Heuristics for Multi-mode Resource-Constrained Project Scheduling
    Tchao, Celso
    Martins, Simone L.
    LEARNING AND INTELLIGENT OPTIMIZATION, 2008, 5313 : 234 - +
  • [22] Optimizing time, cost and quality in multi-mode resource-constrained project scheduling
    Kannimuthu, Marimuthu
    Raphael, Benny
    Palaneeswaran, Ekambaram
    Kuppuswamy, Ananthanarayanan
    BUILT ENVIRONMENT PROJECT AND ASSET MANAGEMENT, 2019, 9 (01) : 44 - 63
  • [23] A Practical and Robust Execution Time-Frame Procedure for the Multi-Mode Resource-Constrained Project Scheduling Problem with Minimal and Maximal Time Lags
    Chen, Angela Hsiang-Ling
    Liang, Yun-Chia
    Padilla, Jose David
    ALGORITHMS, 2016, 9 (04):
  • [24] Using resource scarceness characteristics to solve the multi-mode resource-constrained project scheduling problem
    Vincent Van Peteghem
    Mario Vanhoucke
    Journal of Heuristics, 2011, 17 : 705 - 728
  • [25] Using resource scarceness characteristics to solve the multi-mode resource-constrained project scheduling problem
    Van Peteghem, Vincent
    Vanhoucke, Mario
    JOURNAL OF HEURISTICS, 2011, 17 (06) : 705 - 728
  • [26] An effective estimation of distribution algorithm for the multi-mode resource-constrained project scheduling problem
    Wang, Ling
    Fang, Chen
    COMPUTERS & OPERATIONS RESEARCH, 2012, 39 (02) : 449 - 460
  • [27] A Path-Relinking algorithm for the multi-mode resource-constrained project scheduling problem
    Fernandes Muritiba, Albert Einstein
    Rodrigues, Carlos Diego
    da Costa, Franciio Araujo
    COMPUTERS & OPERATIONS RESEARCH, 2018, 92 : 145 - 154
  • [28] An automatic algorithm selection approach for the multi-mode resource-constrained project scheduling problem
    Messelis, Tommy
    De Causmaecker, Patrick
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2014, 233 (03) : 511 - 528
  • [29] A hybrid approach for solving multi-mode resource-constrained project scheduling problem in construction
    Roslon, Jerzy Hubert
    Kulejewski, Janusz Edward
    OPEN ENGINEERING, 2019, 9 (01): : 7 - 13
  • [30] A Decomposition Method for the Multi-Mode Resource-Constrained Multi-Project Scheduling Problem (MRCMPSP)
    Kuehn, Mathias
    Dirkmann, Sebastian
    Voelker, Michael
    Schmidt, Thorsten
    OPERATIONS RESEARCH PROCEEDINGS 2016, 2018, : 521 - 526