Need for Alternative Research Approaches in Construction Management: Case of Delay Studies

被引:82
|
作者
AlSehaimi, Abdullah [1 ]
Koskela, Lauri [2 ]
Tzortzopoulos, Patricia [2 ]
机构
[1] Minist Hlth, Medinah, Saudi Arabia
[2] Univ Salford, Sch Built Environm, Salford M5 4WT, Lancs, England
基金
英国工程与自然科学研究理事会;
关键词
Construction delay; Action research; Constructive research; DESIGN SCIENCE; DISPUTES;
D O I
10.1061/(ASCE)ME.1943-5479.0000148
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Over the years, there have been many studies of delay in construction, and this type of study continues to be popular in construction management research. A synthesis and critical evaluation of delay studies in developing countries reveals that poor project management is cited as one of the main causes of delay. However, despite significant consensus, most published studies fall short of providing clear recommendations for the improvement of project management practice. Moreover, the majority of recommendations are general and not devoted to solving the difficulties associated with particular causes of delay. This paper aims to demonstrate that the root cause of this state of affairs is that typical research into delay tends to be descriptive and explanatory, making it inadequate for solving persistent managerial problems in construction. It is contended that many problems in construction could be mitigated through alternative research approaches, i.e.,action and constructive research. Such prescriptive research methods can assist in the development and implementation of innovative tools tackling managerial problems of construction, including that of delay. In so doing, those methods will better connect research and practice, and thus strengthen the relevance of academic construction management. (C) 2013 American Society of Civil Engineers.
引用
收藏
页码:407 / 413
页数:7
相关论文
共 50 条
  • [41] The Need for Research in "Contingency Studies"
    Hammer, Brad
    COLLEGE COMPOSITION AND COMMUNICATION, 2010, 62 (01) : A1 - A3
  • [42] Approaches to Construction Waste Management in Malaysia
    Mydin, M. A. Othuman
    Khor, J. C.
    Sani, N. Md.
    ADVANCED GREEN MATERIAL AND TECHNOLOGY SYMPOSIUM (AGMTS 2014), 2014, 17
  • [43] Alternative delivery approaches for military medical construction projects
    ASCE
    不详
    不详
    J Archit Eng, 4 (149-155):
  • [44] Comparison of project management approaches in construction
    李百毅
    郑敏
    李百战
    AUSTIN S
    THORPE T
    Journal of Central South University, 2009, 16 (S1) : 100 - 104
  • [45] Comparison of project management approaches in construction
    Li Bai-yi
    Zheng Min
    Li Bai-zhan
    Austin, S.
    Thorpe, T.
    JOURNAL OF CENTRAL SOUTH UNIVERSITY OF TECHNOLOGY, 2009, 16 : 100 - 104
  • [46] Case studies as an option for empirical research in operations management
    Csillag, Joao Mario
    Martins, Ricardo
    Mendes Primo, Marcos Andre
    RAE-REVISTA DE ADMINISTRACAO DE EMPRESAS, 2012, 52 (04): : 380 - 385
  • [47] Disaster risk management approaches in construction and built environment A research collaboration networks perspective
    Taba, Seyedamir Tavakoli
    Mojtahedi, Mohammad
    Newton, Sidney
    INTERNATIONAL JOURNAL OF DISASTER RESILIENCE IN THE BUILT ENVIRONMENT, 2019, 11 (01) : 85 - 99
  • [48] Linking research and management: Conceptual designs and case studies
    Morrison, ML
    Block, WM
    Hall, LS
    Christoferson, LL
    Martin, JA
    TRANSACTIONS OF THE SIXTY-FIRST NORTH AMERICAN WILDLIFE AND NATURAL RESOURCES CONFERENCE, 1996, : 463 - 471
  • [49] CASE STUDIES AND MANAGEMENT ACCOUNTING RESEARCH: EPISTEMOLOGIAL CONSIDERATIONS
    Makrygiannakis, Georgios
    GLOBAL AND NATIONAL BUSINESS THEORIES AND PRACTICE: BRIDGING THE PAST WITH THE FUTURE, 2017, : 907 - 917
  • [50] The need for integrated approaches to environmental data management
    Harmancioglu, NB
    INTEGRATED APPROACH TO ENVIRONMENTAL DATA MANAGEMENT SYSTEMS, 1997, 31 : 3 - 14