An Assignment-Based Continuous-Time MILP Model for the Resource-Constrained Project Scheduling Problem

被引:0
|
作者
Rihm, Tom [1 ]
Trautmann, Norbert [1 ]
机构
[1] Univ Bern, Dept Business Adm, Schuetzenmattstr 14, CH-3012 Bern, Switzerland
关键词
Mixed-Integer Linear Programming; Operations Research; Project Management; Resource-Constrained Project Scheduling; LIMITED RESOURCES; FORMULATION;
D O I
暂无
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
The widely studied resource-constrained project scheduling problem consists of determining the start times for a set of precedence-related project activities requiring time and scarce resources during execution such that the total project duration is minimized. In the literature, in addition to a large variety of specific solution approaches, various mixed-integer linear programming (MILP) models have been proposed for this problem. We present a novel MILP model that is based on explicit assignment and sequencing variables; we enhance the performance of the model by eliminating some symmetric solutions from the search space and by modifying the sequencing constraints for pairs of activities that cannot be processed in parallel. Our computational results for four standard test sets from the literature indicate that this novel model outperforms two state-of-the-art models, particularly when resources are very scarce.
引用
收藏
页码:35 / 39
页数:5
相关论文
共 50 条
  • [1] Two continuous-time assignment-based models for the multi-mode resource-constrained project scheduling problem
    Gnaegi, Mario
    Rihm, Tom
    Zimmermann, Adrian
    Trautmann, Norbert
    COMPUTERS & INDUSTRIAL ENGINEERING, 2019, 129 : 346 - 353
  • [2] A Continuous-Time Unit-Based MILP Formulation for the Resource-Constrained Project Scheduling Problem
    Gnagi, M.
    Zimmermann, A.
    Trautmann, N.
    2018 IEEE INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND ENGINEERING MANAGEMENT (IEEE IEEM), 2018, : 432 - 436
  • [3] A Continuous-Time MILP Formulation for the Multi-Mode Resource-Constrained Project Scheduling Problem
    Gnagi, M.
    Rihm, T.
    Trautmann, N.
    2018 IEEE INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND ENGINEERING MANAGEMENT (IEEE IEEM), 2018, : 452 - 456
  • [4] MILP Formulation for Resource-Constrained Project Scheduling Problems
    Kyriakidis, Thomas S.
    Kopanos, Georgios M.
    Georgiadis, Michael C.
    21ST EUROPEAN SYMPOSIUM ON COMPUTER AIDED PROCESS ENGINEERING, 2011, 29 : 880 - 884
  • [5] Resource-constrained project scheduling with flexible resource profiles in continuous time
    Naber, Anulark
    COMPUTERS & OPERATIONS RESEARCH, 2017, 84 : 33 - 45
  • [6] An MILP continuous-time approach to short-term scheduling of resource-constrained multistage flowshop batch facilities
    Méndez, CA
    Henning, GP
    Cerdá, J
    COMPUTERS & CHEMICAL ENGINEERING, 2001, 25 (4-6) : 701 - 711
  • [7] Algorithm for Resource-constrained Project Scheduling Problem With Resource Transfer Time
    Lu Z.-Q.
    Liu X.-Y.
    Lu, Zhi-Qiang (zhiqianglu@tongji.edu.cn), 2018, Science Press (44): : 1028 - 1036
  • [8] Event-based MILP models for resource-constrained project scheduling problems
    Kone, Oumar
    Artigues, Christian
    Lopez, Pierre
    Mongeau, Marcel
    COMPUTERS & OPERATIONS RESEARCH, 2011, 38 (01) : 3 - 13
  • [9] New continuous-time and discrete-time mathematical formulations for resource-constrained project scheduling problems
    Kopanos, Georgios M.
    Kyriakidis, Thomas S.
    Georgiadis, Michael C.
    COMPUTERS & CHEMICAL ENGINEERING, 2014, 68 : 96 - 106
  • [10] Resource-constrained project scheduling problem with reworking
    Liao Y.
    Lu Z.
    Jisuanji Jicheng Zhizao Xitong/Computer Integrated Manufacturing Systems, CIMS, 2019, 25 (11): : 2762 - 2774