Branch-and-price approach for the multi-skill project scheduling problem

被引:0
|
作者
Carlos Montoya
Odile Bellenguez-Morineau
Eric Pinson
David Rivreau
机构
[1] Universidad de los Andes,PYLO Research Group, Department of Industrial Engineering
[2] LUNAM Université,undefined
[3] Ecole des Mines de Nantes,undefined
[4] IRCCyN,undefined
[5] LUNAM Université,undefined
[6] Université Catholique de l’Ouest,undefined
来源
Optimization Letters | 2014年 / 8卷
关键词
Branch-and-price; Column generation; Project scheduling; Multi-skilled resources;
D O I
暂无
中图分类号
学科分类号
摘要
This work introduces a procedure to solve the multi-skill project scheduling problem (MSPSP) (Néron and Baptista, International symposium on combinatorial, optimization (CO’2002), 2002). The MSPSP mixes both the classical resource constrained project scheduling problem and the multi-purpose machine model. The aim is to find a schedule that minimizes the completion time (makespan) of a project, composed of a set of activities. In addition, precedence relations and resources constraints are considered. In this problem, resources are staff members that master several skills. Thus, a given number of workers must be assigned to perform each skill required by an activity. Practical applications include the construction of buildings, as well as production and software development planning. We present a column generation approach embedded within a branch-and-price (B&P) procedure that considers a given activity and time-based decomposition approach. Obtained results show that the proposed B&P procedure is able to reach optimal solutions for several small and medium sized instances in an acceptable computational time. Furthermore, some previously open instances were optimally solved.
引用
收藏
页码:1721 / 1734
页数:13
相关论文
共 50 条
  • [1] Branch-and-price approach for the multi-skill project scheduling problem
    Montoya, Carlos
    Bellenguez-Morineau, Odile
    Pinson, Eric
    Rivreau, David
    OPTIMIZATION LETTERS, 2014, 8 (05) : 1721 - 1734
  • [2] A note on "branch-and-price approach for the multi-skill project scheduling problem"
    Correia, Isabel
    Saldanha-da-Gama, Francisco
    OPTIMIZATION LETTERS, 2015, 9 (06) : 1255 - 1258
  • [3] A note on “branch-and-price approach for the multi-skill project scheduling problem”
    Isabel Correia
    Francisco Saldanha-da-Gama
    Optimization Letters, 2015, 9 : 1255 - 1258
  • [4] A branch-and-bound method for solving multi-skill project scheduling problem
    Bellenguez-Morineau, Odile
    Neron, Emmanuel
    RAIRO-OPERATIONS RESEARCH, 2007, 41 (02) : 155 - 170
  • [5] Lower bounds for a multi-skill project scheduling problem
    Dhib, Cheikh
    Kooli, Anis
    Soukhal, Ameur
    Neron, Emmanuel
    OPERATIONS RESEARCH PROCEEDINGS 2011, 2012, : 471 - 476
  • [6] Methods to solve multi-skill project scheduling problem
    Bellenguez-Morineau, Odile
    4OR-A QUARTERLY JOURNAL OF OPERATIONS RESEARCH, 2008, 6 (01): : 85 - 88
  • [7] Methods to solve multi-skill project scheduling problem
    Odile Bellenguez-Morineau
    4OR, 2008, 6 : 85 - 88
  • [8] Tabu Search approach for Multi-Skill Resource Constrained Project Scheduling Problem
    Skowronski, Marek E.
    Myszkowski, Pawel B.
    Adamski, Marcin
    Kwiatek, Pawel
    2013 FEDERATED CONFERENCE ON COMPUTER SCIENCE AND INFORMATION SYSTEMS (FEDCSIS), 2013, : 153 - 158
  • [9] Constraint Programming Applied to the Multi-Skill Project Scheduling Problem
    Young, Kenneth D.
    Feydy, Thibaut
    Schutt, Andreas
    PRINCIPLES AND PRACTICE OF CONSTRAINT PROGRAMMING (CP 2017), 2017, 10416 : 308 - 317
  • [10] A branch-and-price approach for solving the train unit scheduling problem
    Lin, Zhiyuan
    Kwan, Raymond S. K.
    TRANSPORTATION RESEARCH PART B-METHODOLOGICAL, 2016, 94 : 97 - 120