Predicting Project Cost Performance Level by Assessing Risk Factors of Building Construction in South Korea

被引:11
|
作者
Cha, Hee Sung [1 ]
Shin, Kang Yong [1 ]
机构
[1] Ajou Univ, Dept Architectural Engn, Suwon 443749, South Korea
基金
新加坡国家研究基金会;
关键词
building project; cost performance; quantitative analysis; risk assessment;
D O I
10.3130/jaabe.10.437
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
There exists a strong relationship between the level of planning effort and overall project performance. Project stakeholders are concerned about various project objectives among which cost performance has long been regarded as one of the most crucial. Recognizing the lack of a systematic approach in assessing building project risk in association with cost performance prediction, this study identified 49 risk factors from various sources and quantified the relative impact of each factor. By normalizing these values, a Project Risk Score (PRS) has been developed for the purpose of predicting cost performance on a particular project. The 13 real case studies showed a statistically significant relationship between the PRS and cost performance. Predicting cost performance is not simple. Project managers must consider not only factors that are innate to the project, but also project-independent circumstances. This study provides straightforward guidance in assessing a particular project in order to recognize the level of cost performance before project execution. This risk-based performance prediction can improve early-stage project evaluation and enhances the possibility of achieving a sustainable business in a challenging environment.
引用
收藏
页码:437 / 444
页数:8
相关论文
共 50 条
  • [41] Prevalence and risk factors for bovine tuberculosis in South Korea
    Ok, Y. S.
    Jang, Y. H.
    Kim, T. W.
    Jeong, M. K.
    Hyun, B. H.
    Kim, J. M.
    INTERNATIONAL JOURNAL OF ANTIMICROBIAL AGENTS, 2017, 50 : S164 - S165
  • [42] Assessing the Risk Level of the Challenges Faced In Construction Projects
    Alameri, Abdulla
    Alhammadi, Ahmed S. A. Marey
    Memon, Aftab Hameed
    Rahman, Ismail Abdul
    Nasaruddin, Nur Ain Ngah
    ENGINEERING TECHNOLOGY & APPLIED SCIENCE RESEARCH, 2021, 11 (03) : 7152 - 7157
  • [43] Factors Determining e-Trade Performance Based on Transaction Cost Theory: The Case of South Korea
    Kim, Hag-Min
    Lee, Ho-Hyung
    JOURNAL OF KOREA TRADE, 2009, 13 (01): : 21 - 44
  • [44] Construction project management through building contracts, a South African perspective
    du Plessis, Hendri
    Oosthuizen, Pierre
    ACTA STRUCTILIA, 2018, 25 (01) : 152 - 181
  • [45] Factors constraining successful building project implementation in South Africa
    Mbachu, Jasper
    Nkado, Raymond
    CONSTRUCTION MANAGEMENT AND ECONOMICS, 2007, 25 (01) : 39 - 54
  • [46] Categorization of potential project cost overrun factors in construction industry
    Karunakaran, P.
    Abdullah, A. H.
    Nagapan, S.
    Sohu, S.
    Kasvar, K. K.
    4TH INTERNATIONAL CONFERENCE ON CIVIL AND ENVIRONMENTAL ENGINEERING FOR SUSTAINABILITY (ICONCEES 2017), 2018, 140
  • [47] Building worker power for day laborers in South Korea's construction industry
    Yi, Sohoon
    Chun, Jennifer Jihye
    INTERNATIONAL JOURNAL OF COMPARATIVE SOCIOLOGY, 2020, 61 (2-3) : 122 - 140
  • [48] Factors Affecting the Accuracy of Construction Project Cost Estimation in Egypt
    Ibrahim, Ahmed H.
    Elshwadfy, Lamiaa M.
    JORDAN JOURNAL OF CIVIL ENGINEERING, 2021, 15 (03) : 329 - 344
  • [49] Work rate modeling of building construction projects using system dynamic to optimize project cost and time performance
    Rachmawati, Farida
    Mudjahidin, Mudjahidin
    Widowati, Elok Dewi
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2024, 24 (02) : 213 - 225
  • [50] Critical Factors Driving Construction Project Performance in Integrated 5D Building Information Modeling
    Sun, Hui
    Khoo, Terh Jing
    Esa, Muneera
    Mahdiyar, Amir
    Li, Jiguang
    BUILDINGS, 2024, 14 (09)