Safety Risk Assessment Using a BP Neural Network of High Cutting Slope Construction in High-Speed Railway

被引:12
|
作者
Huang, Jianling [1 ]
Zeng, Xiaoye [1 ]
Fu, Jing [2 ]
Han, Yang [1 ]
Chen, Huihua [1 ]
机构
[1] Cent South Univ, Sch Civil Engn, Dept Engn Management, Changsha 410083, Peoples R China
[2] Org Dept CPC Loudi Municipal, Loudi 417000, Peoples R China
基金
国家重点研发计划;
关键词
high cutting slope; risk assessment; BP neural network; STABILITY ANALYSIS; LANDSLIDE; DEFORMATION; MODEL;
D O I
10.3390/buildings12050598
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
High-speed railway construction is extending to mountainous areas, and the harsh environment and complex climate pose various risks to the slope construction. This seriously threatens human lives and causes huge economic losses. The existing research results on the construction safety risks of high cutting slope construction in HSRs are limited, and a complete set of safety risk assessment processes and methods has not yet been formed. Therefore, in this study, we aimed to develop a safety risk assessment model, including factor identification and classification and assessment data processing, to help project managers evaluate safety risks in high cutting slope construction. In this study, comprehensive identification of high cutting slope construction safety risks was carried out from three dimensions, risk technical specification, literature analysis, and case statistical analysis, and a list of risk-influencing factors was formed. Based on the historical data, a high side slope risk evaluation model was established using a BP neural network algorithm. The model was applied to the risk evaluation of HF high cutting slopes. The results show that the risk evaluation level is II; the main risks are earthwork excavation method, scaffolding equipment, slope height, slope rate, groundwater, personnel safety awareness, and construction safety risk management system. Finally, a case study was used to verify the proposed model, and control measures for safety risks were proposed. Our findings will help conduct effective safety management, add to the knowledge of construction safety risk management in terms of implementation, and offer lessons and references for future construction safety management of HSR.
引用
收藏
页数:17
相关论文
共 50 条
  • [41] Risk Assessment and Early-Warning System for High-Speed Railway during the Construction and Operation of Underpass Bridges
    He, Wei
    Duan, Yinlong
    Deng, Liwen
    Zhou, Weiguang
    JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES, 2016, 30 (01)
  • [42] Cutting Force Prediction of High-Speed Milling Hardened Steel Based on BP Neural Networks
    Chen, Yuanling
    Long, Weiren
    Ma, Fanglan
    Zhang, Baolei
    SIXTH INTERNATIONAL SYMPOSIUM ON NEURAL NETWORKS (ISNN 2009), 2009, 56 : 571 - 577
  • [43] Risk identification, assessment and monitoring design of high cutting loess slope in heavy haul railway
    Zhang, Qian
    Gao, Yang
    Zhang, Hai-xia
    Xu, Fei
    Li, Feng
    STRUCTURAL MONITORING AND MAINTENANCE, 2018, 5 (01): : 67 - 78
  • [44] Probabilistic Analytical Model for Settlement Risk Assessment of High-Speed Railway Subgrade
    Chen, R. P.
    Jiang, P.
    Ye, X. W.
    Bian, X. C.
    JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES, 2016, 30 (03)
  • [45] Risk assessment for interaction effect of adjacent high-speed railway bridges and highways
    Department of Bridge Engineering, Tongji University, Shanghai, China
    IABSE Conf., Geneva: Struct. Eng.: Provid. Solutions Glob. Challenges - Rep., 1600, (878-885):
  • [46] Quantitative Risk Assessment Method for the On-board ATP of High-speed Railway
    Shi, Lei
    Zheng, Wei
    Ning, Ningjie
    Wu, Daohua
    3RD INTERNATIONAL CONFERENCE ON TRANSPORTATION INFORMATION AND SAFETY (ICTIS 2015), 2015, : 763 - 768
  • [47] Research on the Risk Assessment Method of Subgrade Heaving Deformation of High-speed Railway
    Chen, Minghao
    Zhao, Xiaoyan
    Zhang, Guangze
    Yan, Hongyi
    Fu, Kailong
    Journal of Railway Engineering Society, 2021, 38 (10): : 31 - 36
  • [48] Optimization of Capacity Utilization of High-Speed Railway Network
    Chen, Weilong
    Luo, Qin
    Li, Wei
    Gong, Lei
    2020 IEEE 5TH INTERNATIONAL CONFERENCE ON INTELLIGENT TRANSPORTATION ENGINEERING (IEEE ICITE 2020), 2020, : 224 - 228
  • [49] Characteristic Analysis of High-Speed Railway Network in China
    Guo, Dan
    Qin, Yong
    Wang, Li
    An, Min
    PROCEEDINGS OF THE 3RD INTERNATIONAL CONFERENCE ON ELECTRICAL AND INFORMATION TECHNOLOGIES FOR RAIL TRANSPORTATION (EITRT) 2017: TRANSPORTATION, 2018, 483 : 649 - 659
  • [50] Decoupled wireless network architecture for high-speed railway
    Yan, Li
    Fang, Xuming
    2013 INTERNATIONAL WORKSHOP ON HIGH MOBILITY WIRELESS COMMUNICATIONS (HMWC), 2013,