In this paper a mixed-integer hydro electric power model for short-term planning is discussed. The purpose of the model is to represent the generation characteristic of the Hydro plants accurately. In the modelling part the paper focuses on two requests stated from power producers in an earlier study. First, it is desirable to operate on points with good efficiency. Second, start-ups and shut-downs of the units should not be carried out too often, since this is related to a cost. The problem is decomposed into a subproblem for each hydro power plant by relaxing the power balance equation and using variable splitting, The advantage of this relaxation is that we can use network programming and dynamic programming methods, which have proved to work well for power system planning issues. The relaxation used in this work has, as far as we know, not been applied in the field before. The master problem is solved by a subgradient technique, Finally, a numerical example from a part of the Swedish power system illustrates the technique.
引用
收藏
页码:770 / 775
页数:6
相关论文
共 50 条
  • [21] Scheduling Divisible Loads on Bus Networks with Start-Up Costs by Utilizing Multiple Data Transfer Streams: PORI
    Hu, Jie
    Klefstad, Raymond
    2007 INTERNATIONAL CONFERENCE ON PARALLEL PROCESSING WORKSHOPS (ICPP), 2007, : 188 - 195
  • [22] Incorporating operational characteristics and start-up costs in option-based valuation of power generation capacity
    Deng, SJ
    Oren, SS
    PROBABILITY IN THE ENGINEERING AND INFORMATIONAL SCIENCES, 2003, 17 (02) : 155 - 181
  • [23] Start-up and brake regimes of electric motors in case of repeated and short-term operation
    Egorov, S.V.
    Egorov, V.F.
    Kuninin, P.N.
    Izvestiya Ferrous Metallurgy, 2003, (01): : 67 - 69
  • [24] The short- and long-term effects of formic acid on rapid nitritation start-up
    Wang, Ji-peng
    Liu, Yong-di
    Meng, Fan-gang
    Li, Wei
    ENVIRONMENT INTERNATIONAL, 2020, 135
  • [25] Application of a Fast Evolutionary Algorithm to Short-term Hydro-thermal Generation Scheduling
    Turkay, B.
    Mecitoglu, F.
    Baran, S.
    ENERGY SOURCES PART B-ECONOMICS PLANNING AND POLICY, 2011, 6 (04) : 395 - 405
  • [26] A successive approximation approach for short-term cascaded hydro scheduling with variable water flow delay
    Ge, Xiaolin
    Xia, Shu
    Lee, Wei-Jen
    Chung, C. Y.
    ELECTRIC POWER SYSTEMS RESEARCH, 2018, 154 : 213 - 222
  • [27] A Computationally Efficient Formulation to Accurately Represent Start-Up Costs in the Medium-Term Unit Commitment Problem
    Montero, Luis
    Bello, Antonio
    Reneses, Javier
    Rodriguez, Manuel
    IEEE TRANSACTIONS ON POWER SYSTEMS, 2023, 38 (06) : 5623 - 5634
  • [28] Integer modelling of spinning reserve requirements in short term scheduling of hydro systems: An application to power trading
    Nilsson, O
    Soder, L
    FOURTH INTERNATIONAL CONFERENCE ON ADVANCES IN POWER SYSTEM CONTROL, OPERATION & MANAGEMENT, VOLS 1 AND 2, 1997, : 139 - 144
  • [29] An Energy-Efficient Start-Up Strategy for Large Variable Speed Hydro Pump Turbine Equipped with Doubly Fed Asynchronous Machine
    Singh, Rassiah Raja
    Baranidharan, Manickavel
    Subramaniam, Umashankar
    Bhaskar, Mahajan Sagar
    Rangarajan, Shriram S.
    Abdelsalam, Hany A.
    Collins, Edward Randolph
    Senjyu, Tomonobu
    ENERGIES, 2022, 15 (09)
  • [30] Domain Partition of the Hydro Production Function for Solving Efficiently the Short-Term Generation Scheduling Problem
    Brito, Brunno H.
    Finardi, Erlon C.
    Takigawa, Fabricio Y. K.
    Nogueira, Pierry L. R.
    Morais, Douglas T. S. A.
    Fernandes, Argemiro
    IEEE ACCESS, 2021, 9 : 152780 - 152791