A preliminary study of the factors affecting the cost escalation of construction projects

被引:14
|
作者
Knight, K [1 ]
Fayek, A [1 ]
机构
[1] Univ Alberta, Dept Civil & Environm Engn, Edmonton, AB T6G 2G7, Canada
关键词
construction; costs; expert systems; fuzzy logic; project control; survey;
D O I
10.1139/cjce-27-1-73
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
An interview survey of Alberta-based construction contractors was conducted in July and August 1998. The purpose of this survey was to elicit information on the factors that cause unanticipated project cost escalation during construction, from the contractor's perspective. This paper presents the findings of this survey and a proposed method of modeling the factors identified. The majority of factors identified impact labour productivity, which is a major source of cost overruns. A combination of subjective, objective, and secondary indicators are used to measure these factors and to assess their impact on project performance. The main conclusion of this survey is that many of the factors affecting the cost of construction are evaluated in subjective and imprecise terms and are difficult to quantify. This paper presents a method of modeling these factors using fuzzy membership functions, which capture the imprecision and subjectivity associated with the measurement of these factors. It discusses a basis for the definition of these membership functions and a method of calibrating these functions to make them more widely applicable to suit different contexts. These membership functions are being incorporated in a set of expert rules, which reason about the factors affecting costs, their impact on the project, and the appropriate corrective actions. These expert rules are being developed as part of a fuzzy expert system for construction project monitoring and control. A method of calibrating membership functions to suit individual contexts is currently being developed, which would be a significant advancement in the area of fuzzy logic.
引用
收藏
页码:73 / 83
页数:11
相关论文
共 50 条
  • [21] A model for preliminary cost estimation in buildings construction projects
    Jassim, Hassanean S. H.
    Hasan, Musaab F.
    Altaee, Mohammed J.
    Gamil, Yaser
    FRONTIERS IN BUILT ENVIRONMENT, 2025, 11
  • [22] Preliminary Study on Causative Factors Leading to Construction Cost Overrun
    Memon, Aftab Hameed
    Rahman, Ismail Abdul
    Azis, Ade Asmi Abdul
    INTERNATIONAL JOURNAL OF SUSTAINABLE CONSTRUCTION ENGINEERING AND TECHNOLOGY, 2011, 2 (01): : 57 - 71
  • [23] A SURVEY OF THE FACTORS AFFECTING THE PRODUCTIVITY OF CONSTRUCTION PROJECTS IN IRAN
    Ghoddousi, Parviz
    Hosseini, Mohammad Reza
    TECHNOLOGICAL AND ECONOMIC DEVELOPMENT OF ECONOMY, 2012, 18 (01) : 99 - 116
  • [24] FACTORS AFFECTING THE PERFORMANCE OF CONSTRUCTION PROJECTS IN THE GAZA STRIP
    Enshassi, Adnan
    Mohamed, Sherif
    Abushaban, Saleh
    JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2009, 15 (03) : 269 - 280
  • [25] Critical factors affecting quality performance in construction projects
    Jha, K. N.
    Iyer, K. C.
    TOTAL QUALITY MANAGEMENT & BUSINESS EXCELLENCE, 2006, 17 (09) : 1155 - 1170
  • [26] Investigation to Factors Affecting IT Implementation in Chinese Construction Projects
    Wang Guangbin
    Cao Dongping
    Chong Dan
    PROCEEDINGS OF THE 4TH CONFERENCE ON SYSTEMS SCIENCE, MANAGEMENT SCIENCE AND SYSTEMS DYNAMICS, SSMSSD10, VOL 3, 2011, : 365 - 373
  • [27] Assessment of Cost Escalation factors for Building and Civil Engineering Projects in Nigerian Construction Industry: a Multiple Regression Approach
    Muhammad, Nasiru Zakari
    Keyvanfar, Ali
    Majid, Muhd Zaimi Abd
    Shafaghat, Arezou
    Magana, Aliyu Muhammad
    Lawan, Hasan
    Balubaid, Saeed
    JURNAL TEKNOLOGI, 2015, 74 (04): : 85 - 91
  • [28] Factors Affecting the Utilization of Big Data in Construction Projects
    Yu, Tao
    Liang, Xin
    Wang, Yaowu
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2020, 146 (05)
  • [29] Exploring the critical waste factors affecting construction projects
    Bajjou, Mohamed Saad
    Chafi, Anas
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2022, 29 (06) : 2268 - 2299
  • [30] Analysing factors affecting delays in Indian construction projects
    Doloi, Hemanta
    Sawhney, Anil
    Iyer, K. C.
    Rentala, Sameer
    INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2012, 30 (04) : 479 - 489