An Assignment-Based Continuous-Time MILP Model for the Resource-Constrained Project Scheduling Problem

被引:0
|
作者
Rihm, Tom [1 ]
Trautmann, Norbert [1 ]
机构
[1] Univ Bern, Dept Business Adm, Schuetzenmattstr 14, CH-3012 Bern, Switzerland
关键词
Mixed-Integer Linear Programming; Operations Research; Project Management; Resource-Constrained Project Scheduling; LIMITED RESOURCES; FORMULATION;
D O I
暂无
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
The widely studied resource-constrained project scheduling problem consists of determining the start times for a set of precedence-related project activities requiring time and scarce resources during execution such that the total project duration is minimized. In the literature, in addition to a large variety of specific solution approaches, various mixed-integer linear programming (MILP) models have been proposed for this problem. We present a novel MILP model that is based on explicit assignment and sequencing variables; we enhance the performance of the model by eliminating some symmetric solutions from the search space and by modifying the sequencing constraints for pairs of activities that cannot be processed in parallel. Our computational results for four standard test sets from the literature indicate that this novel model outperforms two state-of-the-art models, particularly when resources are very scarce.
引用
收藏
页码:35 / 39
页数:5
相关论文
共 50 条
  • [21] Multidirectional Scheduling Scheme in Resource-Constrained Project Scheduling Problem
    Yoosefzadeh, Hamid R.
    Tareghian, Hamed R.
    Farahi, Mohammad H.
    NAVAL RESEARCH LOGISTICS, 2014, 61 (01) : 44 - 55
  • [22] Flexible resource-constrained resource leveling project scheduling problem
    Yu, Xiao-Guang
    Zhan, De-Chen
    Nie, Lan-Shun
    Chu, Dian-Hui
    Xu, Xiao-Fei
    Jisuanji Jicheng Zhizao Xitong/Computer Integrated Manufacturing Systems, CIMS, 2010, 16 (09): : 1967 - 1976
  • [23] A Neurogenetic approach for the resource-constrained project scheduling problem
    Agarwal, Anurag
    Colak, Selcuk
    Erenguc, Selcuk
    COMPUTERS & OPERATIONS RESEARCH, 2011, 38 (01) : 44 - 50
  • [24] Genetic algorithm for the resource-constrained project scheduling problem
    E. N. Goncharov
    V. V. Leonov
    Automation and Remote Control, 2017, 78 : 1101 - 1114
  • [25] The proactive and reactive resource-constrained project scheduling problem
    Morteza Davari
    Erik Demeulemeester
    Journal of Scheduling, 2019, 22 : 211 - 237
  • [26] Periodically aggregated resource-constrained project scheduling problem
    Morin, Pierre-Antoine
    Artigues, Christian
    Hait, Alain
    EUROPEAN JOURNAL OF INDUSTRIAL ENGINEERING, 2017, 11 (06) : 792 - 817
  • [27] Integration of routing into a resource-constrained project scheduling problem
    Lacomme, Philippe
    Moukrim, Aziz
    Quilliot, Alain
    Vinot, Marina
    EURO JOURNAL ON COMPUTATIONAL OPTIMIZATION, 2019, 7 (04) : 421 - 464
  • [28] Memetic algorithm for the resource-constrained project scheduling problem
    Chen, Di
    Liu, Shixin
    Qin, Shujin
    2014 11TH WORLD CONGRESS ON INTELLIGENT CONTROL AND AUTOMATION (WCICA), 2014, : 4991 - 4996
  • [29] Resource-Constrained Project Scheduling Problem with Modified PSO
    Zhang, Kai
    Jiang, Jing
    Zhao, Guo-rong
    ICMS2010: PROCEEDINGS OF THE THIRD INTERNATIONAL CONFERENCE ON MODELLING AND SIMULATION, VOL 6: MODELLING & SIMULATION INDUSTRIAL ENGINEERING & MANAGEMENT, 2010, : 308 - 311
  • [30] An evolution programme for the resource-constrained project scheduling problem
    Cheng, RW
    Gen, M
    INTERNATIONAL JOURNAL OF COMPUTER INTEGRATED MANUFACTURING, 1998, 11 (03) : 274 - 287