A preliminary study of the factors affecting the cost escalation of construction projects

被引:14
|
作者
Knight, K [1 ]
Fayek, A [1 ]
机构
[1] Univ Alberta, Dept Civil & Environm Engn, Edmonton, AB T6G 2G7, Canada
关键词
construction; costs; expert systems; fuzzy logic; project control; survey;
D O I
10.1139/cjce-27-1-73
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
An interview survey of Alberta-based construction contractors was conducted in July and August 1998. The purpose of this survey was to elicit information on the factors that cause unanticipated project cost escalation during construction, from the contractor's perspective. This paper presents the findings of this survey and a proposed method of modeling the factors identified. The majority of factors identified impact labour productivity, which is a major source of cost overruns. A combination of subjective, objective, and secondary indicators are used to measure these factors and to assess their impact on project performance. The main conclusion of this survey is that many of the factors affecting the cost of construction are evaluated in subjective and imprecise terms and are difficult to quantify. This paper presents a method of modeling these factors using fuzzy membership functions, which capture the imprecision and subjectivity associated with the measurement of these factors. It discusses a basis for the definition of these membership functions and a method of calibrating these functions to make them more widely applicable to suit different contexts. These membership functions are being incorporated in a set of expert rules, which reason about the factors affecting costs, their impact on the project, and the appropriate corrective actions. These expert rules are being developed as part of a fuzzy expert system for construction project monitoring and control. A method of calibrating membership functions to suit individual contexts is currently being developed, which would be a significant advancement in the area of fuzzy logic.
引用
收藏
页码:73 / 83
页数:11
相关论文
共 50 条
  • [31] Risk factors affecting the construction projects in the developing countries
    Bahamid, R. A.
    Doh, S., I
    Al-Sharaf, M. A.
    NATIONAL COLLOQUIUM ON WIND AND EARTHQUAKE ENGINEERING, 2019, 244
  • [32] Factors affecting the cost performance of transport infrastructure projects
    Moschouli, Eleni
    Soecipto, Raden Murwantara
    Vanelslander, Thierry
    Verhoest, Koen
    EUROPEAN JOURNAL OF TRANSPORT AND INFRASTRUCTURE RESEARCH, 2018, 18 (04): : 535 - 554
  • [33] COST ESCALATION, SCHEDULE OVERRUNS AND QUALITY SHORTFALLS ON CONSTRUCTION PROJECTS: THE CASE OF ZAMBIA
    Muya, Mundia
    Kaliba, Chabota
    Sichombo, Balimu
    Shakantu, Winston
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2013, 13 (01) : 53 - 68
  • [34] Study on Integrated Cost Management of Total Factors and Total Process in Construction Projects
    Li Nannan
    Li Qingli
    Zhang Jingtao
    PROCEEDINGS OF 2008 INTERNATIONAL CONFERENCE ON CONSTRUCTION & REAL ESTATE MANAGEMENT, VOLS 1 AND 2, 2008, : 132 - 135
  • [35] An analytical study of critical factors affecting contractor efficiency in construction projects in Indian scenario
    Deep, Shumank
    Simon, Laura
    Asim, Mohd
    Rahimzadeh, Ali
    Al-Hamdani, Sulala
    ORGANIZATION TECHNOLOGY AND MANAGEMENT IN CONSTRUCTION, 2018, 10 (01): : 1794 - 1802
  • [36] Factors affecting contractors' risk attitudes in construction projects: Case study from China
    Wang, Jiayuan
    Yuan, Hongping
    INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2011, 29 (02) : 209 - 219
  • [37] Critical cost factors of building construction projects in Malaysia
    Toh, Tien-Choon
    Ting, Connie
    Ali, Kherun-Nita
    Aliagha, Godwin-Uche
    Munir, Omar
    INTERNATIONAL CONFERENCE ON ASIA PACIFIC BUSINESS INNOVATION AND TECHNOLOGY MANAGEMENT, 2012, 57 : 360 - 367
  • [38] An exploration into cost-influencing factors on construction projects
    Cheng, Ying-Mei
    INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2014, 32 (05) : 850 - 860
  • [39] Inhibiting Factors of Cost Performance in UAE Construction Projects
    Alhammadi, Ahmed Salem Ahmed Marey
    Memon, Aftab Hameed
    INTERNATIONAL JOURNAL OF SUSTAINABLE CONSTRUCTION ENGINEERING AND TECHNOLOGY, 2020, 11 (02): : 126 - 132
  • [40] Modeling of Factors Affecting Worker Engagement in Construction Projects in Thailand
    Ngowtanasuwan, Grit
    PROCEEDINGS OF 6TH INTERNATIONAL CONFERENCE ON CIVIL ENGINEERING AND ARCHITECTURE, VOL 2, ICCEA 2023, 2024, 531 : 279 - 288