Multimode resource-constrained project scheduling in flexible projects

被引:13
|
作者
Kosztyan, Zsolt T. [1 ]
Szalkai, Istvan [2 ]
机构
[1] Univ Pannonia, Fac Business & Econ, Dept Quantitat Methods, Egyet Str 10, Veszprem, Hungary
[2] Univ Pannonia, Fac Informat Technol, Dept Math, Egyet Str 10, Veszprem, Hungary
关键词
Multimode resource-constrained project scheduling problem; Flexible project management approaches; Matrix-based project planning; COST TRADEOFF PROBLEM; DISCRETE-TIME; OFF PROBLEMS; QUALITY; MODELS; AGILE;
D O I
10.1007/s10898-019-00832-8
中图分类号
C93 [管理学]; O22 [运筹学];
学科分类号
070105 ; 12 ; 1201 ; 1202 ; 120202 ;
摘要
Flexible agile and extreme project management methods have become increasingly popular among practitioners, particularly in the IT and R&D sectors. In contrast to the theoretically and algorithmically well-established and developed trade-off and multimode methods applied in traditional project management methods, flexible project scheduling methods, which are applied in agile, hybrid, and especially extreme project management, lack a principled foundation and algorithmic handling. The aim of this paper is to fill this gap. We propose a matrix-based method that provides scores for alternative project plans that host flexible task dependencies and undecided, supplementary task completion while also handling the new but unplanned tasks. In addition, traditional multimode resource-constrained project scheduling problems are also covered. The proposed method can bridge the flexible and traditional approaches.
引用
收藏
页码:211 / 241
页数:31
相关论文
共 50 条
  • [31] Closure to "Ant Colony Optimization for Multimode Resource-Constrained Project Scheduling" by Hong Zhang
    Zhang, Hong
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2014, 30 (03)
  • [32] Control Risk for Multimode Resource-Constrained Project Scheduling Problems under Hybrid Uncertainty
    Gan, Lu
    Xu, Jiuping
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2015, 31 (03)
  • [33] Solving Multimode Resource-Constrained Project Scheduling Problems Using an Organizational Evolutionary Algorithm
    Wang, Lixia
    Liu, Jing
    PROCEEDINGS OF THE 18TH ASIA PACIFIC SYMPOSIUM ON INTELLIGENT AND EVOLUTIONARY SYSTEMS, VOL 1, 2015, : 271 - 283
  • [34] A branch-and-cut procedure for the multimode resource-constrained project-scheduling problem
    Zhu, Guidong
    Bard, Jonathan F.
    Yu, Gang
    INFORMS JOURNAL ON COMPUTING, 2006, 18 (03) : 377 - 390
  • [35] Some new concepts of setup costs in multimode resource-constrained project scheduling problem
    Mika, Marek
    Rozycki, Rafal
    Waligora, Grzegorz
    2012 17TH INTERNATIONAL CONFERENCE ON METHODS AND MODELS IN AUTOMATION AND ROBOTICS (MMAR), 2012, : 470 - 474
  • [36] Resource-constrained project scheduling - Minimization of project duration
    不详
    PROJECT SCHEDULING WITH TIME WINDOWS AND SCARCE RESOURCES, 2002, 508 : 21 - 174
  • [37] Resource-constrained project scheduling problem with reworking
    Liao Y.
    Lu Z.
    Jisuanji Jicheng Zhizao Xitong/Computer Integrated Manufacturing Systems, CIMS, 2019, 25 (11): : 2762 - 2774
  • [38] Disruption management for resource-constrained project scheduling
    Zhu, G
    Bard, JF
    Yu, G
    JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 2005, 56 (04) : 365 - 381
  • [39] An Extended CPM for Resource-constrained Project Scheduling
    Ju, C. H.
    Xie, Y.
    ULTRA-PRECISION MACHINING TECHNOLOGIES, 2009, 69-70 : 695 - 699
  • [40] A Practical Approach for Resource-Constrained Project Scheduling
    Manousakis, Konstantinos
    Savva, Giannis
    Papadouri, Nicos
    Mavrovouniotis, Michalis
    Christofides, Athanasios
    Kolokotroni, Nedi
    Ellinas, Georgios
    IEEE ACCESS, 2024, 12 : 12976 - 12991