A mathematical model for the multi-mode resource-constrained project scheduling problem with mode dependent time lags

被引:0
|
作者
Majid Sabzehparvar
S. Mohammad Seyed-Hosseini
机构
[1] Iran University of Science and Technology,Department of Industrial Engineering
来源
关键词
Multi-mode; Rectangle packing; Resource constrained; Time lags; Time windows;
D O I
暂无
中图分类号
学科分类号
摘要
This paper presents an exact model for the multi-mode resource-constrained project scheduling problem with generalized precedence relations in which the minimal or maximal time lags between a pair of activities may vary depending on the chosen modes. All resources considered are renewable. The objective is to determine a mode and a start time for each activity so that all constraints are obeyed and the project duration is minimized. Project scheduling of this type occurs in many fields, for instance, construction industries. The proposed model has been inspired by the rectangle packing problems. In spite of the fact that it needs a feasible solution to start for conventional models, the new model has no need for a feasible solution to start. Computational results with a set of 60 test problems have been reported and the efficiency of the proposed model has been analyzed.
引用
收藏
页码:257 / 273
页数:16
相关论文
共 50 条
  • [1] A mathematical model for the multi-mode resource-constrained project scheduling problem with mode dependent time lags
    Sabzehparvar, Majid
    Seyed-Hosseini, S. Mohammad
    JOURNAL OF SUPERCOMPUTING, 2008, 44 (03): : 257 - 273
  • [2] The Multi-Mode Resource-Constrained Multi-Project Scheduling Problem
    Wauters, Tony
    Kinable, Joris
    Smet, Pieter
    Vancroonenburg, Wim
    Vanden Berghe, Greet
    Verstichel, Jannes
    JOURNAL OF SCHEDULING, 2016, 19 (03) : 271 - 283
  • [3] Modeling of the flexible resource-constrained multi-mode project scheduling problem
    School of Management, Wuhan University of Technology, Wuhan 430070, China
    不详
    Wuhan Ligong Daxue Xuebao, 2008, 11 (176-179+188):
  • [4] Multi-mode resource-constrained project scheduling problem with activities overlapping
    Chu Z.
    Xu Z.
    Yu J.
    Xu, Zhe (xuzhebuaa@163.com), 1600, CIMS (23): : 557 - 566
  • [5] Solving the Multi-Mode Resource-Constrained Project Scheduling Problem with SMT
    Bofill, Miquel
    Coll, Jordi
    Suy, Josep
    Villaret, Mateu
    2016 IEEE 28TH INTERNATIONAL CONFERENCE ON TOOLS WITH ARTIFICIAL INTELLIGENCE (ICTAI 2016), 2016, : 239 - 246
  • [6] Multi-mode resource-constrained project scheduling problem with alternative project structures
    Tao, Sha
    Dong, Zhijie Sasha
    COMPUTERS & INDUSTRIAL ENGINEERING, 2018, 125 : 333 - 347
  • [7] A branch-and-bound procedure for the multi-mode resource-constrained project scheduling problem with minimum and maximum time lags
    Heilmann, R
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2003, 144 (02) : 348 - 365
  • [8] A multi-mode resource-constrained project scheduling reformulation for the waterway ship scheduling problem
    Alessandro Hill
    Eduardo Lalla-Ruiz
    Stefan Voß
    Marcos Goycoolea
    Journal of Scheduling, 2019, 22 : 173 - 182
  • [9] A multi-mode resource-constrained project scheduling reformulation for the waterway ship scheduling problem
    Hill, Alessandro
    Lalla-Ruiz, Eduardo
    Voss, Stefan
    Goycoolea, Marcos
    JOURNAL OF SCHEDULING, 2019, 22 (02) : 173 - 182
  • [10] The multi-mode resource-constrained project scheduling problem with generalized precedence relations
    De Reyck, B
    Herroelen, W
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1999, 119 (02) : 538 - 556